Installation of New Electrical Component Manufacturing Equipment at the Yahata Plant

First written in FY2020-Q2. 2 of 8 entries say "Advanced", first in FY2020-Q3. Latest entry: FY2022.

8entries
4years
0from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseAdvancedFY2020-Q3ReframedFY2020 – FY2021-Q1RaisedFY2021-Q3RaisedFY2022-Q1 – FY20222019: 220192020: 320202021: 220212022: 12022
Same theme, other companies
Installation of New Electrical Component Manufacturing Equipment at the Yahata PlantA theme 1 companies write about · 0 as a headwind · 1 as a tailwind

No other company in this theme has enough history to compare yet.

Full recordFilings, disclosures and news, newest first
  1. FY2022AdvancedAnnual report

    「Head office and Yahata Plant Manufacturing equipment for electrical components ¥2,318 million」

    For the Yahata Plant, an increase of ¥2,318 million in electrical component manufacturing equipment during the fiscal year is disclosed, indicating progress in capital investment.
  2. FY2022-Q1RaisedAnnual report

    「Reporting company Yahata Plant Fukuoka Prefecture Kitakyushu City Yahatanishi-ku Electrical components Manufacturing equipment for electrical components 7,261 1,086 Internal funds and borrowings February 2021 August 2022 20%」

    The Yahata Plant capital investment plan has changed to total investment of ¥7,261 million, a post-completion capacity increase of 20%, and completion scheduled for August 2022, with investment and capacity increased from the previous plan.
  3. FY2021SoftenedAnnual report

    「Reporting company Yahata Plant Fukuoka Prefecture Kitakyushu City Yahatanishi-ku Electrical components Manufacturing equipment for electrical components 6,409 — Internal funds and borrowings February 2021 July 2022 15%」

    For the Yahata Plant equipment plan, the scheduled completion remains July 2022, while the post-completion capacity increase has changed from 20% to 15%.
  4. FY2021-Q3RaisedAnnual report

    「Reporting company Yahata Plant Fukuoka Prefecture Kitakyushu City Yahatanishi-ku Electrical components Manufacturing equipment for electrical components 6,137 1,947 Internal funds and borrowings February 2020 July 2022 20%」

    The Yahata Plant capital investment plan has increased to total investment of ¥6,137 million and a post-completion capacity increase of 20%. The scheduled completion has changed from February 2021 to July 2022.
  5. FY2021-Q1ReframedAnnual report

    「Reporting company Yahata Plant Fukuoka Prefecture Kitakyushu City Yahatanishi-ku Electrical components Manufacturing equipment for electrical components 2,329 200 Internal funds and borrowings February 2020 February 2021 10%」

    The Yahata Plant capital investment plan is disclosed as total investment of ¥2,329 million, ¥200 million already paid, and completion scheduled for February 2021, with the investment amount and scheduled completion changed from the previous plan.
  6. FY2020ReframedAnnual report

    「Reporting company Yahata Plant Fukuoka Prefecture Kitakyushu City Electrical components Manufacturing equipment for electrical components 1,340 — Internal funds and borrowings February 2020 January 2021 10%」

    The Yahata Plant capital investment plan is disclosed as a plan for total investment of ¥2,331 million and completion in August 2020, changed to total investment of ¥1,340 million and completion in January 2021. The post-completion capacity increase of 10% is unchanged.
  7. FY2020-Q3AdvancedAnnual report

    「Reporting company Yahata Plant Fukuoka Prefecture, Kitakyushu City, Yahatanishi-ku Electrical components Manufacturing equipment for electrical components 2,331 590 Internal funds and borrowings February 2019 August 2020 10%」

    For the Yahata Plant capital investment in manufacturing equipment, the amount already paid increased from the previously disclosed ¥479 million to ¥590 million, indicating progress on the plan.
  8. FY2020-Q2First statedAnnual report

    「Reporting company Yahata Plant Fukuoka Prefecture, Kitakyushu City, Yahatanishi-ku Electrical components Manufacturing equipment for electrical components 2,331 479 Internal funds and borrowings February 2019 August 2020 10%」

    The disclosure newly states a plan to install ¥2,331 million of electrical component manufacturing equipment at the Yahata Plant, with work commencing in February 2019, completion scheduled for August 2020, and post-completion capacity expected to increase by 10%.
Moved together

"Expansion of the electrical components business through the expansion of the Shanghai plant" moved the same way as this thread, in the same document, in 6 of its 8 moves.

644433★123456
  1. ★This thread
  2. 1Expansion of the electrical components business through the expansion of the Shanghai plant6×
  3. 2Expanding motor core sales by leveraging an integrated production system from prototyping through mass production4×
  4. 3Expansion of Orders for Components Used in Smartphones and Other Information Terminals4×
  5. 4Expansion of motor core production capacity for environmentally friendly vehicles through construction of a new plant at the Gifu facility4×
  6. 5Productivity Improvements and Cost Reductions Across the Entire Group3×
  7. 6Payment of Interim Dividends3×

★ is this thread; numbers match the list above. The number on a line is how many documents both moved the same way in; lines between the other threads count the documents they moved together in too. Threads that move together often sit closer.

When this could move next
No upcoming earnings preview for Mitsui High-tec yet.
News
No news is linked to this thread yet. When an article touches it, it will appear here by date.
Installation of New Electrical Component Manufacturing Equipment at the Yahata Plant | Mitsui High-tec,Inc. (6966) | Komori