Capital investments in the Yonago Plant research facility and the new Shanghai Plant
First written in FY2018. 8 of 11 entries say "Advanced", first in FY2019. Latest entry: FY2025.
No other company in this theme has enough history to compare yet.
- FY2025AchievedAnnual report
「At our Kyoto plant, the Company's main domestic plant, a motor production building designed for submersible motor production and improved productivity has been completed, and we are working to improve submersible motor technology and expand production.」
The Kyoto plant motor production building, which had been under construction, was completed, and the project moved into the phase of improving productivity and expanding submersible motor production. - FY2025-H1AdvancedAnnual report
「Expenditures for the acquisition of property, plant and equipment associated with the construction of the new Kyoto plant building and other projects increased by ¥995 million.」
Expenditures for the acquisition of property, plant and equipment associated with the construction of the new Kyoto plant building and other projects increased by ¥995 million during the interim period, and capital investment continued to be implemented. - FY2024AdvancedAnnual report
「During the consolidated fiscal year, we made total capital investments of ¥4,743 million, primarily in plant facilities. Major investments included land purchases and new construction costs associated with the ongoing construction of a new building at our Kyoto plant, for a total investment of ¥4,308 million.」
Capital investment for the fiscal year reached ¥4,743 million overall, including ¥4,308 million in Japan, centered on the new Kyoto plant building. - FY2024-Q2AdvancedAnnual report
「This was mainly due to a ¥1,626 million increase in expenditures for the acquisition of property, plant and equipment associated with the construction of the new Kyoto plant building, while proceeds from the redemption of time deposits increased by ¥328 million, proceeds from the sale and redemption of securities increased by ¥437 million, and expenditures for the acquisition of investment securities decreased by ¥1,789 million.」
Expenditures for the acquisition of property, plant and equipment associated with the construction of the new Kyoto plant building increased by ¥1,626 million, indicating progress in implementing capital investment. - FY2023AdvancedAnnual report
「During the consolidated fiscal year, we made total capital investments of ¥1,604 million, primarily in plant facilities. Major investments included land purchases associated with the ongoing construction of a new building at our Kyoto plant, as well as land purchases and new construction costs associated with relocating our Chubu Branch office, for a total investment of ¥1,421 million.」
Capital investment, including the construction of the new Kyoto plant building and the relocation of the Chubu Branch, continued, bringing full-year capital investment to ¥1,604 million, of which ¥1,421 million was in Japan. - FY2022AdvancedAnnual report
「As part of the Group's production activities, the new building at our domestic Yonago plant, completed in December 2021 and capable of producing and testing large drainage pumps in the 2,000 mm diameter class, is operating smoothly.」
The new building at the Yonago plant, which had been planned and under construction through the previous consolidated fiscal year, was completed in December 2021 and is operating smoothly as a facility capable of producing and testing large drainage pumps in the 2,000 mm diameter class. - FY2022-Q3AchievedAnnual report
「The planned construction of major facilities at the end of the previous consolidated fiscal year, specifically the new building at the Yonago plant, was completed as planned during the nine-month period of the current consolidated fiscal year.」
The planned construction of the new Yonago plant building was completed as scheduled. - FY2021AdvancedAnnual report
「Our company | Yonago Plant | Yonago, Tottori Prefecture, Japan | Construction of a new plant building | ¥1,736 million | ¥539 million | Internal funds and borrowings | April 2020 | December 2021」
Construction of the new building at the Yonago plant, with a total cost of ¥1,736 million and ¥539 million already paid, was progressing toward its scheduled completion in December 2021. During the full year, a logistics and distribution center was also newly constructed in Tochigi Prefecture, bringing total capital investment to ¥1,484 million. - FY2020AdvancedAnnual report
「During the consolidated fiscal year, we made total capital investments of ¥1,854 million, primarily in plant facilities. Major investments included land purchases and other costs associated with the construction of a new logistics and distribution center in Tochigi Prefecture, as well as the construction of a new plant and acquisition of machinery and equipment by SHANGHAI TSURUMI PUMP CO.,LTD.」
Investment related to the construction of the Shanghai plant continued from the previous fiscal year, while investment in the logistics and distribution center in Tochigi Prefecture was added, bringing full-year capital investment to ¥1,854 million. - FY2019AdvancedAnnual report
「The company made total capital investments of ¥1,927 million during the current consolidated fiscal year, primarily in plant facilities. Major investments included construction of a new molding research facility at the company's Yonago Plant, relocation of a warehouse at TSURUMI(AMERICA),INC., and construction of a new plant at SHANGHAI TSURUMI PUMP CO.,LTD.」
Investment in the Yonago plant research facility and the new Shanghai plant, which had been planned in the previous fiscal year, moved into the implementation stage, bringing total capital investment, including the North American warehouse relocation, to ¥1,927 million. - FY2018First statedAnnual report
「The company Yonago Plant Nambu, Tottori Prefecture Japan Construction of research facility 358 - Internal funds June 2018 October 2018 SHANGHAI TSURUMI PUMP CO.,LTD. Shanghai Plant People's Republic of China Shanghai China Construction of new plant 1,045 282 Internal funds and borrowings June 2017 March 2019」
The company planned construction of a research facility at the Yonago Plant costing ¥358 million and construction of a new Shanghai Plant costing ¥1,045 million, and disclosed the planned start and completion dates and the funding methods of internal funds and borrowings.