Construction of rental housing by the Kishisato Project
First written in FY2024-Q1. 2 of 4 entries say "Advanced", first in FY2024-Q2. Latest entry: FY2025.
No other company in this theme has enough history to compare yet.
- FY2025AchievedAnnual report
「The planned (working title) Kishisato Project was completed in December 2024, and the planned (working title) Kamoike Project was completed in March 2025. Both began operations as rental properties under the names "Crea Grace Kishisato" and "Crea Grace Kamoike," respectively.」
The Kishisato Project was completed in December 2024 and the Kamoike Project in March 2025, and both began operations as rental properties. - FY2024-Q3AdvancedAnnual report
「Reporting company (working title) Kishisato Project Nishinari-ku, Osaka, Osaka Prefecture Rental housing 474,926 156,503 Equity and borrowings April 2023 December 2024」
The Kishisato Project had a planned total investment of ¥474.926 million and cumulative payments of ¥156.503 million, with payments progressing from the previous quarter. The planned completion date of December 2024 remains unchanged. - FY2024-Q2AdvancedAnnual report
「Reporting company (working title) Kishisato Project Nishinari-ku, Osaka, Osaka Prefecture Rental housing 471,080 114,313 Equity and borrowings April 2023 December 2024」
The Kishisato Project had a planned total investment of ¥471.080 million and cumulative payments of ¥114.313 million, up from ¥109.985 million in the previous quarter as payments progressed. The planned completion date of December 2024 remains unchanged. - FY2024-Q1First statedAnnual report
「(tentative name) Kishisato Project Nishinari-ku, Osaka City, Osaka Prefecture Rental housing 471,275 109,985 Internal funds and borrowings April 2023 December 2024」
The Company disclosed a new capital investment plan to construct rental housing in Nishinari-ku, Osaka City. Total planned investment is ¥471.275 million, of which ¥109.985 million has been paid. The project will be funded with internal funds and borrowings, with construction scheduled to begin in April 2023 and be completed in December 2024.