Construction and Operation of the Sakaiminato Biomass Power Plant

First written in FY2020-Q2. 8 of 14 entries say "Advanced", first in FY2020. Latest entry: FY2026.

14entries
8years
0from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseAdvancedFY2020 – FY2023AdvancedFY2024 – FY20262019: 12020: 220202021: 120212022: 220222023: 420232024: 220242025: 120252026: 12026
Same theme, other companies
Construction and Start of Operations of Biomass Power PlantsA theme 11 companies write about · 1 as a headwind · 21 as a tailwind

2 other companies' latest entry also says "Advanced".

Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Full recordFilings, disclosures and news, newest first
  1. FY2026AdvancedAnnual report

    「In the biomass field, the company provides O&M (operations and maintenance) services for biomass power plants across Japan and, together with the biomass power plant of Sakaiminato Energy Power GK, is working to improve its capabilities in equipment diagnostics and performance analysis as the plants continue operating smoothly. It is also advancing research and development into applying CCUS (carbon capture, utilisation and storage) to biomass power generation jointly with startup companies.」

    The company is expanding its biomass business from ongoing O&M operations to improving its equipment diagnostics and performance analysis capabilities and conducting CCUS research and development with startups.
  2. FY2025AdvancedAnnual report

    「In the biomass field, biomass power plants across Japan for which the company had undertaken O&M (operations and maintenance) services have commenced commercial operations. Together with the biomass power plant of the company's subsidiary, Sakaiminato Energy Power GK, which has been in commercial operation for 2 years, they have continued operating smoothly without any major problems.」

    The Sakaiminato Biomass Power Plant has been in commercial operation for 2 years and continues operating without any major problems, together with the O&M-contracted power plants across Japan.
  3. FY2024AdvancedAnnual report

    「The biomass power plant of the company's subsidiary, Sakaiminato Energy Power GK, has continued operating smoothly without any major problems.」

    The Sakaiminato Biomass Power Plant has continued operating smoothly without any major problems since the start of commercial operations.
  4. FY2024-Q3RestatedAnnual report

    「Meanwhile, revenue amounted to ¥63.648 billion, up 11.3% year on year, due to progress on construction of biomass power plants, renovation work at hydroelectric power plants and decommissioning-related work at Fukushima Daiichi Nuclear Power Station, as well as electricity sales revenue from the Group's own biomass power plant, which began commercial operations in October 2022.」

    The company's biomass power plant continues to generate electricity sales revenue after the start of commercial operations, and the company continues its efforts in biomass construction and operations.
  5. FY2024-Q2RestatedAnnual report

    「Net sales amounted to ¥4.1344 billion, up 9.5% year on year, supported by progress in construction work for biomass power plants, renewal work for large-scale power generation facilities at steelworks and work related to the decommissioning of the Fukushima Daiichi Nuclear Power Station, as well as electricity sales revenue from the group's own biomass power plant, which began commercial operations last October.」

    Electricity sales revenue from the Sakaiminato Biomass Power Plant after the start of commercial operations continued to contribute to revenue for the cumulative second quarter of the fiscal year.
  6. FY2024-Q1Recorded electricity sales revenue after the start of commercial operationsAnnual report

    「Revenue was ¥20,295 million, up 6.8% year on year, due to decommissioning-related work at the Fukushima Daiichi Nuclear Power Station, progress in repair and maintenance work for thermal power generation equipment, and revenue from electricity sales at the Group’s own biomass power plant, which began commercial operation in October of the previous year.」

    Electricity sales revenue from the Sakaiminato Biomass Power Plant after the start of commercial operations contributed to revenue for the quarter.
  7. FY2023AchievedAnnual report

    「The woody biomass power plant being constructed by the company's subsidiary, Sakaiminato Energy Power GK, in Sakaiminato, Tottori Prefecture, commenced commercial operations in October 2022.」

    The Sakaiminato Biomass Power Plant commenced commercial operations in October 2022, achieving a key milestone in its construction and operation plan.
  8. FY2023-Q3AdvancedAnnual report

    「The projects completed during the cumulative third quarter of the fiscal year among the plans for new construction and other work on major facilities at the end of the previous consolidated fiscal year are as follows.」

    The new construction plan for the Sakaiminato Biomass Power Plant was disclosed as completed during the cumulative third quarter of the fiscal year, with commercial operations scheduled to begin in October 2022.
  9. FY2022AdvancedAnnual report

