Construction of rental housing under the Kamoike Project

First written in FY2024-Q1. 3 of 5 entries say "Advanced", first in FY2024-Q2. Latest entry: FY2025.

5entries
3years
0from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseAdvancedFY2024-Q2 – FY20252023: 220232024: 220242025: 12025
Same theme, other companies
Construction of rental housing under the Kamoike projectA theme 1 companies write about · 0 as a headwind · 1 as a tailwind

No other company in this theme has enough history to compare yet.

Full recordFilings, disclosures and news, newest first
  1. FY2025AchievedAnnual report

    「The planned (working title) Kishisato Project was completed in December 2024, and the planned (working title) Kamoike Project was completed in March 2025. Both began operations as rental properties under the names "Crea Grace Kishisato" and "Crea Grace Kamoike," respectively.」

    The Kamoike Project was completed in March 2025 and began operations as a rental property under the name "Crea Grace Kamoike."
  2. FY2024AdvancedAnnual report

    「(Working title) Kamoike Project Kagoshima, Kagoshima Prefecture Rental housing 462,977 164,833 Equity and borrowings April 2023 February 2025」

    Cumulative payments for the Kamoike Project increased from ¥114.583 million in the previous quarter to ¥164.833 million. The planned total investment and completion date were updated, with completion now scheduled for February 2025.
  3. FY2024-Q3AdvancedAnnual report

    「Reporting company (working title) Kamoike Project Kagoshima, Kagoshima Prefecture Rental housing 453,568 114,583 Equity and borrowings April 2023 January 2025」

    The Kamoike Project had a planned total investment of ¥453.568 million and cumulative payments of ¥114.583 million, with payments progressing from the previous quarter. The planned completion date of January 2025 remains unchanged.
  4. FY2024-Q2AdvancedAnnual report

    「Reporting company (working title) Kamoike Project Kagoshima, Kagoshima Prefecture Rental housing 453,568 107,583 Equity and borrowings April 2023 January 2025」

    The Kamoike Project had a planned total investment of ¥453.568 million and cumulative payments of ¥107.583 million, a substantial increase from ¥12.830 million in the previous quarter. The planned completion date of January 2025 remains unchanged.
  5. FY2024-Q1First statedAnnual report

    「(Working title) Kamoike Project Kagoshima, Kagoshima Prefecture Rental housing 452,083 12,830 Equity and borrowings April 2023 January 2025」

    A new capital investment plan to construct rental housing in Kagoshima was disclosed. The planned total investment is ¥452.083 million, of which ¥12.830 million has been paid. Funding will comprise equity and borrowings, with construction scheduled to begin in April 2023 and completion planned for January 2025.
Moved together

"Full-year schedule for completion and handover of 12 properties" moved the same way as this thread, in the same document, in 4 of its 5 moves.

433333★123456
  1. ★This thread
  2. 1Full-year schedule for completion and handover of 12 properties4×
  3. 2Regionally Diversified Development and Expansion into Surrounding Cities Using a Nationwide Hub Portfolio3×
  4. 3Efficient Working Capital Funding Framework3×
  5. 4Launch of the “クレアグレイス” Rental Compact-Apartment Brand and Building Up a Portfolio of High-Quality Rental Assets3×
  6. 5Strengthening Product Development Capabilities in Environmental Protection, Disaster Preparedness and Post-COVID-19 Response3×
  7. 6Construction of rental housing by the Kishisato Project3×

★ is this thread; numbers match the list above. The number on a line is how many documents both moved the same way in; lines between the other threads count the documents they moved together in too. Threads that move together often sit closer.

When this could move next
No upcoming earnings preview for Central General Development yet.
News
No news is linked to this thread yet. When an article touches it, it will appear here by date.