Logistics Center and Facility Development
First written in FY2016-Q3. 11 of 21 entries say "Advanced", first in FY2016. Latest entry: FY2026-H1.
19 other companies' latest entry also says "Advanced".
- FY2026-H1AdvancedAnnual report
「Our company, Shonan Center, Ebina, Kanagawa Prefecture, Ambient-temperature distribution business, Office and warehouse, ¥5,831 million, Internal funds, November 2025 / Our company, Logistics Center, Koga, Fukuoka Prefecture, Ambient-temperature distribution business, Logistics center site, ¥3,076 million, ¥253 million, Internal funds, December 2025, November 2026」
The Shonan Center was completed in November 2025. A new construction plan was also added for a logistics center site in Koga, Fukuoka Prefecture, with total planned investment of ¥3,076 million and completion scheduled for November 2026. - FY2025-H1AdvancedAnnual report
「The following major new capital investment projects were newly finalized during the interim consolidated accounting period.」
New construction plans were newly finalized for a logistics center site in Mizuho, Nishitama District, Tokyo, with total planned investment of ¥2,393 million, and for a logistics center site in Itami, Hyogo Prefecture, with planned investment of ¥6,518 million. Both will be funded with internal funds, with commencement and completion scheduled for April or May 2025. - FY2024-Q2SoftenedAnnual report
「Among the major new facilities under planning at the end of the previous consolidated fiscal year, the scheduled completion date for the 丹波篠山 Plant of ㈱グリーンウッドファクトリー has been changed from March 2024 to May 2024.」
Scheduled completion of the 丹波篠山 Plant of グリーンウッドファクトリー was postponed from March 2024 to May 2024. - FY2023AdvancedAnnual report
「Our company, New Shonan Center (provisional name), Ebina, Kanagawa Prefecture, Ambient-temperature distribution business, Office and warehouse, ¥5,869 million, —, Internal funds, May 2024, October 2025」
The plan for a new logistics base, the New Shonan Center, was developed with total planned investment of ¥5,869 million, work commencing in May 2024 and completion scheduled for October 2025. - FY2023SoftenedAnnual report
「For the 丹波篠山 Plant of 兵庫興農㈱, newly planned in the previous consolidated fiscal year, the total planned investment has been changed from ¥6,505 million to ¥7,015 million, and the scheduled completion date has been changed from November 2023 to March 2024.」
Planned investment in the 丹波篠山 Plant increased, and scheduled completion was postponed from November 2023 to March 2024. 兵庫興農 changed its corporate name to グリーンウッドファクトリー. - FY2023-Q1AchievedAnnual report
「Our company, Nangoku Center in Kochi, Nangoku, Kochi Prefecture, Ambient-temperature distribution business, Office and warehouse, ¥1,086 million, Internal funds, October 2022」
The office and warehouse of the Nangoku Center in Kochi, which had been under planning, were completed in October 2022. Total investment was ¥1,086 million. - FY2022AdvancedAnnual report
「Total capital investment during the consolidated fiscal year was ¥5,688 million, mainly comprising new plant construction and reconstruction work on offices at our company.」
Annual capital investment of ¥5,688 million was made, and plans to develop logistics and manufacturing bases were updated, including the Nangoku Center in Kochi, scheduled for completion in October 2022, and the 丹波篠山 Plant of 兵庫興農, scheduled for completion in November 2023. - FY2022-Q3SoftenedAnnual report
「The scheduled completion of our company’s Tohoku Branch office, which had been scheduled for June 2022, has been changed to July 2022.」
The scheduled completion of the Tohoku Branch office was postponed by 1 month, from June 2022 to July 2022. - FY2022-Q2DroppedAnnual report
「The plant and manufacturing equipment of 和歌山産業㈱, our consolidated subsidiary, which was under planning at the end of the previous consolidated fiscal year, has been cancelled following a review of the plan.」
The plant and manufacturing equipment plan of 和歌山産業 was cancelled following a review. Overall logistics and facilities development included completion of the Kyoto Third Center. - FY2022-Q1AchievedAnnual report
「マンナ運輸㈱, Kyoto Third Center, Kumiyama, Kuse District, Kyoto Prefecture, Other, Office and warehouse, ¥749 million, Internal funds and borrowings from the filing company, October 2021」
The Kyoto Third Center of マンナ運輸, which was under planning at the end of the previous consolidated fiscal year, was completed in October 2021. Total investment was ¥749 million. - FY2021AdvancedAnnual report
「Total capital investment during the consolidated fiscal year was ¥7,936 million, mainly comprising reconstruction work on offices and warehouses at our company.」
Annual capital investment of ¥7,936 million was made. In addition, plans for the construction or reconstruction of the South Building of Head Office, Shin-Nango Center, Tohoku Branch, Rinku Plant and Kyoto Third Center have been developed and updated. - FY2021-Q3AdvancedAnnual report
