Development of technical training and R&D infrastructure through the Tsukuba Training Center, Inorganic Research Building, etc.
First written in FY2021. 4 of 7 entries say "Advanced", first in FY2022. Latest entry: FY2026.
0 other companies' latest entry also says "Achieved".
- FY2026AchievedAnnual report
「During the consolidated fiscal year, capital investments totaling ¥1,174 million were made. The principal investment was construction costs for the Yashio Plant, which was completed during the fiscal year.」
The Yashio Plant, whose construction had been underway, was completed during the fiscal year, and property, plant and equipment with a carrying amount of ¥3,038 million was recorded as production facilities. - 2026-09-01AchievedGeneral Meetings of Shareholders
「The total amount of capital expenditures made during the consolidated fiscal year was ¥1,174 million. The main expenditure was the construction cost of the Yashio Plant, which was completed during the fiscal year.」
The disclosure regarding the Yashio Plant progressed from describing it as under construction and scheduled for completion to stating that it had been completed during the fiscal year. - FY2025AdvancedAnnual report
「Total capital investment during the consolidated fiscal year was ¥948 million… The principal investment was construction costs for the Yashio Plant, scheduled for completion in the fiscal year ending June 2026.」
Construction of the Yashio Plant is progressing, with a total planned investment of ¥2,480 million, ¥1,530 million already paid and completion scheduled for October 2025. - FY2024AdvancedAnnual report
「During the consolidated fiscal year, capital investments totaling ¥1,075 million were made. The principal investment was construction costs for the Yashio Plant, scheduled for completion in the fiscal year ending June 2026.」
Construction of the Yashio Plant is progressing as part of the development of the technology and materials production platform. The Company disclosed a planned completion in the fiscal year ending June 2026 and a total investment plan of ¥2,380 million. - FY2023AdvancedAnnual report
「Total capital investment during the consolidated fiscal year was ¥1,178 million… The principal investment was construction costs for the Northern Japan Branch building, completed in June 2023.」
The Northern Japan Branch building was completed in June 2023, and ¥1,139 million was invested in domestic construction. Following development of the training and R&D platform, work on the operating sites is progressing. - FY2022AdvancedAnnual report
「During the consolidated fiscal year, capital investments totaling ¥2,286 million were made. The principal investments were construction costs for the Tsukuba Training Center, completed in October 2021; land acquisition and construction costs associated with the relocation of the Northern Japan Branch; and acquisition costs for the Urawa-Kita Warehouse.」
The Tsukuba Training Center planned in the previous fiscal year was completed in October 2021, and investment in domestic construction facilities, including the Northern Japan Branch and Urawa-Kita Warehouse, progressed. Investment plans were also presented for ¥1,290 million at the Northern Japan Branch and ¥2,000 million at the Yashio Plant for the following fiscal year and beyond. - FY2021First statedAnnual report
「During the consolidated fiscal year, capital investments totaling ¥1,336 million were made. The principal investments were construction costs for the Tsukuba Training Center, a facility supporting the Company's Group employees and personnel of partner companies in acquiring repair and reinforcement techniques and receiving practical safety and health training; the Inorganic Materials Research Building, newly constructed within the Repair Engineering Research Institute for the development of inorganic materials; and the Kyoto Branch building. "Repair Engineering Research Institute (Tsukuba, Ibaraki Prefecture)" "Training Center" "819" "506" "January 2021" "October 2021"」
¥1,336 million was invested in domestic construction, including the Tsukuba Training Center, the Inorganic Materials Research Building and the Kyoto Branch building. The Training Center had a total cost of ¥819 million, with ¥506 million already paid, and was scheduled for completion in October 2021.