Construction of Rental Housing under the Crea Grace Arata II Project

First written in FY2022-Q1. 3 of 5 entries say "Advanced", first in FY2022-Q2. Latest entry: FY2023.

5entries
3years
0from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseFirst statedFY2022-Q1AdvancedFY2022-Q2 – FY20232021: 220212022: 220222023: 12023
Same theme, other companies
Construction of rental housing under Clair Grace Arata IIA theme 1 companies write about · 0 as a headwind · 1 as a tailwind

No other company in this theme has enough history to compare yet.

Full recordFilings, disclosures and news, newest first
  1. FY2023AchievedAnnual report

    「The Shinmori-Furuichi and Arata II projects, which had been planned by the filing company, were completed in January 2023, and leasing operations have begun under the names “Clare Grace Shinmori-Furuichi” and “Clare Grace Arata II.”」

    The Arata II Project was completed in January 2023, and leasing operations began under the name “Clare Grace Arata II.”
  2. FY2022AdvancedAnnual report

    「(Tentative name) Arata II Project Kagoshima City, Kagoshima Prefecture Rental housing ¥445.981 million ¥186.426 million Internal funds and borrowings April 2021 January 2023」

    The Arata II Project had planned total investment of ¥445.981 million and an amount already paid of ¥186.426 million, with payments progressing toward the scheduled completion in January 2023.
  3. FY2022-Q3AdvancedAnnual report

    「(Tentative name) Clare Grace Arata II Project Kagoshima City, Kagoshima Prefecture Rental housing ¥445.981 million ¥185.763 million Internal funds and borrowings April 2021 January 2023」

    The amount already paid for the Clare Grace Arata II Project was ¥185.763 million, an increase from the previous disclosure. Planned total investment and the scheduled completion in January 2023 remained unchanged.
  4. FY2022-Q2AdvancedAnnual report

    「(Tentative name) Clare Grace Arata II Project Kagoshima City, Kagoshima Prefecture Rental housing ¥445.981 million ¥131.644 million Internal funds and borrowings April 2021 January 2023」

    The Clare Grace Arata II Project had planned total investment of ¥445.981 million and an amount already paid of ¥131.644 million, updating the progress of the plan. The scheduled completion in January 2023 remained unchanged.
  5. FY2022-Q1First statedAnnual report

    「(Tentative name) Clare Grace Arata II Project Kagoshima City, Kagoshima Prefecture Rental housing ¥446.139 million ¥131.444 million Internal funds and borrowings April 2021 January 2023」

    A plan to construct Clare Grace Arata II in Kagoshima City was newly disclosed. Planned total investment was ¥446.139 million, the amount already paid was ¥131.444 million, and completion was scheduled for January 2023.
Moved together

"Launch of the “クレアグレイス” Rental Compact-Apartment Brand and Building Up a Portfolio of High-Quality Rental Assets" moved the same way as this thread, in the same document, in 4 of its 5 moves.

444333★123456
  1. ★This thread
  2. 1Launch of the “クレアグレイス” Rental Compact-Apartment Brand and Building Up a Portfolio of High-Quality Rental Assets4×
  3. 2Construction of Rental Housing by the Mito Project4×
  4. 3Construction of Rental Housing by the Shinmori-Furuichi Project4×
  5. 4Decline in Supply in the Market for Newly Built For-Sale Condominiums3×
  6. 5Year-on-year performance improvement3×
  7. 6Growth in earnings from the real estate leasing and management business3×

★ is this thread; numbers match the list above. The number on a line is how many documents both moved the same way in; lines between the other threads count the documents they moved together in too. Threads that move together often sit closer.

When this could move next
No upcoming earnings preview for Central General Development yet.
News
No news is linked to this thread yet. When an article touches it, it will appear here by date.