    「The woody biomass power plant being constructed by the company's subsidiary, Sakaiminato Energy Power GK, in Sakaiminato, Tottori Prefecture, began trial operations in July of this year as planned, and construction is progressing steadily toward the commencement of commercial operations during fiscal 2022.」

    Construction of the Sakaiminato Biomass Power Plant is progressing toward the start of trial operations in July 2022 and the transition to commercial operations during fiscal 2022.
  10. FY2022-Q3AdvancedAnnual report

    「Orders received during the nine-month period ended 31 December increased to ¥81,636 million, compared with ¥42,199 million in the same period of the previous year, due to increases in construction work for thermal power generation equipment transferred from Hitachi Plant Construction Co., Ltd., decommissioning-related work at the Fukushima Daiichi Nuclear Power Station, and long-term operations and maintenance contracts for biomass power plants.」

    The increase in long-term operation and maintenance contracts for biomass power plants demonstrated the company's track record of orders in the operation and maintenance area of the biomass business.
  11. FY2021AdvancedAnnual report

    「In December 2020, the Group began construction of a company-owned woody biomass power plant in Sakaiminato, Tottori Prefecture, with the aim of commencing commercial operations during fiscal 2022, as part of its efforts to reduce CO2 emissions and achieve carbon neutrality on a global scale.」

    Construction of the Sakaiminato Biomass Power Plant began in December 2020, with the project progressing toward the commencement of commercial operations during fiscal 2022.
  12. FY2020AdvancedAnnual report

    「Regarding the woody biomass power generation business in Sakaiminato, Tottori Prefecture, the company is proceeding with construction work with the aim of commencing commercial operations during fiscal 2022, as part of its efforts to expand renewable energy in line with global initiatives to reduce CO2 emissions and achieve carbon neutrality.」

    Construction of the Sakaiminato Biomass Power Plant is progressing toward the commencement of commercial operations during fiscal 2022 as part of efforts to reduce CO2 emissions and achieve carbon neutrality.
  13. FY2020-Q3RestatedAnnual report

    「The company has worked to expand its business areas, including entering the biomass business and establishing bases for overseas business development, drawing on the construction, maintenance and operation expertise it has developed to date.」

    The company continues to participate in the biomass business, including the construction and operation of the Sakaiminato Biomass Power Plant, while establishing bases for its overseas business.
  14. FY2020-Q2First statedAnnual report

    「At a Board of Directors meeting held on 19 September 2019, the company resolved to construct and operate a woody biomass power plant in Sakaiminato, Tottori Prefecture, through Sakaiminato Energy Power GK, a wholly owned subsidiary. Plant overview: Facility name: Sakaiminato Biomass Power Plant (tentative name); Location: 2-9 and other sites, Showamachi, Sakaiminato, Tottori Prefecture; Site area: approximately 26,000 square metres; Rated output: 24,300 kilowatts; Annual electricity transmitted: approximately 166.32 million kilowatt-hours (annual electricity consumption of approximately 55,000 households); Fuels: palm kernel shells, bark and wood pellets; Construction-related costs: approximately ¥12 billion; Scheduled start of operations: during fiscal 2022.」

    The company resolved to construct and operate a woody biomass power plant in Sakaiminato, Tottori Prefecture, through a wholly owned subsidiary. The plant has rated output of 24,300 kilowatts, annual electricity transmission of approximately 166.32 million kilowatt-hours, construction-related costs of approximately ¥12 billion, and is scheduled to begin operations during fiscal 2022.
Moved together

"Power Generation Facility Construction and LTSA/O&M for New Power Providers and Others" moved the same way as this thread, in the same document, in 8 of its 14 moves.

877666★123456
  1. ★This thread
  2. 1Power Generation Facility Construction and LTSA/O&M for New Power Providers and Others8×
  3. 2Expansion of Renewable Energy-Related Construction7×
  4. 3Overseas expansion through a joint venture in Thailand7×
  5. 4Decommissioning and safety-related work at nuclear power plants6×
  6. 5Facilities Construction Segment’s Fall from Profit to Loss6×
  7. 6Providing high-value-added services through consultative sales and a one-stop approach6×

★ is this thread; numbers match the list above. The number on a line is how many documents both moved the same way in; lines between the other threads count the documents they moved together in too. Threads that move together often sit closer.

When this could move next
Tokyo Energy & Systems's next results are scheduled for 2026-11-05. Read the earnings preview
News
No news is linked to this thread yet. When an article touches it, it will appear here by date.
Construction and Operation of the Sakaiminato Biomass Power Plant | TOKYO ENERGY & SYSTEMS INC. (1945) | Komori