The Takigami Steel Construction (5918) · InitiativeWorsened

Enhancing Production Capacity and Reducing Costs in the Steel-Frame Business

First written in FY2016. 11 of 30 entries say "Worsened", first in FY2020-Q3. Latest entry: FY2026.

30entries
11years
3from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseFirst statedFY2016WorsenedFY2025-H1 – 2026-05-152016: 120162017: 020172018: 320182019: 320192020: 420202021: 220212022: 420222023: 420232024: 320242025: 220252026: 42026
Same theme, other companies
Strengthening the Competitiveness and Profitability of the Core Bridge and Steel Structure BusinessesA theme 5 companies write about · 1 as a headwind · 7 as a tailwind

The Takigami Steel Construction moved to the "Worse" side of this theme in 2024.

1 other company's latest entry also says "Worsened".

Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Full recordFilings, disclosures and news, newest first
  1. FY2026WorsenedAnnual report

    「In the steel frame division, demand for steel frames remained sluggish as construction plans were reviewed and start dates postponed, reflecting cautious private-sector construction investment amid persistently high material prices and an uncertain outlook. Orders in the steel frame division were ¥2,110 million, down 52.1% year on year.」

    Demand for steel frames remained sluggish, and orders in the steel frame division declined 52.1% year on year due to reviews of construction plans and postponed starts.
  2. FY2026-H1WorsenedAnnual report

    「Steel frame construction declined substantially from the same period of the previous year because there were no new orders and the Company only worked through previously awarded projects.」

    There were no new orders for steel frame construction, and the Company only worked through previously awarded projects. At the consolidated subsidiary whose main business is steel frames, orders and production declined as the order environment deteriorated due to a review of steel frame projects and other factors, resulting in a substantial loss.
  3. FY2025WorsenedAnnual report

    「At the Company, the recording of provisions for construction losses on large-scale steel frame construction projects in the Tokyo metropolitan area and elsewhere substantially depressed profit. Completed construction revenue was ¥20,670 million, up 5.5% year on year, and the operating loss was ¥540 million, compared with operating profit of ¥420 million in the same period of the previous year.」

    Although steel frame production and completed construction revenue increased, provisions for construction losses were recorded on large-scale steel frame construction projects in the Tokyo metropolitan area and elsewhere, resulting in an operating loss of ¥540 million in the steel structure manufacturing business.
  4. FY2025-H1WorsenedAnnual report

    「In terms of profitability, higher costs due to personnel expenses, fuel costs and other factors became apparent, generally depressing margins on bridge construction. In steel frame construction, the recording of a substantial provision for construction losses on a large-scale high-rise building project significantly depressed profitability for the segment as a whole.」

    Higher costs due to personnel expenses, fuel costs and other factors depressed margins on bridge construction, while a substantial provision for construction losses was recorded for a large-scale high-rise building project. The deterioration in costs and profitability is explicitly noted despite the increase in production volume.
  5. FY2024ReframedAnnual report

    「Amid expectations of a medium- to long-term decline in orders for new bridges, we have positioned work on ultra-high-rise projects in the Tokyo metropolitan area as a challenge equivalent to launching a new business. We will steadily establish our internal structure while making capital and personnel investments, coordinate with group companies expected to be acquired through M&A, and pursue steady growth.」

    The focus of the steel frame business was expanded from its traditional power-related projects and other work to ultra-high-rise projects in the Tokyo metropolitan area, and the plan was restructured to combine capital investment, personnel investment and M&A.
  6. FY2024-Q3Large-scale steel frame production increased, but a provision for construction losses was recorded for certain projectsAnnual report

    「In the steel frame division, production increased substantially from the previous fiscal year as large-scale steel frames became the focus. In terms of profitability, provisions for construction losses were recorded for certain large-scale bridge and steel frame projects because deterioration in profitability was expected. However, at subsidiaries, improvement in construction profitability and progress on highly profitable projects resulted in completed construction revenue of ¥13,960 million, up ¥3,310 million, or 31.1%, year on year, and operating profit of ¥100 million, compared with an operating loss of ¥6 million in the same period of the previous year.」

