Komori
Ishikawa Seisakusho (6208) · FactContinued decrease and re-recognition of provision for loss on orders receivedLatest Results (2026-11-09): "Worsened"

Recognition of a Provision for Losses on Contracts

First written in FY2023-Q2. 1 of 12 entries say "Restated". Latest entry: 2026-11-09.

12entries
5years
2from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseOtherFY2023-Q2 – FY2026-H12022: 12023: 420232024: 220242025: 220252026: 32026
Same theme, other companies
Release of the Provision for Losses on Contracts Expected to Incur LossesA theme 167 companies write about · 166 as a headwind · 1 as a tailwind

Ishikawa Seisakusho moved to the "Worse" side of this theme in 2026, 3 years after the typical company in this theme (2023).

The whole theme swung hardest in 2026: 26 of 114 companies on the "Worse" side.

26 other companies' latest entry also says "Worsened".

Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Showing 14 of the 167 companies compared. The sentences above are computed from all 167.
Full recordFilings, disclosures and news, newest first
  1. 2026-11-09WorsenedResults

    「Provision for loss on orders received 4 78」

    The provision for loss on orders received increased from ¥4 million at the end of the previous consolidated fiscal year to ¥78 million, reflecting expanded provisioning for order-related losses.
  2. FY2026Continued decrease and re-recognition of provision for loss on orders receivedAnnual report

    「Provision for contract losses — 4,000」

    The provision for contract losses increased from zero at the end of the previous fiscal year to ¥4 million, and ¥9.1 million was recognized as an expense related to the provision for contract losses in cost of sales.
  3. 2026-05-11MaterialisedResults

    「Provision for loss on orders received — 4」

    A provision for loss on orders received, which was zero at the end of the previous fiscal year, was recorded at ¥4 million at the end of the current fiscal year, marking the renewed recognition of such a provision.
  4. FY2026-H1Contract loss provision re-recognizedAnnual report

    「Provision for contract losses — 7,500」

    The provision for contract losses, which was zero at the end of the previous consolidated fiscal year, was recognized at ¥7.5 million at the end of the current interim period. It was recognized again after the provision had been eliminated at the end of the FY2025 interim period.
  5. FY2025Contract loss provision eliminatedAnnual report

    「Provision for contract losses 49,275 —」

    The provision for contract losses, which was ¥49.275 million at the end of the previous fiscal year, fell to zero at the end of the current fiscal year. The current fiscal year included no expense related to the provision for contract losses, and the provision recognized in the previous fiscal year was reversed.
  6. FY2025-H1Decrease in Provision for Losses on OrdersAnnual report

    「Provision for contract losses 49,275 1,030」

    The provision for contract losses decreased substantially from ¥49.275 million at the end of the previous consolidated fiscal year to ¥1.030 million at the end of the current interim period.
  7. FY2024-Q3Increase in the provision for loss-making ordersAnnual report

    「Provision for contract losses 23,447 49,379」

    The provision for contract losses increased from ¥23.447 million at the end of the previous consolidated fiscal year to ¥49.379 million.
  8. FY2024-Q2Increase in the provision for loss-making ordersAnnual report

    「Provision for contract losses 23,447 44,379」

    The provision for contract losses increased from ¥23.447 million at the end of the previous consolidated fiscal year to ¥44.379 million.
  9. FY2024-Q1Increase in the provision for loss-making ordersAnnual report

    「Provision for contract losses 23,447 36,569」

    The provision for contract losses increased from ¥23.447 million at the end of the previous consolidated fiscal year to ¥36.569 million. Recognition of the provision for contracts expected to incur losses in the future continued.
  10. FY2023Increase in the provision for loss-making ordersAnnual report

    「Provision for contract losses — 23,447」

    The provision for contract losses increased from zero at the end of the previous consolidated fiscal year to ¥23.447 million. The provision is recognized for contracts expected to incur losses in the future.
  11. FY2023-Q3RestatedAnnual report

    「Provision for loss on orders received - 9,545」

    Recognition of a ¥9.545 million provision for contract losses continued. The amount recognized at the end of the previous consolidated fiscal year was zero.
  12. FY2023-Q2First statedAnnual report

    「Provision for loss on orders received - 9,545」

    A provision for contract losses of ¥9.545 million was recognized in the balance sheet at the end of the second quarter, compared with zero at the end of the previous consolidated fiscal year. The statement of cash flows also shows a ¥9.545 million change in the provision for contract losses.
Moved together

"Increase in Inventories and Short-Term Borrowings" moved the same way as this thread, in the same document, in 2 of its 12 moves.

2★1
  1. ★This thread
  2. 1Increase in Inventories and Short-Term Borrowings2×

★ is this thread; numbers match the list above. The number on a line is how many documents both moved the same way in; lines between the other threads count the documents they moved together in too. Threads that move together often sit closer.

When this could move next
Ishikawa Seisakusho's next results are scheduled for 2026-11-09. Read the earnings preview It last moved in the Results of 2026-11-09: "Worsened".
News
No news is linked to this thread yet. When an article touches it, it will appear here by date.