Komori
Dreambed (7791) · InitiativeAdvanced

Improved production capacity and efficiency through the redevelopment of the Yachiyo No. 1 Plant

First written in FY2021. 12 of 13 entries say "Advanced", first in FY2022-Q1. Latest entry: FY2025.

13entries
5years
0from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseAdvancedFY2022-Q1 – FY20252021: 220212022: 420222023: 420232024: 220242025: 12025
Same theme, other companies
Increasing production capacity and efficiency through redevelopment of the Yachiyo First PlantA theme 1 companies write about · 0 as a headwind · 1 as a tailwind

No other company in this theme has enough history to compare yet.

Full recordFilings, disclosures and news, newest first
  1. FY2025AdvancedAnnual report

    「Through the automated material handling and supply equipment that began operating at the new plant in 2024, we will pursue further efficiency gains. By also investing in the introduction of new equipment, we will establish a system capable of handling future increases in orders.」

    Following the redevelopment of the Yachiyo No. 1 Plant, the company is pursuing production efficiency improvements and preparing to handle increased orders through the operation of automated material handling and supply equipment and new equipment investment.
  2. FY2024AdvancedAnnual report

    「Construction of the completed sewing building at the new plant was completed in December 2023, and it began operations in January 2024.」

    As part of the redevelopment of the Yachiyo No. 1 Plant, construction of the completed sewing building was completed and operations began in January 2024. Capital expenditure included ¥1,393.314 million for the building and ¥98.360 million for structures.
  3. FY2024-Q3AdvancedAnnual report

    「In the same month, construction of the completed sewing building at the new plant was completed, and it began operations in January.」

    As part of the redevelopment of the Yachiyo No. 1 Plant, construction of the completed sewing building was completed in December 2023, and the building began operations in January 2024.
  4. FY2024-Q2AdvancedAnnual report

    「Property, plant and equipment amounted to ¥6,188.720 million, an increase of ¥581.470 million from the end of the previous fiscal year. This was mainly attributable to an increase of ¥574.112 million in construction in progress and an increase of ¥82.850 million in other assets under investments and other assets. The main reason for the increase in construction in progress was the ¥507.870 million related to the rebuilding of the Yachiyo No. 1 Plant.」

    Construction in progress related to the rebuilding of the Yachiyo No. 1 Plant increased, and investment in its redevelopment continued.
  5. FY2024-Q1AdvancedAnnual report

    「The main reason for the decrease in cash and deposits was the allocation of ¥507.870 million to the rebuilding of the Yachiyo No. 1 Plant. Meanwhile, property, plant and equipment amounted to ¥6,197.307 million, an increase of ¥590.057 million from the end of the previous fiscal year. This was mainly attributable to an increase of ¥540.941 million in construction in progress and an increase of ¥83.518 million in other assets under investments and other assets. The main reason for the increase in construction in progress was the ¥507.870 million related to the rebuilding of the Yachiyo No. 1 Plant.」

    During the first quarter, ¥507.870 million was allocated to rebuilding the Yachiyo No. 1 Plant, while construction in progress increased by ¥540.941 million, indicating that investment in the redevelopment continued.
  6. FY2023AdvancedAnnual report

    「The main item in production equipment was ¥1,750.218 million in capital expenditure related to the construction and expansion of the Yachiyo No. 1 Plant, completed in December 2022.」

    The construction and expansion of the Yachiyo No. 1 Plant was completed in December 2022, with ¥1,750.218 million invested in equipment. Further investment plans remain for the next phase, including the completed sewing building.
  7. FY2023-Q3AdvancedAnnual report

    「In December of the same year, we began work on the completed sewing building as the next phase of construction of the new plant, preparing for increased production to meet demand from the hotel industry, where signs of recovery had begun to emerge.」

    At the Yachiyo No. 1 Plant, the pocket coiling equipment and the construction and expansion of buildings were completed in October 2022. In December, work began on the completed sewing building, scheduled to begin operations in January 2024, advancing the expansion of production capacity to the next stage.
  8. FY2023-Q2AdvancedAnnual report

