Expanding Sales Regions Through New Factory Construction and Managing Profitability by Business Segment
First written in FY2017-Q1. 16 of 19 entries say "Advanced", first in FY2017-Q2. Latest entry: FY2026.
The whole theme swung hardest in 2019: 1 of 7 companies on the "Worse" side.
2 other companies' latest entry also says "Advanced".
- FY2026AdvancedAnnual report
「In the Processed Foods Business Division, we invested to expand production capacity at each plant.」
To expand production capacity at each plant, the Company made capital investments of ¥9,681 million in the Processed Foods Business Division and ¥1,098 million in the Meat Business Division. - FY2024-Q3RestatedAnnual report
「The newly rebuilt Kagoshima Plant began full-scale operations this spring and is contributing to the stable supply of existing products and the launch of new products.」
The Company reconfirms that, following the start of full-scale operations at the Kagoshima Plant, it is contributing to a stable supply and the provision of new products. - FY2024-Q1AdvancedAnnual report
「The newly rebuilt Kagoshima Plant began full-scale operations this spring and is contributing to the stable supply of products.」
The new Kagoshima Plant began full-scale operations and advanced to the stage of contributing to a stable supply of products. - FY2023AdvancedAnnual report
「In the Processed Foods Business Division, the new Kagoshima Plant began operations in fiscal 2022. The new Kagoshima Plant received capital investment, including the introduction of state-of-the-art equipment, to expand locally produced products and automate production lines,」
The new Kagoshima Plant began operations in fiscal 2022, advancing the development of its supply system through expanded locally produced products, automated production lines and the introduction of state-of-the-art equipment. - FY2023-Q2AdvancedAnnual report
「Net cash used in investing activities was ¥5,797 million, compared with net cash used of ¥15,784 million in the same period of the previous year. The main factors were ¥9,760 million in payments for the acquisition of property, plant and equipment for the renewal of production equipment, productivity improvements and quality stabilization, and ¥5,000 million in proceeds from the refund of deposits with affiliated companies.」
Investment in plant and production-related equipment progressed, with ¥9,760 million in expenditures for the acquisition of property, plant and equipment for production equipment upgrades and other purposes. Property, plant and equipment increased by ¥3,622 million from the beginning of the fiscal year. - FY2022AdvancedAnnual report
「Prima Meat Packers,Ltd.; Kagoshima Plant (Nishisatsucho, Ichikikushikino); Processed Foods Business Division; construction of a new plant; ¥13,000 million; ¥3,280 million; internal funds; 2021; fiscal 2022」
The Company disclosed a capital investment plan for the new Kagoshima Plant, with total planned investment of ¥13 billion, payments to date of ¥3,280 million, and completion scheduled for fiscal 2022. - FY2022-Q2AdvancedAnnual report
「This was mainly due to increases of ¥5,315 million in construction in progress and ¥5,217 million in inventories, and decreases of ¥4,987 million in deposits and ¥3,078 million in cash and deposits.」
Construction in progress increased by ¥5,315 million, indicating that investment in equipment and plants is under way. - FY2021AdvancedAnnual report
「Following the new Ibaraki Plant, construction of a new plant at the Kagoshima Plant will begin in fiscal 2021. The new Kagoshima Plant will receive capital investment, including the introduction of state-of-the-art equipment, to expand locally produced products and automate production lines.」
Following the start of operations at the new Ibaraki Plant, the Company is proceeding with construction of a new Kagoshima Plant. Planned investment is ¥13 billion, with construction beginning in 2021 and completion scheduled for fiscal 2022. The plan includes expanding locally produced products, automating production lines and introducing state-of-the-art equipment. - FY2020-Q3RestatedAnnual report
「In addition, the new Ibaraki Plant began full-scale operations in July, and the establishment of the production system and other preparations proceeded smoothly.」
Following the start of full-scale operations at the new Ibaraki Plant, the Company continues to establish its production system. - FY2020-Q2AdvancedAnnual report
