Construction of a second factory and capital investment for new projects
First written in FY2023. 10 of 12 entries say "Advanced", first in FY2024-Q2. Latest entry: FY2026.
No other company in this theme has enough history to compare yet.
- FY2026AdvancedAnnual report
「Company submitting the filing Head Office Plant No. 2 Production equipment, inspection equipment and other items 2,575,000 886,346 Internal funds and borrowings August 2025 April 2027 Company submitting the filing Head Office Plant Buildings A/B Production equipment, inspection equipment and other items 2,446,000 1,130,813 Internal funds and borrowings August 2025 June 2027」
Even after completion of Building B, the Group has developed concrete plans for ¥5,021 million in new production equipment, inspection equipment and other items at Head Office Plant No. 2 and Head Office Plant Buildings A/B. - FY2026-H1AdvancedAnnual report
「Cash used in investing activities during the interim accounting period was ¥1,272,384 thousand, compared with ¥833,890 thousand used in the same period of the previous year. The main factor was ¥1,254,877 thousand in expenditure for the acquisition of property, plant and equipment.」
Capital investment continued for the new plant and mass production of the new material, with expenditure for the acquisition of property, plant and equipment totaling ¥1,254,877 thousand. - FY2025AdvancedAnnual report
「Total capital investment during the current fiscal year was ¥1,779,872 thousand, including construction in progress. The main investments were the new plant and production equipment for mass production of aircraft engine components other than those for LEAP engines.」
Even after Building B was completed, the company invested ¥1,779,872 thousand to prepare facilities and production capacity for components other than LEAP engine components. - FY2025-H1RestatedAnnual report
「With respect to new mass-production projects, we are currently establishing a mass-production structure for aircraft engine components scheduled to be produced at the new plant completed in June 2024.」
The new plant has been completed, and the company continues establishing a mass-production structure for aircraft engine components. Completion of the start of mass production was not reported. - FY2024AdvancedAnnual report
「June 2024: New plant Building B completed on the head-office plant premises」
Building B for mass production of new aircraft engine components was completed. Total capital investment was ¥1,756,983 thousand, and preparations continued for mass production to begin during the following fiscal year. - FY2024-Q3AdvancedAnnual report
「The main factors were a ¥186,968 thousand increase in cash and deposits associated with quarterly net income and the issuance of new shares through the stock listing, and a ¥918,046 thousand increase in property, plant and equipment. The main reason for the increase in property, plant and equipment was construction of a new plant and capital investment for mass production of aircraft engine components other than titanium-aluminide blades.」
Construction of the new plant and capital investment for mass production of aircraft engine components other than titanium-aluminide blades increased property, plant and equipment by ¥918,046 thousand. Mass production was scheduled to begin during the following fiscal year. - FY2024-Q2AdvancedAnnual report
「Construction of a new plant and development of mass-production technology for new mass-production projects involving aircraft engine components other than titanium-aluminide blades, for which orders are expected, progressed generally as planned.」
Construction of the new plant and development of mass-production technology for new projects progressed generally as planned. Completion of construction or the start of mass production was not reported. - FY2023First statedAnnual report
「To respond to expected new processing projects for aircraft engine components, we plan to construct the following new plant on the head-office plant premises and invest in new equipment.」
The plan for the second plant at the head-office site involved total planned investment of ¥1,883,000 thousand, beginning in July 2023 and scheduled for completion in June 2024, funded by internal funds and equity financing.