Construction plan for a new self-elevating platform (SEP) multipurpose crane vessel and transfer to a jointly owned subsidiary
First written in FY2020-Q3. 5 of 6 entries say "Advanced", first in FY2020. Latest entry: FY2026.
3 other companies' latest entry also says "Advanced".
- FY2026AdvancedAnnual report
「HLV (heavy-lift foundation installation vessel) (1 vessel) 130,000 73,821 Internal funds and borrowings Scheduled for completion in 2028 CLV (cable-laying vessel) (1 vessel) 34,000 15,151 Internal funds and borrowings Scheduled for completion in 2028」
Construction of the heavy-lift foundation installation vessel and cable-laying vessel is progressing, with payments made to date updated to ¥73.821 billion and ¥15.151 billion, respectively. - FY2025AdvancedAnnual report
「During the consolidated fiscal year, work began on a major conversion of the foreign-flagged SEP vessel Sea Challenger to a 1,600-ton lifting capacity, with operations targeted to begin in 2026.」
Regarding the acquisition and conversion of a new SEP vessel, work began to convert Sea Challenger to a 1,600-ton lifting capacity, with operations targeted to begin in 2026. - FY2023AdvancedAnnual report
「1,600-ton SEP multipurpose crane vessel (1 vessel) 18,500 14,612 Internal funds and borrowings Scheduled to enter service in fiscal 2023」
Payments made to date for the 1,600-ton SEP vessel increased from ¥13.927 billion to ¥14.612 billion, and entry into service was scheduled for fiscal 2023. A plan by Japan Offshore Marine to acquire another SEP vessel and modify its crane was also described. - FY2022AdvancedAnnual report
「1,600-ton SEP multipurpose crane vessel (1 vessel) 18,500 13,927 Internal funds and borrowings Scheduled to enter service in March 2023」
Payments made to date for the 1,600-ton SEP vessel increased to ¥13.927 billion, with scheduled entry into service in March 2023 maintained. A plan to acquire another SEP vessel and modify its crane was also added. - FY2020AdvancedAnnual report
「1,600-ton SEP multipurpose crane vessel (1 vessel) 18,500 3,372 Internal funds and borrowings Scheduled for completion in September 2022 Upon completion of construction, the above equipment is scheduled to be transferred to PKY Marine Co., Ltd., a consolidated subsidiary established through a joint investment by KAJIMA CORPORATION and Yorigami Construction Co., Ltd.」
Payments made to date for the 1,600-ton SEP vessel increased to ¥3.372 billion against the planned investment of ¥18.5 billion. The scheduled completion date of September 2022 was maintained, and the planned transfer to PKY Marine after completion was specified. - FY2020-Q3First statedAnnual report
「PENTA-OCEAN CONSTRUCTION CO.,LTD. (Bunkyo-ku, Tokyo) SEP multipurpose crane vessel (1 vessel) 18,500 — Scheduled for completion in September 2022 (Note) 1. The above amount does not include consumption tax, etc. 2. Upon completion of construction, the above equipment is scheduled to be transferred to a consolidated subsidiary to be established through a joint investment by KAJIMA CORPORATION and Yorigami Construction Co., Ltd.」
For the newly finalized construction plan for one SEP multipurpose crane vessel, the company disclosed a planned investment of ¥18.5 billion, no amount paid to date, and scheduled completion in September 2022. Upon completion, the vessel is scheduled to be transferred to a consolidated subsidiary jointly funded by KAJIMA CORPORATION and Yorigami Construction Co., Ltd.