Improving production capacity through refurbishment of core equipment at the Tokyo Plant
First written in FY2020. 2 of 4 entries say "Advanced", first in FY2021. Latest entry: FY2024.
No other company in this theme has enough history to compare yet.
- FY2024AdvancedAnnual report
「The renewal work was completed with the construction of a new office building at the Tokyo Plant. Total investment amounted to approximately ¥1.8 billion.」
The company states that the renewal work at the Tokyo Plant, which followed the refurbishment of its core equipment, was completed with the construction of a new office building. Total investment amounted to approximately ¥1.8 billion. - FY2022AchievedAnnual report
「As an investment in the manufacturing division, the company refurbished core equipment at the Tokyo Plant, its main concrete-pile manufacturing facility. This has secured a more stable product supply system while also improving manufacturing efficiency.」
Regarding the refurbishment of core equipment at the Tokyo Plant, which had been described as a plan through the previous filing, the company states that it completed the equipment renewal, securing a stable supply system and improving manufacturing efficiency. - FY2021AdvancedAnnual report
「Tokyo Plant: equipment for manufacturing concrete piles; planned investment ¥1,450 million, amount already paid ¥517 million, work commenced February 2020, scheduled completion December 2022, post-completion capacity increase: 5% increase in production capacity」
For the refurbishment of core equipment at the Tokyo Plant, the amount already paid increased from ¥208 million in the previous disclosure to ¥517 million, indicating progress on the plan. Completion is scheduled for December 2022, with production capacity planned to increase by 5%. - FY2020First statedAnnual report
「Tokyo Plant: equipment for manufacturing concrete piles; planned investment ¥1,450 million, amount already paid ¥208 million, work commenced February 2020, scheduled completion December 2022, post-completion capacity increase: 5% increase in production capacity」
The company describes for the first time a specific refurbishment plan for concrete-pile manufacturing equipment at the Tokyo Plant, involving investment of ¥1,450 million, scheduled completion in December 2022, and a planned 5% increase in production capacity.