「Our company, South Building of Head Office, Nishinomiya, Hyogo Prefecture, Ambient-temperature distribution business, Office, ¥1,180 million, 1, Internal funds, May 2021, October 2022 / マンナ運輸㈱, Kyoto Third Center, Kumiyama, Kuse District, Kyoto Prefecture, Other, Office and warehouse, ¥772 million, ¥258 million, Internal funds and borrowings from the filing company, March 2021, November 2021」
New construction plans for the South Building of Head Office and マンナ運輸’s Kyoto Third Center were finalized. Planned investment amounted to ¥1,180 million and ¥772 million, respectively, with completion scheduled for October 2022 and November 2021. - FY2021-Q2AdvancedAnnual report
「Our company, Shizuoka Branch and Kakegawa Center, Office and warehouse, ¥953 million, Internal funds, February 2021 / Our company, Shinji Branch and Shinji Center, Office and warehouse, ¥2,200 million, Internal funds, March 2021 / Our company, Sendai Center, Office and warehouse, ¥1,032 million, Internal funds, March 2021」
The Shizuoka Branch and Kakegawa Center, Shinji Branch and Shinji Center, and Sendai Center, 3 facilities in total, were completed, advancing the development of logistics and sales bases. - FY2020SoftenedAnnual report
「For the Shizuoka Branch and Kakegawa Center newly planned in the previous consolidated fiscal year, the scheduled completion date has been changed from September 2020 to February 2021.」
The scheduled completion of the Shizuoka Branch and Kakegawa Center was postponed from September 2020 to February 2021. Meanwhile, capital investment in the Shinji Branch, Shinji Center and other facilities is continuing. - FY2019-Q3AdvancedAnnual report
「和歌山産業㈱, Rinku Plant, Higashine, Yamagata Prefecture, Ambient-temperature distribution business, Plant and manufacturing equipment, ¥1,080 million, —, Borrowings from the filing company, July 2019, March 2022」
A new construction plan for 和歌山産業’s Rinku Plant and manufacturing equipment, with a planned total investment of ¥1,080 million, work commencing in July 2019 and completion scheduled for March 2022, funded by borrowings from the filing company, was newly finalized. - FY2019-Q2AdvancedAnnual report
「The Company | Shin-ki Branch | Suma-ku, Kobe | Ambient-temperature distribution business | Office and warehouse | 1,931 | — | Internal funds | March 2020 | February 2021」
A new plan was finalized for the construction of an office and warehouse at the Shin-ki Branch, with a planned total investment of ¥1,931 million, construction starting in March 2020, scheduled for completion in February 2021, and financed with internal funds. - FY2017-Q3AchievedAnnual report
「Of the major facilities planned for construction at the end of the previous consolidated fiscal year, those completed during the cumulative third quarter of the current consolidated fiscal year are as follows.」
The expansion of the Kyoto No. 2 Center building operated by マンナ運輸 was completed in June 2017 at a total investment of ¥535 million. The plan for warehouse and material-handling equipment in Suminoe-ku, Osaka remains in place. - FY2017-Q2RestatedAnnual report
「Compared with the initial plan, the facility investment was changed from logistics center land to warehouse and material-handling equipment, and the financing method was changed from internal funds to internal funds or leases.」
Continuing the plan for warehouse and material-handling equipment in Suminoe-ku, Osaka, with a planned total investment of ¥4,659 million, construction starting in October 2017 and scheduled for completion in December 2018. - FY2017-Q1AdvancedAnnual report
「Compared with the initial plan, the facility investment was changed from logistics center land to warehouse and material-handling equipment, and the financing method was changed from internal funds to internal funds or leases.」
The previously undecided logistics center plan was made concrete as an investment in warehouse and material-handling equipment. The planned total investment is ¥4,659 million, construction is scheduled to start in October 2017 and be completed in December 2018, and the financing method was changed to internal funds or leases. - FY2016AdvancedAnnual report
「マンナ運輸 Co., Ltd. | Kyoto No. 2 Center | Building expansion | 550 | Borrowings from the reporting company | December 2016 | May 2017」
The expansion of the Kyoto No. 2 Center building operated by マンナ運輸 was specified as a ¥550 million investment, starting in December 2016 and scheduled for completion in May 2017. Total capital investment for the current fiscal year was ¥4,953 million, mainly for new logistics center construction and the acquisition of material-handling equipment. - FY2016-Q3First statedAnnual report
「The Company | Wawatatsu Distribution Center | Kitahiroshima, Hokkaido | Ambient-temperature distribution business | Material-handling equipment | 426 | Internal funds | April 2016」
The building, facilities and material-handling equipment at the planned Wawatatsu Distribution Center were completed. The total investment in material-handling equipment was ¥426 million, and completion took place in April 2016.