Full-year schedule for completion and handover of 12 properties

First written in FY2017-Q2. 15 of 34 entries say "Advanced", first in FY2017-Q3. Latest entry: FY2026.

34entries
11years
1from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseAdvancedFY2017-Q3 – FY2020-Q1AchievedFY2025 – FY20262016: 12017: 320172018: 420182019: 420192020: 420202021: 320212022: 420222023: 420232024: 320242025: 220252026: 22026
Same theme, other companies
Development of Condominium ProjectsA theme 15 companies write about · 0 as a headwind · 16 as a tailwind

The whole theme swung hardest in 2022: 2 of 14 companies on the "Worse" side.

1 other company's latest entry also says "Achieved".

Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Showing 14 of the 15 companies compared. The sentences above are computed from all 15.
Full recordFilings, disclosures and news, newest first
  1. FY2026AchievedAnnual report

    「The properties completed during the current consolidated fiscal year were the 18 properties listed below (15 in regional areas and 3 in the greater Tokyo area), all of which were completed and handed over as planned.」

    The annual plan to complete and hand over 18 properties (15 in regional areas and 3 in the greater Tokyo area) was completed as planned. Four properties were in cities entered for the first time.
  2. 2026-06-02AchievedGeneral Meetings of Shareholders

    「当社の主力事業である新築分譲マンション事業では、当初の計画どおり18物件(地方圏15物件・首都圏3物件)を竣工・引渡しいたしました。」

    FY2026の18物件の竣工・引渡し計画を完了した。
  3. FY2026-H1RaisedAnnual report

    「The company plans to complete and hand over 18 properties during the current consolidated fiscal year, mainly in regional areas (15 in regional areas and 3 in the greater Tokyo area).」

    The annual completion and handover target increased from 16 properties in the previous year to 18. The breakdown was 15 properties in regional areas and 3 in the greater Tokyo area, of which 3 had been completed as planned by the end of the first half.
  4. FY2025AchievedAnnual report

    「The properties completed during the current consolidated fiscal year were the 16 properties listed below (13 in regional areas and 3 in the greater Tokyo area), all of which were completed and handed over as planned.」

    The annual plan to complete and hand over 16 properties (13 in regional areas and 3 in the greater Tokyo area) was completed as planned.
  5. FY2025-H1Annual plan for 16 properties; 2 completed.Annual report

    「The company plans to complete and hand over 16 properties during the current consolidated fiscal year, mainly in regional areas (13 in regional areas and 3 in the greater Tokyo area). During the interim consolidated fiscal period, only 2 properties, Crea Homes Asakadai (Asaka, Saitama) and Crea Homes Toyama Shiroganemachi Grand View (Toyama, Toyama), were completed and handed over as planned.」

    The annual completion and handover plan was set at 16 properties (13 in regional areas and 3 in the greater Tokyo area), of which 2 had been completed as planned by the end of the first half.
  6. FY2024AchievedAnnual report

    「The properties completed during the current consolidated fiscal year were the 17 properties listed below, all of which were completed and handed over as planned.」

    The annual plan to complete and hand over 17 properties (4 in the greater Tokyo area and 13 in regional areas) was completed as planned. Of the 17 properties, 13 were in regional areas, including 2 in cities entered for the first time.
  7. FY2024-Q3AdvancedAnnual report

    「As a result, 8 of the 17 properties scheduled for completion and handover during the current consolidated fiscal year, comprising 13 properties in regional areas and 4 in the Tokyo metropolitan area, have been completed and handed over. The remaining 9 properties are scheduled for completion and handover in the fourth quarter consolidated accounting period.」

    Against the annual plan of 17 properties, 8 had been completed and handed over by the third quarter, with progress reaching the stage where the remaining 9 were scheduled for the fourth quarter.
  8. FY2024-Q2AdvancedAnnual report

    「The company plans to complete and hand over 17 properties during the current consolidated fiscal year, mainly in regional areas (13 in regional areas and 4 in the greater Tokyo area). During the six months ended the second quarter, a total of 5 properties were completed and handed over as planned: Crea Homes Tsukisamu Chuo Station Front (Toyohira-ku, Sapporo, Hokkaido) and Crea Homes Yamahana Residence (Chuo-ku, Sapporo, Hokkaido) during the first quarter, and Crea Homes Bancho Residence (Takamatsu, Kagawa), Crea Homes Fran Tokyo Minowa II (Taito-ku, Tokyo), and Crea Homes Urawa Tsuji Ryokudo (Minami-ku, Saitama, Saitama) during the second quarter.」

