Development of a New Production Base for Automotive Electronic Components in Chitose, Hokkaido
First written in FY2016. 11 of 17 entries say "Advanced", first in FY2017-Q1. Latest entry: FY2021.
0 other companies' latest entry also says "Advanced".
- FY2021AdvancedAnnual report
「The factory opened in Chitose, Hokkaido, in 2016 is also steadily increasing production volumes.」
The company says production volumes are increasing at the new production site in Chitose, Hokkaido. - FY2020RestatedAnnual report
「The manufacturing lines installed at the factory opened in Chitose, Hokkaido, in 2017 have begun operating sequentially, and expansion work is now under way to increase space for further production growth.」
At the production site in Chitose, Hokkaido, the company is continuing the sequential start-up of installed lines and expansion work to increase production. - FY2020-Q3AdvancedAnnual report
「The Chitose factory, newly established in Hokkaido in 2016 as a molding plant for automotive parts, has completed installation of the planned molding lines and is now undergoing expansion work to increase space for further production growth.」
At the new production site in Chitose, Hokkaido, the company reported completion of the planned line installations and expansion work to increase production capacity. - FY2020-Q2AdvancedAnnual report
「Production transfer to the Chitose factory in Hokkaido, newly established in 2016, is progressing smoothly. As demand for automotive electrical components is expected to continue increasing, expansion work is under way at the Chitose factory, with completion targeted for the first half of fiscal 2020.」
Production transfers are under way at the automotive production site in Chitose, Hokkaido, and expansion work targeted for completion in the first half of fiscal 2020 has begun. - FY2020-Q1AdvancedAnnual report
「The production transfer to the newly established Chitose Plant, built to increase production of automotive molded parts, is progressing smoothly, and delivery of all manufacturing lines included in the initial plan is scheduled to be completed in September 2019. As demand for automotive electrical components is expected to continue increasing, the company plans to expand the Chitose Plant, with completion targeted for the first half of fiscal 2020.」
For the Chitose Plant, the company presented plans to complete delivery of the manufacturing lines included in the initial plan and to carry out an expansion project targeted for completion in the first half of fiscal 2020. - FY2019AdvancedAnnual report
「The transfer of production from the existing factory in Shizuoka Prefecture to the Chitose factory in Hokkaido, established to increase production of automotive molded products, is progressing smoothly, and approximately 90% of the manufacturing lines had been installed as of the end of the fiscal year.」
Production transfers and the installation of manufacturing lines are progressing at the new production site in Chitose, Hokkaido, with approximately 90% of the lines installed by the end of the fiscal year. - FY2019-Q3RestatedAnnual report
「Production transfer of automotive sensor components to the new factory established in Chitose, Hokkaido, the year before last, is progressing smoothly.」
Production transfers to the new production site in Chitose, Hokkaido, are continuing, and the company says they are progressing smoothly. - FY2019-Q2RestatedAnnual report
「Production transfer of automotive sensor components to the new factory established in Chitose, Hokkaido, the year before last, is progressing smoothly.」
The company says production transfers to the new production site in Chitose, Hokkaido, are progressing smoothly. - FY2019-Q1RestatedAnnual report
「Production transfer of automotive sensor components to the new factory established in Chitose, Hokkaido, the year before last, is progressing smoothly.」
Production transfers to the new plant in Chitose, Hokkaido, are continuing, and the company says the transfers are progressing smoothly. - FY2018-Q3RestatedAnnual report
「In its Precision Machinery-related operations, the company is gradually transferring production of automotive molded products to the new factory established in Chitose, Hokkaido, last year, while considering mass production of new products in the space freed up at the existing factory in Shizuoka Prefecture.」
Production transfers to the new production site in Chitose, Hokkaido, are continuing, while vacant space at existing plants is also being used to consider mass production of new products. - FY2018-Q2AdvancedAnnual report
「The company is transferring production of automotive molded products from its existing factory in Shizuoka Prefecture to the new factory established in Chitose, Hokkaido, while considering mass production of new automotive molded products in the space freed up at the existing factory.」
The new production site in Chitose has reached the stage of transferring production from the existing plant in Shizuoka Prefecture, and its utilization is being expanded. - FY2018-Q1AdvancedAnnual report
「At the new automotive parts factory that began operating in Chitose, Hokkaido, last year, the company is adding molding lines and sales are gradually expanding.」
Additional molding lines are being installed at the automotive-parts production site in Chitose, and site revenue has begun to increase. - FY2017AdvancedAnnual report
「During the fiscal year, the company established a new automotive parts factory in Chitose, Hokkaido, and one production line began operating in October of the previous year. The company plans to expand the facility to 20 production lines in 2020.」
1 line is now operational at the automotive-parts production site in Chitose, with a plan presented to expand the site to 20 lines. - FY2017-Q3AdvancedAnnual report
「The new factory for automotive molded products in Chitose, Hokkaido, has begun shipping products to customers, and the company is focusing on commissioning the molding machines brought in to support further production increases.」
Customer shipments have begun from the automotive molded-parts production site in Chitose, Hokkaido, and equipment commissioning for increased production is under way. - FY2017-Q2AdvancedAnnual report
「At the new factory for automotive molded products in Chitose, Hokkaido, the company prepared its mass-production system for shipments beginning in or after the third quarter.」
At the Chitose production base for automotive molded products, the company proceeded with preparations to begin mass production after completion and advanced to the stage of establishing a system for shipments beginning in or after the third quarter. - FY2017-Q1AdvancedAnnual report
「The new factory for automotive molded products under construction in Chitose, Hokkaido, was completed at the end of March, and preparations were made to begin mass production.」
The new factory for automotive molded products in Chitose, whose construction had been under way in the previous fiscal year, was completed at the end of March. - FY2016First statedAnnual report
「For automotive electronic components, for which demand continues to expand steadily, the company proceeded with construction of a new production base in Chitose, Hokkaido, in light of business-continuity risks arising from major earthquakes and other events.」
不二電子工業 built a new factory in Chitose, and capital investment in Precision Machinery-related equipment during the fiscal year was ¥1,423,312 thousand.