Transfer of equipment from the Tape Anjo Plant to the Saitama Plant
First written in FY2021. 2 of 6 entries say "Advanced", first in FY2024-Q1. Latest entry: FY2024-Q3.
No other company in this theme has enough history to compare yet.
- FY2024-Q3AchievedAnnual report
「The building was completed in February 2023 and the manufacturing equipment in October 2023, and both are in full-scale operation.」
For the plan to transfer the Tape Anjo Plant equipment and buildings to the Saitama Plant, the manufacturing equipment was completed in October 2023 following completion of the building, and full-scale operation began. The investment amounted to ¥2,424 million. - FY2024-Q2AdvancedAnnual report
「Net cash used in investing activities was ¥2,330 million. This was mainly due to ¥2,244 million in expenditure for the acquisition of property, plant and equipment, including adhesive solution manufacturing equipment and buildings at the company's Saitama Plant.」
In connection with the transfer of the Tape Anjo Plant equipment to the Saitama Plant, ¥2,244 million in expenditure for the acquisition of property, plant and equipment was incurred during the cumulative second-quarter period. - FY2024-Q1AdvancedAnnual report
「The adhesive solution manufacturing equipment and buildings at the company's Saitama Plant are scheduled to begin operation in the second half of the fiscal year.」
The plan to transfer the Tape Anjo Plant equipment to the Saitama Plant has progressed to the stage where the equipment and buildings, following the delay, are scheduled to begin operation in the second half of the fiscal year. - FY2022SoftenedAnnual report
「In the plan for new equipment installations in the previous consolidated fiscal year, the scheduled completion date was August 2022, but this has been changed to March 2023.」
For the plan to transfer the Tape Anjo Plant equipment and buildings to the Saitama Plant, the scheduled completion date was postponed from August 2022 to March 2023. The planned investment is ¥2,430 million. - FY2022-Q3Increase in investment and delay in completionAnnual report
「The planned investment was ¥2,300 million, but this has been changed to ¥2,430 million. In the plan for new equipment installations in the previous consolidated fiscal year, the scheduled completion date was August 2022, but this has been changed to January 2023.」
For the plan to transfer the adhesive solution manufacturing equipment and buildings to the Saitama Plant, the planned investment was increased from ¥2,300 million to ¥2,430 million, while the scheduled completion date was postponed from August 2022 to January 2023. - FY2021First statedAnnual report
「Filing company Saitama Plant (Hidaka City, Saitama Prefecture) Tape business Adhesive solution manufacturing equipment and buildings 2,300 155 Borrowings 2021 January 2022 August *1 」
As part of the response to insufficient earthquake resistance and aging at the Tape Anjo Plant and the development of an optimal production structure, the company has disclosed for the first time a plan to transfer the adhesive solution manufacturing equipment and buildings to the Saitama Plant.