    Although production of large-scale steel frames increased, provisions for construction losses were recorded for certain large-scale bridge and steel frame projects due to expected deterioration in profitability. Improved construction profitability at subsidiaries and other factors resulted in segment operating results moving from a loss in the same period of the previous year to profit of ¥100 million.
  7. FY2024-Q2Operating profit increased on higher revenue despite continued high costsAnnual report

    「In steel frame construction, the increase in carried-over construction projects and design changes made a significant contribution, resulting in a substantial increase from the same period of the previous year. In terms of profitability, high costs due to higher material and personnel costs, among other factors, continued, but operating profit increased because the factors driving higher revenue had a substantial impact.」

    While higher costs due to material and personnel expenses continued, increased revenue from a rise in carried-over construction projects and design changes contributed to higher operating profit.
  8. FY2024-Q1WorsenedAnnual report

    「On the other hand, operating profit declined due to higher material and personnel costs, among other factors.」

    In the steel structure manufacturing business, operating profit declined due to higher material and personnel costs, and deterioration in costs was noted in relation to the themes of production capacity and cost reduction.
  9. FY2023AdvancedAnnual report

    「As actions toward fiscal 2023, the final year of the new medium-term management plan, we will continue securing civil engineering and construction engineers and other personnel, as in the previous fiscal year. In terms of facilities, we will reorganize the production system at the head-office factory by separating the production lines for bridges and steel frames, while also renewing processing equipment such as welding machines and presses, to improve productivity and profitability.」

    Toward the final year, the Company identified the separation of the bridge and steel frame lines at the head-office factory, renewal of welding machines and presses, and improvements in productivity and profitability as specific measures.
  10. FY2023-Q3AdvancedAnnual report

    「Our factory operations remained strong, resulting in an increase in construction output.」

    Strong factory operations led to an increase in construction output.
  11. FY2023-Q2RestatedAnnual report

    「Recovery in our factory operations」

    The recovery in factory operations continues to be described as a factor contributing to improved production capacity.
  12. FY2023-Q1AdvancedAnnual report

    「The impact of COVID-19 was limited, and the operating level of our factory increased by approximately 20% year on year. The burden of indirect costs and other expenses is also gradually returning to pre-COVID levels.」

    The factory operating level increased by approximately 20% year on year, and the burden of indirect costs and other expenses is also gradually returning to pre-COVID levels. Improvement is indicated in production capacity and the burden of fixed costs.
  13. FY2022WorsenedAnnual report

    「As actions toward fiscal 2022, the second year of the new medium-term management plan, we will strengthen recruitment of civil engineering and construction engineers and secure the personnel required as the foundation of our management resources. We will also work to reduce the burden of fixed costs and restore profitability, which has declined, by recovering factory operations to pre-COVID levels and improving production efficiency.」

    Factory operations had not recovered to pre-COVID levels, and insufficient production volume due to extended construction periods and other factors, together with a higher burden of indirect costs, continued. Toward fiscal 2022, the Company identified stronger recruitment, recovery in factory operations and improved production efficiency as priorities.
  14. FY2022-Q3Factory operations recovered, but high costs continuedAnnual report

    「At the Company, factory operations recovered to normal levels from the second quarter onward as the COVID-19 situation temporarily subsided. However, the trend of higher costs on a full-year basis has continued, and we believe that improving the income statement will take time.」

    Although factory operations recovered to approximately normal levels, the full-year trend of higher costs continued, and the Company stated that improving the income statement would take time.
  15. FY2022-Q2WorsenedAnnual report

    「Because orders for construction projects linked to factory production have been weak since the previous fiscal year, sales declined and the fixed-cost ratio for indirect costs and other expenses increased, although」

    Sales declined and the fixed-cost ratio for indirect costs and other expenses rose due to weak orders for construction projects linked to factory production.
  16. FY2021-Q3AdvancedAnnual report