    「Property, plant and equipment amounted to ¥4,608.282 million, an increase of ¥691.994 million from the end of the previous fiscal year. This was mainly attributable to an increase of ¥657.286 million in construction in progress and an increase of ¥24.955 million in other assets under investments and other assets. The main reason for the increase in construction in progress was the ¥511.434 million related to the construction and expansion of the Yachiyo No. 1 Plant.」

    Construction in progress related to the construction and expansion of the Yachiyo No. 1 Plant increased, and investment in the plant redevelopment is continuing.
  9. FY2023-Q1AdvancedAnnual report

    「The main reason for the decrease in cash and deposits was the allocation of ¥511.434 million to the construction and expansion of the Yachiyo No. 1 Plant. Property, plant and equipment amounted to ¥4,483.831 million, an increase of ¥567.543 million from the end of the previous fiscal year. This was mainly attributable to an increase of ¥570.078 million in construction in progress and an increase of ¥25.469 million in other assets. The main reason for the increase in construction in progress was the ¥511.434 million related to the construction and expansion of the Yachiyo No. 1 Plant.」

    During the first quarter, ¥511.434 million was allocated to the construction and expansion of the Yachiyo No. 1 Plant, resulting in an increase in construction in progress.
  10. FY2022AdvancedAnnual report

    「In addition, ¥511.434 million in construction in progress was invested in the construction and expansion of the Yachiyo No. 1 Plant.」

    Investment in construction in progress for the Yachiyo No. 1 Plant is progressing. The company disclosed a plan scheduled for completion in January 2023 and a 30% increase in capacity after completion.
  11. FY2022-Q3AdvancedAnnual report

    「This was mainly attributable to an increase of ¥101.798 million in land and an increase of ¥481.761 million in construction in progress. Of the increase in land, the entire amount, and of the increase in construction in progress, ¥511.434 million, was attributable to the construction and expansion of the Yachiyo No. 1 Plant.」

    Land and construction in progress increased in connection with the construction and expansion of the Yachiyo No. 1 Plant, indicating that the plant redevelopment is progressing.
  12. FY2022-Q1AdvancedAnnual report

    「The following major facilities were completed during the cumulative first quarter.」

    Pocket coiling equipment was completed at the Yachiyo No. 1 Plant in June 2021. The disclosure does not indicate that the redevelopment of the entire plant or the production capacity enhancement plan has been completed.
  13. FY2021First statedAnnual report

    「Using the funds raised at the time of listing, we will rebuild the Yachiyo No. 1 Plant, consolidate multiple production lines previously operated in separate buildings into a single building, and replace the plant's equipment, thereby seeking to increase production capacity and improve production efficiency.」

    The company plans to construct and expand plant buildings, consolidate production lines and renew equipment. Its equipment plan indicates that capacity will increase by 30% after completion.
Moved together

"Investment of Funds Raised Through Listing in Yachiyo No. 1 Factory" moved the same way as this thread, in the same document, in 10 of its 13 moves.

1098766★123456
  1. ★This thread
  2. 1Investment of Funds Raised Through Listing in Yachiyo No. 1 Factory10×
  3. 2Stable Dividend Policy Prioritizing Retained Earnings9×
  4. 3Increasing awareness of the Serta brand8×
  5. 4Slowdown in Hotel Demand Due to COVID-197×
  6. 5Serta’s Digital and Experiential Marketing and Authorized E-Commerce6×
  7. 6Converting the Tokyo Showroom into a Flagship Store6×

★ is this thread; numbers match the list above. The number on a line is how many documents both moved the same way in; lines between the other threads count the documents they moved together in too. Threads that move together often sit closer.

When this could move next
No upcoming earnings preview for Dreambed yet.
News
No news is linked to this thread yet. When an article touches it, it will appear here by date.
Improved production capacity and efficiency through the redevelopment of the Yachiyo No. 1 Plant | DREAMBED CO.,LTD. (7791) | Komori