Establishment of New Electrical Component Manufacturing Facilities in Canada
First written in FY2017-Q2. 6 of 8 entries say "Advanced", first in FY2017-Q3. Latest entry: FY2023.
No other company in this theme has enough history to compare yet.
- FY2023AdvancedAnnual report
「Mitsui High-tec (Canada) Incorporated (Brantford, Ontario, Canada) Electrical components Electrical component manufacturing equipment 3,928 1,561 42 416 - 7,820 13,769」
The total carrying amount of the electrical component manufacturing equipment at the Canada site is stated as ¥13,769 million, indicating that the equipment base is being developed. - FY2022AdvancedAnnual report
「Mitsui High-tec (Canada) Incorporated (Brantford, Ontario, Canada) Electrical component manufacturing equipment Total 3,863」
The carrying amount of the electrical component manufacturing equipment at the Canada site is stated as ¥3,863 million as major equipment, indicating that development of the site's equipment base is progressing. - FY2021SoftenedAnnual report
「Mitsui High-tec (Canada) Incorporated Canada Ontario Electrical components Electrical component manufacturing equipment 726 - Internal funds and borrowings February 2021 January 2022 45%」
The plan to establish the Canada site was reset at an investment amount of ¥726 million, a 45% increase in capacity after completion and completion scheduled for January 2022, representing reduced capacity and a delayed schedule from the previous plan. - FY2020-Q1AdvancedAnnual report
「Mitsui High-tec (Canada) Incorporated Ontario, Canada Electrical components Electrical component manufacturing equipment 759 - Internal funds and borrowings June 2019 May 2020 50%」
The plan states that a ¥759 million manufacturing facility at the Canada site would be newly constructed, with work starting in June 2019 and completion scheduled for May 2020, and that capacity would increase by 50% after completion. - FY2019-Q2AdvancedAnnual report
「The Canadian subsidiary began mass production in July, while the Gifu facility in Japan began mass production in February 2019 as originally scheduled.」
The disclosure states that production at the Canada-based electrical component manufacturing facility reached the specific milestone of commencing mass production in July. - FY2018AdvancedAnnual report
「The consolidated subsidiary Mitsui High-tec (Canada), Inc. was established on 12 January 2015 and began operations in May 2017.」
The disclosure reports the specific milestone of commencing operations after establishing the Canadian facility. - FY2017-Q3AdvancedAnnual report
「Mitsui High-tec (Canada), Inc.; Brantford, Ontario, Canada; electrical components; buildings and electrical components manufacturing equipment; 4,950; 919; internal funds and borrowings; December 2015; January 2018; new construction」
For the new electrical components manufacturing equipment in Canada, the amount already paid increased from ¥545 million to ¥919 million. The disclosure states a total investment of ¥4,950 million, completion scheduled for January 2018, and funding through internal funds and borrowings. - FY2017-Q2First statedAnnual report
「Planned investment: ¥4,950 million; amount already paid: ¥545 million; funding: internal funds and borrowings; start: December 2015; completion: January 2018; equipment: buildings and electrical components manufacturing equipment」
The disclosure states the total investment, funding method, and planned start and completion dates for establishing new equipment at Mitsui High-tec (Canada), Inc. It also states that the planned investment amount and scheduled completion date were changed.