    「The factory operating rate, which had remained low through the first half due to the impact of COVID-19, has been gradually recovering, and this trend is expected to continue. The impact of design changes recorded in the six-month period ended the second quarter was substantial, resulting in completed construction revenue of ¥9,450 million, up ¥220 million, or 2.5%, year on year, and operating profit of ¥100 million, compared with an operating loss of ¥410 million in the same period of the previous year.」

    The factory operating rate gradually recovered from its decline, and the steel structure manufacturing business moved from an operating loss in the same period of the previous year to operating profit of ¥100 million, partly due to the impact of design changes.
  17. FY2021-Q2The decline in factory operations due to COVID-19 and the continuing burden of manufacturing costsAnnual report

    「Although the decline in the factory operating rate and other factors resulting from COVID-19 increased the fixed-cost ratio of manufacturing costs, design changes were recorded for certain expressway projects. As a result, completed construction revenue was ¥6,450 million, up ¥470 million, or 7.9%, year on year, and operating profit was ¥6 million, compared with an operating loss of ¥260 million in the same period of the previous year.」

    While the burden of fixed manufacturing costs due to the lower factory operating rate continued, operating results improved following the recognition of design changes.
  18. FY2021-Q1WorsenedAnnual report

    「Regarding quarterly results, measures to prevent COVID-19 and other factors kept the factory operating rate at approximately 50%, resulting in a substantial decline in production volume. The allocation of common costs, including indirect costs, consequently pushed up production costs. Completed construction revenue was ¥2,490 million, down ¥500 million, or 16.8%, year on year, and the operating loss was ¥280 million, compared with an operating loss of ¥40 million in the same period of the previous year.」

    Measures to prevent COVID-19 restricted the factory operating rate to approximately 50%, resulting in lower production volume and higher production costs due to the burden of fixed costs. The operating loss in the steel structure manufacturing business widened from ¥40 million in the same period of the previous year to ¥280 million.
  19. FY2020AdvancedAnnual report

    「During the fiscal year, capital expenditures included panel-line straightening machines at the Company in the steel structure manufacturing business and plasma cutting machines at subsidiary Marusada Sangyo Co., Ltd. in the materials sales business. As a result, total capital expenditures were ¥581 million, comprising ¥519 million in the steel structure manufacturing business, ¥61 million in the materials sales business and ¥0 million in the machine tools manufacturing business.」

    The steel structure manufacturing business introduced panel-line straightening machines and other equipment, resulting in capital expenditures of ¥519 million in that business.
  20. FY2020-Q3WorsenedAnnual report

    「Regarding quarterly results, in addition to the results through the second quarter, the Company was affected by lower-than-expected profitability on long-term, large-scale construction projects, among other factors. However, its subsidiaries recorded revenue steadily, resulting in completed construction revenue of ¥9,220 million, up ¥610 million, or 7.2%, year on year, and an operating loss of ¥410 million, compared with an operating loss of ¥160 million in the same period of the previous year.」

    The operating loss in the steel structure manufacturing business widened from ¥160 million in the same period of the previous year to ¥410 million, due to lower-than-expected profitability on long-term, large-scale construction projects, among other factors.
  21. FY2020-Q2Deteriorating profitability of bridge and private-sector steel-frame projectsAnnual report

    「However, operating results were affected by the recognition of a provision for construction loss due to deteriorating expected profitability on certain bridge projects, as well as deteriorating profitability in private-sector steel-frame projects. As a result, the business recorded an operating loss of ¥260 million, compared with an operating loss of ¥20 million in the same period of the previous year.」

    In the steel structure manufacturing business, a provision for construction loss was recognized due to deteriorating expected profitability on bridge projects, and profitability deteriorated on private-sector steel-frame projects.
  22. FY2020-Q1Higher costs due to labor shortages and equipment investmentsAnnual report

    「In quarterly earnings, factory operations and on-site construction remained stable, but outsourced costs, including transportation expenses, were affected by higher labor costs resulting from labor shortages, leading to an overall increase in costs. In addition, higher costs associated with new production equipment and the relocation of a subsidiary's office had a slight impact. As a result, completed construction revenue was ¥2.99 billion, up ¥310 million, or 11.6%, year on year, and the business recorded an operating loss of ¥40 million, compared with an operating loss of ¥180 million in the same period of the previous year.」

