Execution of Large-Scale Projects in the Core LNG Business and Initiatives for New Projects
First written in FY2017-Q1. 27 of 37 entries say "Advanced", first in FY2017-Q2. Latest entry: FY2026.
3 other companies' latest entry also says "Advanced".
- FY2026AdvancedAnnual report
「The company continued negotiations on the EPC contracts for Trains 2 and 3 after reaching a basic agreement in June 2025 on the allocation of future cost burdens, and formally signed amended EPC contracts with GPX in November 2025. This established an execution structure covering all three trains, Trains 1 through 3. For Train 1, construction and commissioning were completed in March 2026, and production of first LNG was achieved.」
Regarding Golden Pass LNG, the company signed amended EPC contracts for Trains 2 and 3 and established an execution structure covering all 3 trains. Train 1 completed construction and commissioning in March 2026 and achieved first LNG production. - FY2026-H1AdvancedAnnual report
「Following the withdrawal of Zachry, the U.S. Golden Pass LNG project formed a two-company joint venture with McDermott, replacing the former joint venture with Zachry, and has proceeded with construction after agreeing with its customer, Golden Pass LNG LLC (GPX), to amend the EPC contract for Train 1 last November. During the interim consolidated accounting period, while negotiating amendments to the EPC contract for Trains 2 and 3, the company reached a basic agreement with GPX in June on the allocation of responsibility for future cost burdens, including settlement of costs to be incurred in executing the project going forward. The parties are now in the final stage before signing the contracts.」
Following Zachry's withdrawal from Golden Pass LNG, the company formed a two-company JV with McDermott and, after agreeing to amend the Train 1 contract, advanced to a basic agreement on the allocation of responsibility for future costs related to Trains 2 and 3. - FY2025AdvancedAnnual report
「The company has confirmed that it is working with its customer, U.S. Golden Pass LNG Terminal LLC (GPX), and its U.S. joint venture partner, CB&I LLC (CB&I), to complete the U.S. Golden Pass LNG project (GPX project). In November 2024, it agreed with the customer to amend the contract for Train 1 of the LNG plant and continues to negotiate amendments to the contracts for Trains 2 and 3.」
The major LNG projects saw specific execution progress, with agreement reached to amend the GPX Train 1 contract and negotiations under way to amend the Train 2 and 3 contracts. - FY2025-H1AdvancedAnnual report
「The company has confirmed that it is working with its customer, U.S. Golden Pass LNG Terminal LLC (GPX), and GPX project's U.S. joint venture partner, CB&I LLC (CB&I), to complete the U.S. Golden Pass LNG project (GPX project), and is holding discussions to obtain various forms of support from the customer toward that goal.」
Regarding Golden Pass LNG, following Zachry's withdrawal, the company changed to an execution structure aimed at completion in cooperation with GPX and CB&I, and is holding discussions to obtain customer support. - FY2024RestatedAnnual report
「Overseas, EPC work for LNG plants is under way in Qatar and the United States. Construction work is moving into full swing at both the Qatar North Field East LNG export base project (NFE project), which involves adding four 8-million-ton-per-year LNG plant trains, and the U.S. Golden Pass LNG project.」
The company has reconfirmed that it continues EPC and construction work at Qatar NFE and U.S. Golden Pass LNG. - FY2024-Q3RestatedAnnual report
「Overseas, EPC work for LNG plants is under way in Qatar and the United States. Construction work is moving into full swing and progressing at both the Qatar North Field East LNG export base project (NFE project), which involves adding four 8-million-ton-per-year LNG plant trains, and the U.S. Golden Pass LNG project.」
As part of its core LNG business, the company continues EPC and construction work at Qatar NFE and U.S. Golden Pass LNG. - FY2024-Q2AdvancedAnnual report
「Overseas, we are carrying out EPC activities for LNG plants in Qatar, the United States and Indonesia. Construction work on Qatar’s North Field East LNG export terminal project (NFE project), an expansion project involving four 8-million-ton-per-year LNG trains, and the Golden Pass LNG project in the United States is entering full swing and progressing. Train 3 of Indonesia’s Tangguh LNG expansion project was handed over to the customer in August 2023, and production has begun.」
In its core LNG business, construction work at NFE and Golden Pass is moving into full swing, while Tangguh LNG Train 3 has reached the specific milestones of completing handover and commencing production. - FY2023AdvancedAnnual report
「Overseas, EPC (engineering, procurement and construction) work for LNG plants is under way in Qatar, the United States and Indonesia. At the Qatar North Field East LNG export base project (NFE project), which involves adding four 8-million-ton-per-year LNG plant trains, civil construction for the permanent facilities is moving into full swing and progressing. Construction work at the Golden Pass LNG project in the United States is likewise moving into full swing and progressing.」
In its core LNG business, civil construction at NFE and construction work at Golden Pass are moving into full swing, advancing execution of existing major projects. - FY2023-Q3RestatedAnnual report
