Development of a stainless steel and high-chromium cast iron foundry and a new building at the Kyoto Plant
First written in FY2022. 5 of 7 entries say "Advanced", first in FY2023. Latest entry: FY2026.
No other company in this theme has enough history to compare yet.
- FY2026AdvancedAnnual report
「In addition to its stainless steel and high-chromium foundry, a domestic group company also began operating a new foundry for gray cast iron (FC) and ductile cast iron (FCD). It began manufacturing submersible-pump components and is achieving short lead times, high precision and high quality by using the 3D forming technology it has been developing. Submersible-motor production is also fully operational at the new motor production building at the Kyoto Plant, the group's main domestic plant.」
The scope of operations at the foundries expanded, and production of pump components began. The new motor production building at the Kyoto Plant also progressed toward full-scale operations. - 2026-06-04AchievedGeneral Meetings of Shareholders
「2023年1月竣工の八尾工場に続く鋳造工場の完成により、当社中核事業である水中ポンプの製造において欠かせない鋳物部品の内製化をより強化しました。」
計画されていたアロイテクノロジー南部町事業所の新鋳造工場が竣工し、鋳物部品の内製化強化へ進んでいる。 - FY2025-H1AdvancedAnnual report
「Expenditures for the acquisition of property, plant and equipment associated with the construction of the new Kyoto plant building and other projects increased by ¥995 million.」
Expenditure on the acquisition of property, plant and equipment related to construction of the new building at the Kyoto Plant increased by ¥995 million in the interim period, and development of the new building continues. - FY2024AdvancedAnnual report
「A domestic group company began manufacturing submersible-pump components at its stainless steel and high-chromium foundry, achieving short lead times, high precision and high quality by using the 3D forming technology it has been developing. The company is also constructing a new building at the Kyoto Plant, its main domestic plant, for submersible-motor production and improved productivity.」
The foundry of アロイテクノロジー began manufacturing pump components and is using 3D forming technology, while construction of the new building at the Kyoto Plant continues. - FY2024-Q2AdvancedAnnual report
「Expenditure on the acquisition of property, plant and equipment increased by ¥1,626 million in connection with construction of a new building at the Kyoto Plant.」
Expenditure on the acquisition of property, plant and equipment increased in connection with construction of the new building at the Kyoto Plant, indicating progress in executing the construction plan. - FY2023AdvancedAnnual report
「As part of the group's production activities, 株式会社アロイテクノロジー, a domestic subsidiary, completed a stainless steel and high-chromium cast iron foundry in January 2023 and began manufacturing components such as submersible-pump impellers. The company will also begin construction of a new building at the Kyoto Plant, its main domestic plant, for submersible-motor production and improved productivity.」
The planned foundry of アロイテクノロジー was completed in January 2023 and began manufacturing components. Construction of the new building at the Kyoto Plant has also progressed to the launch stage, for submersible-motor production and improved productivity. - FY2022First statedAnnual report
「To achieve further growth, a domestic group company is constructing a stainless steel and high-chromium cast iron foundry scheduled to begin operations in December 2022. In addition, it plans to proceed with construction of a new building at the Kyoto Plant, the group's main domestic plant.」
A domestic group company is constructing a foundry scheduled to begin operations in December 2022. In addition, the company plans to proceed with construction of a new building at the Kyoto Plant.