- FY2026AdvancedAnnual report
「Total capital investment during the consolidated fiscal year was ¥1,436 million. The main investments were software related to the development of the next-generation ERP (enterprise resource planning system) to promote DX and improve operational efficiency, and improvements to the work environment to create an attractive workplace.」
The main uses of the ¥1,436 million in capital investment have shifted to the next-generation ERP for DX and operational efficiency and improvements to the work environment. - FY2025Continued expansion of capital investment into demonstration facilities and the work environmentAnnual report
「Total capital investment during the consolidated fiscal year was ¥791 million. The main investments were the construction of demonstration-test facilities aimed at achieving carbon neutrality, improvements to the work environment to create an attractive workplace, and the construction of rental housing in the real estate business.」
The main uses of the ¥791 million in capital investment were carbon-neutral demonstration facilities, improvements to the work environment and rental housing construction. - FY2024AdvancedAnnual report
「Total capital investment during the consolidated fiscal year was ¥1,024 million. The main investments were the construction of demonstration-test facilities aimed at achieving carbon neutrality and improvements to the work environment to create an attractive workplace.」
The main uses of the ¥1,024 million in capital investment were carbon-neutral demonstration-test facilities and improvements to the work environment. - FY2023AdvancedAnnual report
「Total capital investment during the consolidated fiscal year was ¥3,933 million. The main investment was the construction of the Sakaiminato Biomass Power Plant in Sakaiminato, Tottori Prefecture, which began commercial operations in October 2022.」
The company recorded total capital investment of ¥3,933 million, completing construction of the Sakaiminato Biomass Power Plant and commencing commercial operations. - FY2023-Q3AdvancedAnnual report
「Sakaiminato Energy Power GK Sakaiminato Biomass Power Plant (Sakaiminato, Tottori Prefecture) Power generation facility 11,203 Internal funds and borrowings October 2022」
The company disclosed construction-related costs of ¥11,203 million for the completed portion of the new Sakaiminato Biomass Power Plant facility project, with commercial operations scheduled to begin in October 2022. - FY2022AdvancedAnnual report
「Total capital investment during the consolidated fiscal year was ¥6,323 million. The main investment was the construction of the Sakaiminato Biomass Power Plant in Sakaiminato, Tottori Prefecture, which was scheduled to begin commercial operations during fiscal 2022.」
Capital investment totaled ¥6,323 million, with construction of the Sakaiminato Biomass Power Plant as the main investment. - FY2017First statedAnnual report
「Total capital investment during the consolidated fiscal year was ¥1,105 million. The main investments were the construction of an office serving as a base for Fukushima reconstruction in Okuma, Futaba District, Fukushima Prefecture, and the purchase of machinery, equipment, tools and fixtures to improve construction capabilities.」
The main components of the ¥1,105 million in capital investment were the construction of an office serving as a reconstruction base in Okuma, Fukushima Prefecture, and the purchase of machinery, equipment, tools and fixtures to improve construction capabilities.