「In addition, the new Ibaraki Plant began full-scale operations in July, and the establishment of the production system and other preparations proceeded smoothly.」
The new Ibaraki Plant began full-scale operations in July 2019, and preparations advanced to the establishment of the production system. - FY2020-Q1AdvancedAnnual report
「In addition, the ham and bacon plant at the Ibaraki Plant was completed, and preparations for full-scale production proceeded smoothly.」
The ham and bacon plant at the Ibaraki Plant was completed, and preparations advanced to the full-scale production stage. - FY2019AdvancedAnnual report
「Under the cost structure reform, the challenge will be to ensure stable operation of the new ham and bacon plant at the Ibaraki Plant, which is scheduled to begin operations in July this year. The plant was designed with consideration for the environment and is also a key element of our new growth strategy.」
The new ham and bacon plant at the Ibaraki Plant is scheduled to begin operations in July 2019, and the focus has shifted to ensuring stable operation. - FY2019-Q2AdvancedAnnual report
「The main factors were ¥7,911 million in expenditures for the acquisition of property, plant and equipment, including investment in new plant facilities and production equipment upgrades to improve productivity and stabilize quality, ¥1,199 million in expenditures for the acquisition of a business, and ¥1,084 million in expenditures for the acquisition of shares in subsidiaries resulting in a change in the scope of consolidation.」
Expenditures for the acquisition of property, plant and equipment for new plant investment, production equipment upgrades and other purposes totaled ¥7,911 million, indicating progress in capital investment and expenditures associated with business expansion. - FY2018AdvancedAnnual report
「Filing company: Ibaraki Plant (Tsuchiura, Ibaraki Prefecture); Processed Foods Business Headquarters; construction of a new plant and upgrades to production equipment, etc.; ¥18,000 million; ¥4,006 million; internal funds and leases; 2017; 2019」
The Company disclosed planned total investment of ¥18 billion, payments to date of ¥4,006 million, and scheduled completion in 2019 for the new plant at the Ibaraki Plant. Construction of the Sagamihara No. 2 Plant and Hirakata Plant is also under way. - FY2018-Q2AdvancedAnnual report
「The main factor was ¥7,883 million in expenditures for the acquisition of property, plant and equipment, including investment in new plant facilities and production equipment upgrades to improve productivity and stabilize quality.」
The Company acquired property, plant and equipment, including investment in new plant facilities, and capital investment is progressing as a specific expenditure. - FY2017AdvancedAnnual report
「Filing company: Ibaraki Plant (Tsuchiura, Ibaraki Prefecture); Processed Foods Business Headquarters; construction of a new plant; ¥18,000 million; internal funds and leases; 2017; 2019」
The Company disclosed a specific capital investment plan for the new plant at the Ibaraki Plant, with total planned investment of ¥18 billion, construction beginning in 2017 and completion scheduled for 2019. - FY2017-Q3AdvancedAnnual report
「In addition, the new wiener plant at the Ibaraki Plant, which began operations in June 2016, performed well after taking on the planned volume for the autumn peak demand season.」
The new wiener plant at the Ibaraki Plant took on the planned volume for the autumn peak demand season and operated successfully. - FY2017-Q2AdvancedAnnual report
「In addition, the new wiener plant at the Ibaraki Plant began operations in June this year. We established a production system for the peak demand season in autumn while also building an environmentally conscious operating structure.」
The new wiener plant at the Ibaraki Plant began operations in June 2016, and preparations for the production system for the autumn demand season proceeded. - FY2017-Q1First statedAnnual report
「To respond flexibly to the policies of the relevant business partners as sales regions expand following the construction of new plants, the Company introduced a divisional structure from the first quarter of the current fiscal year and is managing the profitability of each division in greater detail.」
The relationship among the construction of a new plant, the expansion of sales regions and the introduction of a divisional structure at certain consolidated subsidiaries is explained.