    Against the annual plan to complete and hand over 17 properties, 5 had been completed as planned by the end of the six months ended the second quarter. Progress improved from 2 properties in the first quarter.
  9. FY2024-Q1Annual plan for 17 properties; 2 completed.Annual report

    「The company plans to complete and hand over 17 properties during the current consolidated fiscal year, mainly in regional areas (13 in regional areas and 4 in the greater Tokyo area). During the three months ended the first quarter, 2 properties, Crea Homes Tsukisamu Chuo Station Front (Toyohira-ku, Sapporo, Hokkaido) and Crea Homes Yamahana Residence (Chuo-ku, Sapporo, Hokkaido), were completed and handed over as planned.」

    The annual completion and handover plan was updated to 17 properties (13 in regional areas and 4 in the greater Tokyo area), of which 2 had been completed as planned by the end of the first quarter.
  10. FY2023AchievedAnnual report

    「The properties completed during the current consolidated fiscal year were the 12 properties listed below, all of which were completed and handed over as planned.」

    The annual plan to complete and hand over 12 properties was completed as planned. Of the 12 properties, 10 were in regional areas, including 3 in cities entered for the first time.
  11. FY2023-Q3AdvancedAnnual report

    「As a result, 9 of the 12 properties scheduled for completion and handover during the current consolidated fiscal year had been completed and handed over.」

    Against the annual plan to complete and hand over 12 properties, 9 had been completed as planned by the third quarter.
  12. FY2023-Q2AdvancedAnnual report

    「The company plans to complete and hand over 12 properties during the current consolidated fiscal year. During the six months ended the second quarter, a total of 4 properties were completed and handed over as planned: Crea Homes Kochi Honmachi The Park Front (Kochi, Kochi) during the first quarter, and Crea Homes Ueda Chuo (Ueda, Nagano), Crea Homes Ushida-naka The Premium (Higashi-ku, Hiroshima, Hiroshima), and Crea Homes Fran Kitamochida (Matsuyama, Ehime) during the second quarter.」

    Against the annual plan of 12 properties, 4 had been completed and handed over as planned by the end of the six months ended the second quarter. Progress improved from 1 property completed in the previous quarter.
  13. FY2023-Q1Annual plan for 12 properties; 1 completed.Annual report

    「The company plans to complete and hand over 12 properties during the current consolidated fiscal year. During the three months ended the first quarter, 1 property, Crea Homes Kochi Honmachi The Park Front (Kochi, Kochi), was completed and handed over as planned.」

    The annual completion and handover plan was set at 12 properties, of which 1 property in Kochi had been completed as planned by the end of the first quarter. The fiscal year and planned number of properties were updated from the previous year's plan of 14 properties.
  14. FY2022AchievedAnnual report

    「The properties completed during the current consolidated fiscal year were the 14 properties listed below (compared with 12 in the previous consolidated fiscal year), all of which were completed and handed over as planned.」

    The annual plan to complete and hand over 14 properties was completed as planned.
  15. FY2022-Q3RestatedAnnual report

    「The company plans to complete and hand over 14 condominiums during the current consolidated fiscal year, mainly in regional areas. Of these, 4 were completed and handed over as planned during the six months ended the second quarter, and the remaining 10 are expected to be completed and handed over as planned during the fourth quarter.」

    Of the 14-property plan, 4 had been completed, and the remaining 10 were planned for handover in the fourth quarter. The plan was effectively unchanged from the previous quarter.
  16. FY2022-Q2AdvancedAnnual report

    「The company plans to complete and hand over 14 condominiums during the current consolidated fiscal year, mainly in regional areas, including 10 scheduled for handover in the second half. During the six months ended the second quarter, a total of 4 properties were completed and handed over as planned: Crea Homes Asaka Honcho (Asaka, Saitama) and Crea Homes Takajo Koen-mae The Premium (Kochi, Kochi) during the first quarter, and Crea Homes Dogo Midoridai The Residence (Matsuyama, Ehime) and Crea Homes Fran Sendai Itsutsubashi (Aoba-ku, Sendai, Miyagi) during the second quarter.」

