Implementation of a production management system for bright steel bars
First written in FY2016. 3 of 6 entries say "Advanced", first in FY2017. Latest entry: FY2026.
2 other companies' latest entry also says "Advanced".
- FY2026AdvancedAnnual report
「SANYU CO.,LTD. Osaka Prefecture Bright steel bars and steel wire for cold heading division Core system renewal ¥300 million ¥15.76 million paid to date Internal funds June 2025 October 2027 -」
Following a review of investment related to the production management system, the core system renewal has been specified as a total investment of ¥300 million, with ¥15.76 million paid to date, work commencing in June 2025 and completion scheduled for October 2027. - FY2024Re-recording of investment related to the production management systemAnnual report
「Increase in software (Hirakata Plant) Head office production management system ¥8.5 million (Kyushu Plant) Modification of Kyushu production management system ¥5.8 million」
Following the 2023 review of the development plan and impairment, ¥8.5 million for the head office production management system at the Hirakata Plant and ¥5.8 million for modifications to the Kyushu production management system are listed as increases in software. - FY2023Review of the production management system development plan and impairmentAnnual report
「The development costs for the production management system had been recorded for the above assets as software under construction included in other intangible fixed assets. Following the decision to review the development plan, the originally anticipated benefits were no longer expected, so the carrying amount was reduced to the recoverable amount, and part of the reduction was recorded as an impairment loss under extraordinary losses. The recoverable amount was measured based on value in use, but because no future cash flows were expected, the recoverable amount was assessed at zero.」
Following a review of the production management system development plan, the originally anticipated benefits and future cash flows were no longer expected, and an impairment loss of ¥13.473 million was recorded for software under construction. - FY2019AdvancedAnnual report
「Increase in tools, furniture and fixtures (Yao Plant) Production management system server ¥13.1 million」
The acquisition of a server for the production management system at the Yao Plant, costing ¥13.1 million, is listed as an increase in property, plant and equipment. The completion date itself is not stated, but investment related to the implementation is continuing. - FY2017AdvancedAnnual report
「The bright steel bar production management system was scheduled for completion in March 2017, but the expected completion date is likely to be pushed back to January 2018 due to improvements to the specifications.」
¥48.832 million was recorded for Phase 1 of the production management system, while Phase 2 is also proceeding, and the scheduled completion date was postponed to January 2018. - FY2016First statedAnnual report
「The bright steel bar production management system was scheduled for completion in January 2016, but the expected completion date is likely to be pushed back to March 2017 due to improvements to the specifications.」
The scheduled completion of the production management system implementation was postponed due to improvements to the specifications.