「Overseas, EPC (engineering, procurement and construction) work for LNG plants is under way in Qatar, the United States and Indonesia. At the Qatar North Field East LNG export base project (NFE project), which involves adding four 8-million-ton-per-year LNG plant trains, civil construction for the permanent facilities is moving into full swing and progressing. Construction work at the Golden Pass LNG project in the United States is likewise moving into full swing and progressing.」
The company has reconfirmed that it continues EPC work on the Qatar NFE, U.S. Golden Pass and Indonesian LNG projects, with civil construction at NFE and construction work at Golden Pass moving into full swing. - FY2023-Q2AdvancedAnnual report
「Overseas, EPC (engineering, procurement and construction) work for LNG plants is under way in Qatar, the United States and Indonesia. At the Qatar North Field East LNG export base project (NFE project), which involves adding four 8-million-ton-per-year LNG plant trains, civil construction for the permanent facilities is under way in earnest. Construction work is also moving into full swing at the Golden Pass LNG project in the United States. Indonesia's Tangguh LNG Expansion Project (Train 3) is nearing the end of construction.」
In its core LNG business, the company continues EPC work in Qatar, the United States and Indonesia and describes specific progress: civil construction for NFE's permanent facilities, the acceleration of construction at Golden Pass, and the approach of Tangguh Train 3 to the end of construction. - FY2023-Q1AdvancedAnnual report
「In Qatar, we are carrying out EPC activities for the North Field East LNG export terminal project (NFE project), an expansion project involving four 8-million-ton-per-year LNG trains, and construction of the permanent plant has begun. At the Golden Pass LNG project in the United States, where we are carrying out EPC activities, field construction is entering full swing. In Indonesia, construction of Train 3 of the Tangguh LNG expansion project is approaching completion and is progressing toward completion.」
The company describes specific progress in its core LNG business: civil construction for the permanent facilities at Qatar NFE has begun, construction work at Golden Pass is moving into full swing, and construction of Tangguh Train 3 is nearing completion. - FY2022-Q3RestatedAnnual report
「Overseas, EPC (engineering, procurement and construction) work for LNG (liquefied natural gas) plants is under way in Qatar, the United States, Indonesia and Nigeria. In Qatar, EPC work is under way on the North Field East LNG export base project (NFE project), which involves adding four 8-million-ton-per-year LNG plant trains. In the United States, EPC work is under way on the Golden Pass LNG project.」
The company continues to execute EPC work on major LNG projects, including the NFE project and Golden Pass LNG. - FY2022-Q2RestatedAnnual report
「Overseas, EPC (engineering, procurement and construction) work for LNG (liquefied natural gas) plants is under way in Qatar, the United States, Indonesia and Nigeria. In Qatar, EPC work is under way on the North Field East LNG export base project (NFE project), which involves adding four 8-million-ton-per-year LNG plant trains. In the United States, EPC work is under way on the Golden Pass LNG project.」
The company continues to execute EPC work on major LNG projects, including NFE and Golden Pass. - FY2022-Q1AdvancedAnnual report
「The North Field East LNG export terminal project (NFE project), an expansion project involving four 8-million-ton-per-year LNG trains in Qatar, has begun EPC activities.」
In its core LNG business, the Qatar NFE project to add four 8-million-ton-per-year trains has reached the start of EPC work. - FY2021-Q3AdvancedAnnual report
「Overseas, EPC work for LNG (liquefied natural gas) plants is under way in the United States, Indonesia, Mozambique and Nigeria. In the United States, the Cameron LNG project has commenced commercial production across all trains. EPC work is under way on the Golden Pass LNG project. In Mozambique and Nigeria, technical support, including reviews of designs carried out by partners, is under way on LNG projects. The company also submitted a bid for a project in Qatar to add four 7.8-million-ton-per-year LNG plant trains.」
The company continues to execute LNG projects and has advanced the Qatar project to add four 7.8-million-ton-per-year trains from the previous quotation stage to the bidding stage. - FY2021-Q2AdvancedAnnual report
「In the United States, commercial operations began at the third train of the Cameron LNG project in August 2020, bringing all trains into commercial operation.」
All trains of the Cameron LNG project entered commercial operation following the start of commercial operations at the third train. - FY2021-Q1AdvancedAnnual report
「Overseas, the company is executing EPC services for LNG (liquefied natural gas) plants in the United States, Indonesia, Mozambique and Nigeria. In the United States, commercial operations began at the third train of the Freeport LNG project in May 2020, bringing all trains into commercial operation. Production began at the third train of the Cameron LNG project in May 2020, and the company continues to execute the project safely and reliably toward the start of commercial operations.」
