Komori
Chiyoda (6366) · InitiativeAdvanced

Demonstration Plant for Next-Generation Battery Materials and Advanced Materials Plant Project

First written in FY2024-Q1. 7 of 9 entries say "Advanced", first in FY2024-Q2. Latest entry: FY2026.

9entries
4years
3from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseRestatedFY2024-Q3AdvancedFY2025 – FY20262023: 220232024: 120242025: 220252026: 42026
Same theme, other companies
EPC for demonstration plants and mass-production facilities for next-generation battery materialsA theme 1 companies write about · 0 as a headwind · 1 as a tailwind

No other company in this theme has enough history to compare yet.

Full recordFilings, disclosures and news, newest first
  1. FY2026AdvancedAnnual report

    「Idemitsu Kosan Co.,Ltd. awarded us an order for EPC services for a large-scale solid-electrolyte pilot facility for the commercialisation of all-solid-state lithium-ion secondary batteries, which are widely regarded as the leading next-generation battery for electric vehicles.」

    In the next-generation battery field, after completing the small-scale solid-electrolyte demonstration plant, progressed to an order for EPC services for a large-scale pilot facility and a strategic partnership aimed at mass production.
  2. FY2026-H1AdvancedAnnual report

    「In Japan, we completed a small-scale demonstration plant project for solid electrolytes for all-solid-state batteries, which are expected to extend driving ranges, shorten charging times and improve safety, mainly for electric vehicles. We have also received orders for the construction of a large-scale facility for lithium sulfide (Li2S), an intermediate material for the commercialisation of all-solid-state batteries, and for basic design services for a large-scale solid-electrolyte pilot plant, and are carrying out this work.」

    In the next-generation battery field, completed a small-scale demonstration plant for solid electrolytes, then progressed to the construction of a large-scale Li2S facility and the execution of an order for basic design services for a large-scale solid-electrolyte pilot plant.
  3. FY2025AdvancedAnnual report

    「In Japan, we completed a small-scale demonstration plant project for solid electrolytes for all-solid-state batteries, which are expected to extend driving ranges, shorten charging times and improve safety, mainly for electric vehicles. We have also received orders for the construction of a large-scale facility for lithium sulfide (Li2S), an intermediate material for the commercialisation of all-solid-state batteries, and for basic design services for a large-scale solid-electrolyte pilot plant, and are carrying out this work.」

    Completed a small-scale demonstration plant for solid electrolytes in the next-generation battery field, then expanded into the construction of a large-scale Li2S facility and the execution of an order for basic design services for a large-scale solid-electrolyte pilot plant.
  4. FY2024-Q3RestatedAnnual report

    「In Japan, we are carrying out preliminary work toward EPC services for an advanced materials plant. In addition, we have received an order for, and are carrying out, a demonstration plant project for inorganic battery materials for next-generation batteries, which are expected to extend driving ranges, shorten charging times and improve safety, mainly for electric vehicles (EVs). We have also newly received an order from KUREHA CORPORATION for EPC services for the monomer process of vinylidene fluoride resin production equipment.」

    Reconfirmed the status of preliminary work for an advanced materials plant, the next-generation battery materials demonstration plant, and the EPC project ordered by KUREHA CORPORATION.
  5. FY2024-Q2AdvancedAnnual report

    「In Japan, we are carrying out preliminary work toward EPC services for an advanced materials plant. In addition, we have received an order for, and are carrying out, a demonstration plant project for inorganic battery materials for next-generation batteries, which are expected to extend driving ranges, shorten charging times and improve safety, mainly for electric vehicles (EVs). We have also newly received an order from KUREHA CORPORATION for EPC services for the monomer process of vinylidene fluoride resin production equipment.」

    Continued preliminary work toward EPC services for an advanced materials plant and work on a demonstration plant for inorganic battery materials for next-generation batteries, and newly received an order from KUREHA CORPORATION for EPC services for the monomer process of vinylidene fluoride resin production equipment.
  6. FY2024-Q1First statedAnnual report

    「In the advanced materials field, we have received an order for, and are currently carrying out, a demonstration plant project for inorganic battery materials for next-generation batteries, which are expected to extend driving ranges, shorten charging times and improve safety, mainly for electric vehicles (EVs). In Japan, we are also carrying out preliminary work toward EPC services for an advanced materials plant.」

    Received an order for and is carrying out a demonstration plant project for inorganic battery materials for next-generation batteries, while also beginning preliminary work toward EPC services for an advanced materials plant in Japan.
Moved together

"Execution of Large-Scale Projects in the Core LNG Business and Initiatives for New Projects" moved the same way as this thread, in the same document, in 6 of its 9 moves.

655444★123456
  1. ★This thread
  2. 1Execution of Large-Scale Projects in the Core LNG Business and Initiatives for New Projects6×
  3. 2Improvements in Orders Received, Construction Revenue and Ordinary Profit5×
  4. 3Bankruptcy and Withdrawal of Golden Pass LNG’s Joint Execution Partner and Completion Risk5×
  5. 4Growth Strategy, Business Foundation Development and Earnings Recovery in the Final Year of the Medium-Term Management Plan4×
  6. 5Building the Foundation for Developing a Diverse Workforce4×
  7. 6Increase in construction costs for US LNG project4×

★ is this thread; numbers match the list above. The number on a line is how many documents both moved the same way in; lines between the other threads count the documents they moved together in too. Threads that move together often sit closer.

When this could move next
Chiyoda's next results are scheduled for 2026-11-04. Read the earnings preview It last moved in the Earnings presentation of 2026-05-27: "Advanced".
News