Establishing a New Headquarters and Software Development Center and Consolidating Development Sites
First written in FY2020-Q1. 4 of 6 entries say "Advanced", first in FY2020-Q2. Latest entry: FY2021.
0 other companies' latest entry also says "Achieved".
- FY2021AchievedAnnual report
「Relocation of the head office and software development center to improve synergies among the 3 business areas」
The Company acquired a new head office and software development center and relocated from the former head office in April 2021. The plan to consolidate dispersed sites has been completed following its implementation. - FY2021-Q3AdvancedAnnual report
「Based on a resolution of the extraordinary meeting of the Board of Directors held on 30 September 2019, the Company acquired fixed assets on 18 March 2021. Acquisition cost: ¥3,643 million」
The Company acquired fixed assets for use as its head office and software development center on 18 March 2021, at an acquisition cost of ¥3,643 million. The plan has progressed to the implementation stage involving construction and the acquisition of facilities. - FY2020AdvancedAnnual report
「Head office, software development center (provisional name) and land: ¥3,550 million; amount paid to date: ¥620 million; funding: internal funds, borrowings and equity financing; start: March 2020; completion: March 2021」
The new head office and software development center project is proceeding as a capital investment plan, with total planned investment of ¥3,550 million, ¥620 million already paid and completion scheduled for March 2021. - FY2020-Q3AdvancedAnnual report
「The entire amount is scheduled to be allocated to the acquisition of the construction site for the head office and software development center (provisional name) and part of the construction costs for the buildings.」
For the head office and software development center plan, the Company stated that proceeds from the third-party allotment associated with its listing would be used to acquire the construction site and build the facilities, and that it had also entered into an agreement to transfer the existing head office property. The planned date for transfer of ownership is 30 April 2021. - FY2020-Q2AdvancedAnnual report
「At an extraordinary meeting of the Board of Directors held on 30 September 2019, the Company resolved to enter into a land purchase agreement and a construction contract for the purpose of establishing a head office and software development center (provisional name) in Nagoya, Aichi Prefecture, and entered into the agreements on the same day.」
The plan for the head office and software development center has progressed concretely through the execution of a land purchase agreement and a construction contract. - FY2020-Q1First statedAnnual report
「The Company has acquired a site for the construction of its head office and software development center (provisional name) in the area around Nagoya Station, which is easily accessible and where infrastructure development is expected to advance further following the opening of the Linear Chuo Shinkansen in 2027. The Company will consolidate all development sites currently dispersed between the head office and the area around Nagoya Station to improve administrative efficiency and strengthen its software development capabilities.」
The Company newly disclosed a plan to consolidate the head office and dispersed development sites in the area around Nagoya Station. The total planned investment is ¥3,550 million, with construction scheduled to begin in March 2020 and be completed in March 2021.