Execution of major LNG projects progressed, with all trains of Freeport LNG entering commercial operation and production beginning at the third train of Cameron LNG. - FY2020-Q3AdvancedAnnual report
「In the United States, commercial operations began at the first train of the Cameron LNG project, and LNG production began at the second train. At the Freeport LNG project, commercial operations began at the first train, and LNG production began at the second train. The company continues to execute both projects safely and reliably toward completion. It is executing EPC work on the Golden Pass LNG project, for which it received an order in February 2019. It is also preparing an EPC estimate for a project in Qatar to add four trains, each with annual capacity of 7.8 million tonnes, to an LNG plant.」
At Cameron LNG and Freeport LNG, commercial operations and production began at the respective trains, while the company progressed to EPC execution on Golden Pass LNG and EPC estimate preparation for the Qatar project to add four trains with annual capacity of 7.8 million tonnes. - FY2020-Q2AdvancedAnnual report
「In the United States, commercial operations began at the first train of the Cameron LNG project, while LNG production and shipments began from the first train of the Freeport LNG project. Full-scale EPC (engineering, procurement and construction) work has begun on the Golden Pass LNG project. Outside the United States, for the LNG project for the partners in Mozambique Offshore Area 1, which reached final investment decision in June this year, the company will provide technical support services, mainly reviewing designs prepared by the EPC partner.」
The company reports multiple concrete milestones in its LNG core business, including commercial operations at the first train of Cameron LNG, production and shipments from the first train of Freeport LNG, full-scale EPC work on Golden Pass LNG, and the start of technical support for the Mozambique project. - FY2020-Q1AdvancedAnnual report
「In the United States, LNG production and shipments began from the first train of the Cameron LNG project, and full-scale EPC (engineering, procurement and construction) work began on the Golden Pass LNG project. In addition, the company is preparing EPC estimates in Qatar and Nigeria.」
The company progressed to production and shipments from the first train of Cameron LNG, full-scale EPC work on Golden Pass LNG, and estimate preparation in Qatar and Nigeria. - FY2019AdvancedAnnual report
「In Australia, both the first and second trains of the Ichthys LNG plant began production. In Russia, the third train of the Yamal LNG plant was completed more than 1 year ahead of the contractual delivery date, bringing the production capacity of the three trains to 16.5 million tonnes, demonstrating steady progress on these large-scale projects. In the United States, the company won an order for a new LNG plant project. In addition, in Qatar it completed FEED services as scheduled for a plan to add four trains to an LNG plant with annual capacity of 7.8 million tonnes, while in Nigeria it is steadily executing FEED and EPC estimating services.」
The company reports multiple developments in large-scale LNG projects, including production starting at the first and second trains of Ichthys LNG, completion of the third train of Yamal LNG, winning an order for a new U.S. project, and completion of FEED in Qatar. - FY2019-Q3AdvancedAnnual report
「In Australia, both the first and second trains of the Ichthys LNG plant began production. In Russia, the third train of the Yamal LNG plant was completed more than 1 year ahead of the contractual delivery date, bringing the production capacity of the three trains to 16.5 million tonnes, demonstrating steady progress on these large-scale projects.」
The first and second trains of Ichthys LNG began production, the third train of Yamal LNG was completed more than 1 year ahead of the contractual delivery date, and the production capacity of the three trains reached 16.5 million tonnes. - FY2019-Q2AdvancedAnnual report
「In Russia, the second train of the Yamal LNG plant was completed, while in Qatar the company is performing FEED (front-end engineering design) services for an expansion project. In Nigeria, it won contracts for FEED and EPC (engineering, procurement and construction) estimating services.」
In its LNG core business, the company completed the second train of Yamal LNG, advanced FEED for the Qatar expansion project, and won contracts for FEED and EPC estimating services in Nigeria. - FY2019-Q1AdvancedAnnual report
「Overseas, the company is executing EPC (engineering, procurement and construction) services for LNG plants in Australia, the United States, Russia and Indonesia. For future EPC work, it continues EPC preparation work on the Mozambique project, where it has already been selected as the contractor. In addition, in Qatar it is steadily executing FEED services for a plan to add three trains to an LNG plant with annual capacity of 7.8 million tonnes, and is preparing an estimate for a new LNG plant project in the United States.」
The company reports EPC execution in Australia, the United States, Russia and Indonesia, EPC preparation in Mozambique, FEED execution in Qatar for a plan to add three trains with annual capacity of 7.8 million tonnes, and estimate preparation for a U.S. project in its LNG core business. - FY2018AdvancedAnnual report