    Against the annual plan to complete and hand over 14 properties, 4 had been completed as planned by the end of the six months ended the second quarter.
  17. FY2022-Q1Presented a plan for 14 properties during the year, with 2 completed.Annual report

    「The company plans to complete and hand over 14 properties during the current consolidated fiscal year. During the three months ended the first quarter, 2 properties, Crea Homes Asaka Honcho (Asaka, Saitama) and Crea Homes Takajo Koen-mae The Premium (Kochi, Kochi), were completed and handed over as planned.」

    The annual completion and handover plan was set at 14 properties, of which 2 had been completed as planned by the end of the first quarter.
  18. FY2021-Q3AdvancedAnnual report

    「Of the 12 properties scheduled for completion and handover during the current consolidated fiscal year, 10 had been completed and handed over.」

    Against the annual plan to complete and hand over 12 properties, 10 had been completed as planned by the third quarter.
  19. FY2021-Q2AdvancedAnnual report

    「As a result, all 12 properties scheduled for completion and handover during the full year had gone on sale. The properties completed and handed over during the six months ended the second quarter were the 2 properties completed during the first quarter. A further 8 properties are scheduled for completion and handover in the third quarter and 2 in the fourth quarter.」

    All properties in the full-year plan of 12 had gone on sale, and 2 had been completed and handed over by the end of the first quarter. The remaining properties were specified as 8 planned for the third quarter and 2 for the fourth quarter.
  20. FY2021-Q1Presented a plan for 12 properties during the year, with 2 completed.Annual report

    「The company plans to complete and hand over 12 properties during the current consolidated fiscal year. During the three months ended the first quarter, 2 properties, Crea Homes Fushimi (Chuo-ku, Sapporo, Hokkaido) and Crea Homes Miyazakidai (Miyamae-ku, Kawasaki, Kanagawa), were completed and handed over as planned.」

    The annual plan was updated from 10 properties in the previous year to 12 properties in the current year, and 2 properties had been completed and handed over as planned by the end of the first quarter.
  21. FY2020AchievedAnnual report

    「The properties completed during the current consolidated fiscal year were the 10 properties listed below, all of which were completed and handed over as planned.」

    The annual plan to complete and hand over 10 properties was completed as planned.
  22. FY2020-Q3AdvancedAnnual report

    「As a result, 7 of the 10 properties scheduled for completion and handover during the current consolidated fiscal year had been completed and handed over.」

    Against the annual plan to complete and hand over 10 properties, 7 had been completed and handed over by the third quarter.
  23. FY2020-Q2Presented a plan to complete and hand over 10 properties during the year.Annual report

    「The company plans to complete and hand over 10 properties during the current consolidated fiscal year, and sales contracts with customers are progressing smoothly.」

    The annual completion and handover plan was set at 10 properties, and sales contracts were reported to be progressing smoothly. The fiscal year and planned number of properties were updated from the previous year's plan of 13 properties.
  24. FY2020-Q1AdvancedAnnual report

    「During the three months ended the first quarter, 2 properties, Crea Homes Makuhari Station Front (Hanamigawa-ku, Chiba, Chiba) and Crea Homes Kotoni Parkside (Nishi-ku, Sapporo, Hokkaido), were completed and handed over.」

    Two properties, Makuhari Station Front and Kotoni Parkside, were completed and handed over in the first quarter. The document does not state the number of properties planned for the full year.
  25. FY2019AchievedAnnual report

    「The properties completed during the current consolidated fiscal year were the 13 properties listed below, all of which were completed and handed over as planned.」

    The full-year plan to complete and hand over 13 properties was completed as planned.
  26. FY2019-Q3AdvancedAnnual report

    「The completion and handover of 13 condominium properties is planned for the current consolidated fiscal year (5 in the greater Tokyo area and 8 in regional areas). As planned, 4 properties had been completed and handed over by the end of the nine months ended the third quarter. The remaining 9 properties are scheduled for completion and handover in the fourth quarter.」

    Against the full-year plan of 13 properties, 4 had been completed and handed over as planned by the end of the nine months ended the third quarter, with the remaining 9 scheduled for the fourth quarter.
  27. FY2019-Q2AdvancedAnnual report

