Tkc (9746) · InitiativeAchieved
Customer Support Center Acquisition Plan
First written in FY2016. 1 of 3 entries say "Advanced", first in FY2017. Latest entry: FY2018-Q2.
3entries
3years
0from disclosures
How it moved
Same theme, other companies
Investment in the Acquisition and Construction of Land and Buildings for Business UseA theme 60 companies write about · 1 as a headwind · 69 as a tailwind
19 other companies' latest entry also says "Achieved".
Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Showing 14 of the 60 companies compared. The sentences above are computed from all 60.Full recordFilings, disclosures and news, newest first
- FY2018-Q2AchievedAnnual report
「On 16 March 2018, the TKC Customer Support Services Building was completed in Kanuma City, Tochigi Prefecture. It has 4 above-ground floors and a total floor area of 4,991.99 m².」
The previous acquisition and construction plan culminated in completion of the Customer Support Services Building. - FY2017AdvancedAnnual report
「TKC Customer Support Center; Kanuma City, Tochigi Prefecture; accounting firm business; office building acquisition; 1,736; 1,092; internal funds; March 2017; March 2018; 4,969 m²」
Construction of the Customer Support Center is under way, with a total planned investment of ¥1,736 million, ¥1,092 million already paid, and completion scheduled for March 2018. - FY2016First statedAnnual report
「Customer Support Center; Kanuma City, Tochigi Prefecture; accounting firm business; office building acquisition; 1,717; 105; internal funds; March 2017; January 2018; 4,969 m²」
Describes an office building acquisition plan funded with ¥1,717 million in internal funds, initiated in March 2017 and scheduled for completion in January 2018.