Komori
Tokyo Energy & Systems (1945) · RiskMitigated

Risk of construction work suspensions, project schedule extensions and worsening order conditions due to COVID-19

First written in FY2020. 3 of 8 entries say "Materialised", first in FY2021-Q3. Latest entry: FY2024-Q1.

8entries
4years
0from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseMaterialisedFY2021-Q3 – FY2022-Q1RestatedFY2022-Q22020: 320202021: 420212022: 020222023: 12023
Same theme, other companies
Delays in Real Estate Transactions and Construction Negotiations Due to COVID-19A theme 29 companies write about · 29 as a headwind · 0 as a tailwind

5 other companies' latest entry also says "Mitigated".

Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Showing 14 of the 29 companies compared. The sentences above are computed from all 29.
Full recordFilings, disclosures and news, newest first
  1. FY2024-Q1MitigatedAnnual report

    「Japan's economy saw signs of recovery in capital investment and corporate earnings as social and economic activity moved toward normalization following the reclassification of COVID-19 as a Category 5 disease under the Infectious Diseases Act.」

    Stated that social and economic activity is moving toward normalization following the reclassification of COVID-19 as a Category 5 disease under the Infectious Diseases Act.
  2. FY2022-Q2RestatedAnnual report

    「Although Japan's economy remains in a difficult situation due to the impact of COVID-19,」

    Stated that the impact of COVID-19 on the economic environment continues.
  3. FY2022-Q1MaterialisedAnnual report

    「The business environment surrounding our Group remains challenging, as competition for orders for power-related infrastructure construction has intensified and private-sector capital investment has contracted or been postponed due to the COVID-19 pandemic.」

    The contraction and postponement of private-sector capital investment due to the impact of the COVID-19 pandemic actually occurred and was described as a factor contributing to deterioration in the order environment.
  4. FY2021MaterialisedAnnual report

    「Revenue amounted to ¥5,951.4 million, down 10.5% year on year, despite progress on cogeneration equipment construction and safety-related work at nuclear power plants, due mainly to a decline from the previous fiscal year in construction work for large-scale thermal power and solar power equipment, as well as the postponement or cancellation of customers' construction plans because of the spread of COVID-19.」

    Customer construction plan delays and cancellations related to the spread of COVID-19 also occurred during the full year, and net sales decreased 10.5% from the previous fiscal year.
  5. FY2021-Q3MaterialisedAnnual report

    「Meanwhile, sales were ¥39,657 million, down 11.6% year on year, as construction work for nuclear power generation facilities' safety measures and cogeneration facilities increased, but construction work for thermal power generation facilities and solar power generation facilities declined, while construction plans were postponed or cancelled due to the spread of COVID-19.」

    Construction plan delays and cancellations related to the spread of COVID-19 actually occurred, and net sales decreased 11.6% year on year.
  6. FY2021-Q2RestatedAnnual report

    「There have been no material changes to the assumptions described in the additional information to the securities report for the previous fiscal year, including assumptions regarding the future spread of COVID-19 and the timing of its end.」

    Stated that there have been no material changes to the assumptions underlying accounting estimates concerning the spread of COVID-19 and the timing of its end.
  7. FY2021-Q1WorsenedAnnual report

    「Japan's economy is experiencing constrained economic activity due to the spread of COVID-19 and the resulting calls for people to refrain from going out, with corporate earnings and personal consumption declining rapidly. The outlook is extremely uncertain.」

    Described the constraints on economic activity and rapid declines in corporate earnings and personal consumption resulting from the spread of COVID-19, and characterized the outlook as extremely uncertain.
  8. FY2020First statedAnnual report

    「As the timing of the end of the global spread of COVID-19 remains uncertain, construction suspensions and project delays, as well as deterioration in the order environment due to the stagnation of economic activity, are among the potential impacts. If these risks materialize, they could have a material impact on the operating results and other aspects of the Group's performance.」

    For the global spread of COVID-19, specifically disclosed for the first time the risks of construction suspensions, project delays and deterioration in the order environment.
Moved together

"Decline in construction volume due to the decommissioning of obsolete thermal power plants and the extension of periodic inspection cycles" moved the same way as this thread, in the same document, in 3 of its 8 moves.

322★123
  1. ★This thread
  2. 1Decline in construction volume due to the decommissioning of obsolete thermal power plants and the extension of periodic inspection cycles3×
  3. 2Deteriorating order environment due to electricity policy, reduced capital investment in facilities, and natural disasters2×
  4. 3Intensifying Cost Competition for Orders from Incumbent Electric Utilities Following the Full Liberalization of Electricity Retailing2×

★ is this thread; numbers match the list above. The number on a line is how many documents both moved the same way in; lines between the other threads count the documents they moved together in too. Threads that move together often sit closer.

When this could move next
Tokyo Energy & Systems's next results are scheduled for 2026-11-05. Read the earnings preview
News
No news is linked to this thread yet. When an article touches it, it will appear here by date.