    「Of the 13 properties scheduled for completion and handover during the current consolidated fiscal year, 12 have already gone on sale. Sales of the remaining property, Crea Homes Kawasaki The Front (Saiwai-ku, Kawasaki, Kanagawa), also began in October.」

    Of the 13 full-year properties, 12 had already gone on sale, and sales of the remaining property were scheduled to begin in October. The completion and handover of 9 properties is planned for the fourth quarter.
  28. FY2019-Q1AdvancedAnnual report

    「The completion and handover of 13 condominium properties is planned for the current consolidated fiscal year (5 in the greater Tokyo area and 8 in regional areas), most of which are concentrated in the six months ending in the fourth quarter.」

    The full-year plan of 13 properties was broken down into 5 in the greater Tokyo area and 8 in regional areas, with 2 properties at Musashi-Urawa completed and handed over in the first quarter.
  29. FY2018AchievedAnnual report

    「As originally planned, we completed and delivered 13 properties (3 in the Tokyo metropolitan area and 10 in regional areas).」

    The full-year plan to complete and hand over 13 properties was completed as planned, comprising 3 properties in the greater Tokyo area and 10 in regional areas.
  30. FY2018-Q3AdvancedAnnual report

    「The company plans to complete and hand over 13 condominium properties during the current consolidated fiscal year, including 6 properties in the fourth quarter consolidated accounting period, and will continue to focus on sales.」

    Against the full-year plan of 13 properties, 6 were completed and handed over in the third quarter, with the remaining 6 planned for the fourth quarter.
  31. FY2018-Q2AdvancedAnnual report

    「The completion and handover of 13 condominium properties is planned for the current consolidated fiscal year, but only 1 new property was completed and handed over during the six months ended the second quarter.」

    Against the full-year plan of 13 properties, 1 new property had been completed and handed over by the end of the six months ended the second quarter.
  32. FY2018-Q1RaisedAnnual report

    「For the current consolidated fiscal year, the completion and handover of 13 condominium properties is planned (3 in the greater Tokyo area and 10 in regional areas).」

    The full-year completion and handover plan increased from 12 to 13 properties, with a breakdown of 3 in the greater Tokyo area and 10 in regional areas.
  33. FY2017-Q3AdvancedAnnual report

    「The company plans to complete and hand over 12 apartment properties during the current fiscal year. Of these, 6 were completed and handed over during the cumulative nine-month period of the current fiscal year, but progress in handovers has been somewhat delayed against a backdrop of rising selling prices.」

    The update states that 6 properties had been completed and handed over against the full-year plan of 12 properties. It also notes that progress was somewhat behind schedule due to rising selling prices.
  34. FY2017-Q2First statedAnnual report

    「The company plans to complete and hand over 12 apartment properties during the current fiscal year, comprising 5 properties in the Tokyo metropolitan area and 7 properties in regional areas.」

    The company explicitly stated its plan to complete and hand over a total of 12 properties during the current fiscal year, comprising 5 properties in the Tokyo metropolitan area and 7 properties in regional areas.
Moved together

"Resilient Office Demand and Rising Rents" moved the same way as this thread, in the same document, in 15 of its 34 moves.

151515131211★123456
  1. ★This thread
  2. 1Resilient Office Demand and Rising Rents15×
  3. 2Year-on-year performance improvement15×
  4. 3Joint and Several Guarantee Obligations Related to Customer Mortgages15×
  5. 4Growth in earnings from the real estate leasing and management business13×
  6. 5Regionally Diversified Development and Expansion into Surrounding Cities Using a Nationwide Hub Portfolio12×
  7. 6Changes in Financial Structure Due to Higher Liabilities and Lower Net Assets11×

★ is this thread; numbers match the list above. The number on a line is how many documents both moved the same way in; lines between the other threads count the documents they moved together in too. Threads that move together often sit closer.

When this could move next
No upcoming earnings preview for Central General Development yet. It last moved in the General Meetings of Shareholders of 2026-06-02: "Achieved".
News
No news is linked to this thread yet. When an article touches it, it will appear here by date.
Full-year schedule for completion and handover of 12 properties | CENTRAL GENERAL DEVELOPMENT CO.,LTD. (3238) | Komori