Construction of new electronic component manufacturing equipment at the Aso Facility
First written in FY2020-Q3. 2 of 5 entries say "Reframed", first in FY2020. Latest entry: FY2023.
No other company in this theme has enough history to compare yet.
- FY2023AdvancedAnnual report
「Aso Plant Electronic components Electronic component manufacturing equipment 899 554 14 180 — 159 1,809」
For the Aso Plant electronic component manufacturing equipment, total carrying value of ¥1,809 million is disclosed, indicating progress in the development of the equipment. - FY2022AdvancedAnnual report
「Aso Plant Electronic component manufacturing equipment ¥131 million」
For the Aso Plant, an increase of ¥131 million in electronic component manufacturing equipment during the fiscal year is disclosed, indicating progress on the equipment development related to the plan. - FY2021ReframedAnnual report
「Filing company | Aso Plant | Kumamoto Prefecture | Aso District | Nishihara Village | Electronic components | Electronic component manufacturing equipment | 607 | — | Internal funds and borrowings | February 2021 | January 2022 | 15%」
The Aso Plant equipment plan is disclosed as a new plan, with the investment amount, commencement timing, and post-completion capacity increase changed from the previous plan. - FY2020ReframedAnnual report
「Reporting company Aso Plant Kumamoto Prefecture Aso District Nishihara Village Electronic components Manufacturing equipment for electronic components 670 — Internal funds and borrowings February 2020 January 2021 10%」
The Aso Plant capital investment plan is disclosed as changed from total investment of ¥500 million, a capacity increase of 35%, and work commencing in November 2019 to total investment of ¥670 million, a capacity increase of 10%, and work commencing in February 2020. - FY2020-Q3First statedAnnual report
「Reporting company Aso Plant Kumamoto Prefecture Aso District Nishihara Village Electronic components Manufacturing equipment for electronic components 500 — Internal funds and borrowings November 2019 November 2020 35%」
The disclosure newly states a plan to install ¥500 million of electronic component manufacturing equipment at the Aso Plant, with work commencing in November 2019, completion scheduled for November 2020, and post-completion capacity expected to increase by 35%.