Construction of Rental Housing by the Arata Project
First written in FY2020-Q2. 4 of 6 entries say "Advanced", first in FY2020-Q3. Latest entry: FY2022-Q1.
No other company in this theme has enough history to compare yet.
- FY2022-Q1AchievedAnnual report
「As the first project, “Crea Grace Arata (Kagoshima, Kagoshima Prefecture)” was completed in February 2021, with occupancy scheduled to begin in March.」
The Arata Project was completed in February 2021, and occupancy began in March. - FY2021-Q3AdvancedAnnual report
「As the first project, “Crea Grace Arata (Kagoshima, Kagoshima Prefecture)” was completed in February 2021, with occupancy scheduled to begin in March.」
The company provided specific progress plans for the Arata Project, with completion in February 2021 and occupancy beginning in March. - FY2021-Q2AdvancedAnnual report
「(Tentative name) Matsudo Project Matsudo, Chiba Prefecture Rental housing ¥477.505 million ¥110.877 million Internal funds and borrowings April 2020 February 2022」
The amount already paid for the Matsudo Project increased from ¥20.299 million in the previous quarter to ¥110.877 million. The total planned investment of ¥477.505 million, financing with internal funds and borrowings, and scheduled completion in February 2022 remain unchanged. - FY2020AdvancedAnnual report
「(Tentative name) Arata Project Kagoshima, Kagoshima Prefecture Rental housing ¥424.755 million ¥190.293 million Internal funds and borrowings July 2019 January 2021」
The amount already paid for the Arata Project is now ¥190.293 million. The total planned investment, financing method, and scheduled start and completion dates remain unchanged. - FY2020-Q3AdvancedAnnual report
「(Tentative name) Arata Project Kagoshima, Kagoshima Prefecture Rental housing ¥424.755 million ¥190.265 million Internal funds and borrowings July 2019 January 2021」
The total planned investment for the Arata Project is now ¥424.755 million, and the amount already paid is ¥190.265 million. The financing plan using internal funds and borrowings remains unchanged, with construction scheduled to begin in July 2019 and be completed in January 2021. - FY2020-Q2First statedAnnual report
「(Tentative name) Arata Project Kagoshima, Kagoshima Prefecture Rental housing ¥420.339 million ¥145.191 million Internal funds and borrowings July 2019 January 2021」
The company disclosed a new capital investment plan to construct rental housing in Kagoshima, Kagoshima Prefecture. The total planned investment is ¥420.339 million, of which ¥145.191 million has already been paid. The project will be financed with internal funds and borrowings, with construction scheduled to begin in July 2019 and be completed in January 2021.