Recovery and reconstruction support framework for areas affected by the Noto Peninsula Earthquake
First written in FY2024-Q2. 9 of 10 entries say "Advanced", first in FY2024-Q3. Latest entry: 2026-10-09.
No other company in this theme has enough history to compare yet.
- FY2025AdvancedAnnual report
「In Japan, as adoption of the company's construction methods remained steady, construction progressed smoothly and revenue increased through projects including the restoration of a port damaged by the Noto Peninsula Earthquake in Ishikawa Prefecture, landslide prevention and earth-pressure reduction measures for bridge caissons in Fukui Prefecture, installation of an Eco-Cycle system in Hyogo Prefecture, and construction of foundations for a seawall at a power plant in Hokkaido.」
The company's construction methods and project track record in disaster relief and recovery expanded, including restoration work at a port damaged by the Noto Peninsula Earthquake. - FY2025-H1AdvancedAnnual report
「As a result, in public works, the method was adopted for road restoration following the Noto Peninsula Earthquake and torrential rain disasters, renewal of river and port revetments, and six-laning of expressways, among other projects, and the number of projects using the method remained solid.」
The company added construction-method proposals and project experience related to disaster recovery, including the adoption of its methods for restoring roads damaged by the Noto Peninsula Earthquake and torrential rains. - FY2024AdvancedAnnual report
「The company received an order for abutment reinforcement work at Noto Ohashi on the Noto Satoyama Kaido for emergency restoration and contributed to the early resumption of two-way traffic using the Gyro Piler and GRB System.」
Through the activities of the Noto Reconstruction Support Office, the company received an order for abutment reinforcement work on the Noto Satoyama Kaido at Noto Ohashi and completed early restoration using the Gyro Piler and GRB System. - FY2024-Q3AdvancedAnnual report
「As part of recovery efforts following the 2024 Noto Peninsula Earthquake, the temporary office opened in Kanazawa, Ishikawa Prefecture, the Noto Reconstruction Support Office, led to a group company, 株式会社技研施工, receiving an order to construct retaining walls supporting the road as part of widening work to create two lanes for the emergency restoration of the Noto Satoyama Kaido. The work was completed using the Silent Piler F112 and the GRB System, a pile-pressing construction system. The affected areas are extensive, and inquiries regarding disaster recovery are increasing.」
Through the activities of the Noto Reconstruction Support Office, the company received an order for emergency restoration work on the Noto Satoyama Kaido and completed the work using the F112 and GRB System. Inquiries regarding recovery work are also increasing. - FY2024-Q2First statedAnnual report
「In response to the 2024 Noto Peninsula Earthquake, the company opened a temporary office in Kanazawa, Ishikawa Prefecture, in late January to support recovery and reconstruction in the affected areas. It continues to conduct field surveys and propose construction methods and technologies, and is seeing strong and growing demand for, and expectations of, its pile-pressing technology, which has enabled rapid recovery and reconstruction in disaster-affected areas in Japan and overseas. The company will contribute to the earliest possible recovery of the region by applying its proprietary technical capabilities and extensive track record.」
To support areas affected by the Noto Peninsula Earthquake, the company opened a temporary office in Kanazawa and began and continues to conduct field surveys and propose construction methods and technologies.