    In connection with strengthening production facilities and the staffing structure, outsourced costs including transportation expenses, higher labor costs due to labor shortages, and increased costs for new production equipment and office relocation arose, resulting in an operating loss in the steel structure manufacturing business.
  23. FY2019AdvancedAnnual report

    「The principal increases during the period were as follows: Machinery and equipment: purchase of a traveling crane, ¥125 million; machinery and equipment: purchase of a steel-frame welding robot, ¥85 million.」

    A traveling crane and a steel-frame welding robot were acquired in connection with the renewal and enhancement of the steel-frame production structure.
  24. FY2019-Q1Deteriorating profitability of large-scale steel-frame projects due to higher transportation costsAnnual report

    「In quarterly earnings, profitability deteriorated on large-scale steel-frame projects because of higher transportation and other costs, resulting in the recognition of a provision for construction loss. In addition, as on-site construction volume declined from the same period of the previous year, completed construction revenue was ¥2.68 billion, down ¥570 million, or 17.6%, year on year, and the business recorded an operating loss of ¥180 million, compared with operating income of ¥130 million in the same period of the previous year.」

    Higher transportation and other costs on large-scale steel-frame projects led to deteriorating profitability and the recognition of a provision for construction loss. This represents deterioration during the quarter against the objectives of enhancing production capacity and reducing costs.
  25. FY2018AdvancedAnnual report

    「In the steel-frame segment, efforts to selectively accept orders with an emphasis on profitability, as in the previous fiscal year, resulted in orders for projects including thermal power plants. Order intake in the steel-frame segment was ¥2.82 billion, an increase of ¥1.44 billion, or 105.1%, year on year.」

    The company continued to selectively accept orders with an emphasis on profitability, resulting in orders for projects including thermal power plants. Order intake in the steel-frame segment increased 105.1% year on year.
  26. FY2018-Q3AdvancedAnnual report

    「As the increase in fabrication man-hours incurred on certain large-scale projects subsided from autumn onward, the deterioration in profitability was brought under control, and the factory recovered to generally normal operating levels.」

    The increase in fabrication man-hours for large-scale projects subsided from autumn onward, and factory operations recovered to generally normal levels.
  27. FY2016First statedAnnual report

    「In the steel-frame business, while continuing to make orders for power-related projects a core focus, we will restructure our production facilities and staffing structure to make maximum use of our subsidiary's capabilities in order to address the steady construction demand related to the 2020 Tokyo Olympics, the Chuo Shinkansen maglev line and other projects, as in the previous year, and will work to enhance production capacity and reduce costs.」

    After identifying demand opportunities, the company cites use of its subsidiary and the restructuring of production facilities and staffing as means of addressing them.
Moved together

"Strengthening Orders for the Bridge and Maintenance Business, Primarily in Chubu and Tohoku" moved the same way as this thread, in the same document, in 16 of its 30 moves.

16129998★123456
  1. ★This thread
  2. 1Strengthening Orders for the Bridge and Maintenance Business, Primarily in Chubu and Tohoku16×
  3. 2Securing an Appropriate Order Volume and Managing Profitability through Revenue and Operating Profit12×
  4. 3Securing Order Profitability Through Technical Proposals, Design Changes and Selective Order Acceptance9×
  5. 4Profit improvement in the materials sales business driven by higher processing volumes and other factors9×
  6. 5Risk of Surging Raw Material Prices and Difficulty Passing Through Costs9×
  7. 6Expansion into New Businesses through the Acquisition of a Machine Tool Manufacturer as a Subsidiary8×

★ is this thread; numbers match the list above. The number on a line is how many documents both moved the same way in; lines between the other threads count the documents they moved together in too. Threads that move together often sit closer.

When this could move next
The Takigami Steel Construction's next results are scheduled for 2026-11-13. Read the earnings preview It last moved in the General Meeting of Shareholders of 2026-06-02: "Mitigated".
News
No news is linked to this thread yet. When an article touches it, it will appear here by date.