「Overseas, the company is executing EPC (engineering, procurement and construction) services for LNG plants in Australia, the United States, Russia and Indonesia. The first train of the Yamal LNG project in Russia began production in December 2017. For future EPC work, it continues EPC preparation work in Mozambique, where it has already been selected as the contractor. In addition, in Qatar it completed a study on debottlenecking (capacity expansion) of an LNG plant, won the FEED (front-end engineering design) contract in March 2018 for a plan to add three trains to an LNG plant with annual capacity of 7.8 million tonnes, and is also preparing an estimate for a new LNG plant project in the United States.」
The company reports concrete progress, including the start of production at the first train of Yamal LNG, completion of the Qatar capacity expansion study, and winning the FEED contract for a plan to add three trains with annual capacity of 7.8 million tonnes. - FY2018-Q3AdvancedAnnual report
「Overseas, the company is executing EPC (engineering, procurement and construction) services for LNG plants in Australia, the United States, Russia and Indonesia. The first train of the Yamal LNG project in Russia, which the company was executing, began production as scheduled in December 2017. In addition, it continues to perform EPC preparation work under the contract in Mozambique, where it was selected as the EPC contractor. Furthermore, as announced in June 2017, it conducted a study on debottlenecking (capacity expansion) of an LNG plant in Qatar under a memorandum of understanding with Qatar Petroleum and contributed to developing a master plan to achieve Qatar’s LNG production expansion target.」
The company reports concrete milestones in its LNG core business, including the first train of Yamal LNG beginning production as scheduled in December 2017 and the Qatar capacity expansion study contributing to the development of a master plan for increased LNG production. - FY2018-Q2AdvancedAnnual report
「Overseas, the company is executing EPC (engineering, procurement and construction) services for LNG plants in Australia, the United States, Russia and Indonesia. In addition, it continues to perform pre-contract work in Mozambique, where it was selected as the EPC contractor. Furthermore, as announced in June this year, it is conducting a study on debottlenecking (capacity expansion) of an LNG plant in Qatar under a memorandum of understanding with Qatar Petroleum.」
In addition to EPC in Australia, the United States, Russia and Indonesia and pre-contract work in Mozambique, the company has begun and is conducting a study on expanding LNG plant capacity in Qatar. - FY2018-Q1RestatedAnnual report
「Even under these challenging conditions, the Group is diligently executing construction work for large-scale projects in its core LNG business in the United States, Australia, Russia and Indonesia. It also continues strategic initiatives to secure orders, including participating in bids after identifying future projects with a high probability of realization.」
The company positions LNG as its core business and continues executing large-scale projects in the United States, Australia, Russia and Indonesia, while bidding on future projects after assessing their feasibility. - FY2017AdvancedAnnual report
「Overseas, the company has completed FEED (front-end engineering design) services for LNG plants in the United States and Russia and is executing EPC (engineering, procurement and construction) services in Australia, the United States, Russia and Indonesia. In addition, it continues to perform pre-contract work in Mozambique, where it was selected as the EPC contractor.」
The company reports completion of FEED in the United States and Russia, execution of EPC in Australia, the United States, Russia and Indonesia, and continued pre-contract work in Mozambique. - FY2017-Q3AdvancedAnnual report
「Overseas, the company is actively executing EPC (engineering, procurement and construction) services for LNG plants in Australia, the United States, Russia and Indonesia, and FEED (front-end engineering design) services for an LNG plant in the United States. In addition, in Mozambique, where it was selected as the EPC contractor for an LNG plant, it is carrying out some pre-contract work.」
In addition to executing LNG plant EPC and FEED services, the company was selected as the EPC contractor in Mozambique and began pre-contract work. - FY2017-Q2AdvancedAnnual report
「In LNG, its core business, the company continues to secure a strong position by actively pursuing new projects, including highly feasible expansion projects, in addition to executing large-scale projects around the world, as demonstrated by its securing a new order in Indonesia.」
In addition to executing existing large-scale projects and pursuing new projects, the company secured a new order in Indonesia for EPC services for an LNG plant. - FY2017-Q1First statedAnnual report
「In LNG, its core business, the company is actively pursuing new projects, including highly feasible expansion projects, in addition to executing large-scale projects around the world, although some projects have experienced delays in reaching final investment decisions.」
The company positions LNG as its core business and is pursuing the execution of existing large-scale projects and business development for new projects in parallel.