Construction of a building and cleanroom for equipment assembly at the Ryugasaki facility
First written in FY2024-Q2. 2 of 5 entries say "Advanced", first in FY2024. Latest entry: FY2026.
No other company in this theme has enough history to compare yet.
- FY2026AchievedAnnual report
「Through the use of the Process Development Center opened in July 2018 and the cleanroom in the new factory building completed in December 2025, among other facilities,」
The new factory building and cleanroom at the Ryugasaki facility reached completion as scheduled in December 2025. - 2026-09-03AchievedGeneral Meetings of Shareholders
「2025年12月に竣工した新工場建屋内のクリーンルームなどの活用により」
竜ケ崎事業所の新工場建屋について、計画段階の記載から2025年12月竣工済みとの記載に進んだ。 - FY2025AdvancedAnnual report
「Equipment-assembly building; planned investment: ¥2,000 million; amount paid to date: ¥714.787 million; construction start: 2025.2; scheduled completion: 2025.12; additional capacity after completion: 10% increase in production capacity」
For the equipment-assembly building project at the Ryugasaki facility, construction began in February 2025 and ¥714.787 million had been spent. The plan for a 10% increase in production capacity after completion remains unchanged. - FY2024AdvancedAnnual report
「Equipment-assembly building; planned investment: ¥2,000 million; construction start: 2025.2; scheduled completion: 2025.12; additional capacity after completion: 10% increase in production capacity」
The equipment-assembly building at the Ryugasaki facility was specified in the capital investment plan as an approximately ¥2 billion project, with construction starting in February 2025, completion scheduled for December of the same year, and production capacity expected to increase by 10% after completion. - FY2024-Q2First statedAnnual report
「The Company decided to make this capital investment to establish a sustainable production system in anticipation of future business expansion by securing production capacity and developing cleanrooms that provide an environment capable of accurately meeting customer requirements.」
Against a backdrop of expanding orders for wafer-handling systems and other products for advanced semiconductors used in generative AI, and the development of the microdisplay and nanolithography businesses, the Company decided to invest in an equipment-assembly building and cleanroom at its Ryugasaki facility. The investment, approximately ¥2 billion, is expected to be funded by internal funds and borrowings, with construction scheduled to begin in February 2025 and completion scheduled for December 2025.