Tokushu Tokai Paper (3708) · InitiativeSoftenedLatest Financial results presentation (2026-05-20): "Advanced"
Construction of an RPF manufacturing plant
First written in FY2024. 2 of 4 entries say "Advanced", first in 2026-05-14. Latest entry: 2026-05-20.
4entries
3years
2from disclosures
How it moved
Same theme, other companies
Construction of an RPF production facility at the Makinohara FactoryA theme 1 companies write about · 0 as a headwind · 1 as a tailwind
No other company in this theme has enough history to compare yet.
Full recordFilings, disclosures and news, newest first
- FY2025SoftenedAnnual report
「RPF manufacturing plant 2,099 1,588 Borrowings 2023.5 2025.11 2,180 t/month」
The scheduled completion of the RPF manufacturing plant has changed from June 2025 to November 2025. The planned investment of ¥2,099 million and production capacity of 2,180 tonnes per month remain unchanged. - FY2024First statedAnnual report
「RPF manufacturing plant 2,099 677 Borrowings 2023.5 2025.6 2,180 t/month」
The company first specifically disclosed a plan to construct an RPF manufacturing plant at Japanese company レックス’s Makinohara Plant. The planned investment is ¥2,099 million, completion is scheduled for June 2025, and production capacity after completion will be 2,180 tonnes per month.