Advancing the Oma Nuclear Power Project with Safety as the Fundamental Principle

First written in FY2016. 7 of 15 entries say "Softened", first in FY2017-Q2. Latest entry: FY2026.

15entries
11years
2from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseRestatedFY2017-Q3 – FY2017SoftenedFY2019 – FY2021-Q2RestatedFY2021-Q3 – FY2022SoftenedFY2023-Q2 – FY2025-H12016: 220162017: 220172018: 120182019: 220192020: 120202021: 120212022: 220222023: 020232024: 120242025: 020252026: 32026
Same theme, other companies
Advancing safety measures and regulatory compliance for the Oma nuclear power projectA theme 1 companies write about · 0 as a headwind · 1 as a tailwind

No other company in this theme has enough history to compare yet.

Full recordFilings, disclosures and news, newest first
  1. FY2026SoftenedAnnual report

    「We have set a target of commencing the additional safety enhancement construction compiled in the application referred to above as early as possible and completing it in the latter half of 2029. However, in light of the status of the Nuclear Regulation Authority's review and additional responses to the new regulatory standards, achieving the target is difficult.」

    While maintaining the target of completing the work in the latter half of 2029, the company explicitly states that achieving the target will be difficult, weakening the specific outlook for the start and completion dates.
  2. FY2025-H1SoftenedAnnual report

    「We are making every effort as a company to commence the additional safety enhancement construction compiled in the application referred to above as early as possible and complete it in the latter half of 2029.」

    The target for completion remains the latter half of 2029, but the wording has retreated from the specific start timing of 'the latter half of 2024' to 'commence as early as possible.'
  3. FY2023-Q2SoftenedAnnual report

    「As an operator, we cannot prejudge the progress of the conformity review. However, we aim to commence the additional safety enhancement construction compiled in the application referred to above in the latter half of 2024 and complete it in the latter half of 2029.」

    The target timing for the additional safety enhancement construction at the Oma Nuclear Power Station has been pushed back from the previously stated start in the latter half of 2022 and completion in the latter half of 2027 to a start in the latter half of 2024 and completion in the latter half of 2029.
  4. FY2022RestatedAnnual report

    「We will continue to steadily implement the necessary safety measures, aiming to resume full-scale construction work as early as possible.」

    The company has reaffirmed its policy of responding to the conformity review, implementing safety measures, and aiming for an early full-scale resumption of construction work.
  5. FY2021-Q3RestatedAnnual report

    「Going forward, we will respond sincerely and appropriately to the Nuclear Regulation Authority's conformity review and steadily implement the necessary safety measures, making every effort as a company to develop a safe power station. As an operator, we cannot prejudge the progress of the conformity review, but we aim to commence additional safety enhancement construction in the latter half of 2022 and complete it in the latter half of 2027.」

    The company has reconfirmed the same information as in the previous quarter regarding its response to the conformity review, implementation of safety measures, and the target of commencing additional safety enhancement construction in the latter half of 2022 and completing it in the latter half of 2027.
  6. FY2021-Q2SoftenedAnnual report

    「As an operator, we cannot prejudge the progress of the conformity review. However, we aim to commence additional safety enhancement construction in the latter half of 2022 and complete it in the latter half of 2027.」

    The target timing for the additional safety enhancement construction has been pushed back from the previously stated start in the latter half of 2020 and completion in the latter half of 2025 to a start in the latter half of 2022 and completion in the latter half of 2027.
  7. FY2019SoftenedAnnual report

    「Our group is currently responding sincerely and appropriately to the Nuclear Regulation Authority's conformity review and will continue to steadily implement the necessary safety measures, aiming to resume full-scale construction work as early as possible.」

    The company continues to implement safety measures and respond to the conformity review, but now states that its immediate goal is an early full-scale resumption of construction work rather than an early start of operations.
  8. FY2019-Q3RestatedAnnual report

    「Going forward, we will respond sincerely and appropriately to the Nuclear Regulation Authority's conformity review and steadily implement the necessary safety measures, making every effort as a company to develop a safe power station. As an operator, we cannot prejudge the progress of the conformity review, but we aim to commence additional safety enhancement construction in the latter half of 2020 and complete it in the latter half of 2025.」

    The company continues to set out its response to the conformity review, the necessary safety measures, and the target of commencing additional safety enhancement construction in the latter half of 2020 and completing it in the latter half of 2025.
  9. FY2019-Q2SoftenedAnnual report

    「As an operator, we cannot prejudge the progress of the conformity review. However, we aim to commence additional safety enhancement construction in the latter half of 2020 and complete it in the latter half of 2025.」

    The target timing for the additional safety enhancement construction has been pushed back from the previously stated start in the latter half of 2018 and completion in the latter half of 2023 to a start in the latter half of 2020 and completion in the latter half of 2025.
  10. FY2017RestatedAnnual report

    「Our group is currently responding sincerely and appropriately to the Nuclear Regulation Authority's conformity review and will continue to steadily implement the necessary safety measures, making every effort to develop a safe power station and achieve an early start of operations.」

    The company has reaffirmed its policy of responding to the conformity review and advancing the necessary safety measures, with the aim of commencing operations as early as possible while giving top priority to safety.
  11. FY2017-Q3RestatedAnnual report

    「As an operator, we cannot prejudge the progress of the conformity review. However, we aim to commence additional safety enhancement construction in the latter half of 2018 and complete it in the latter half of 2023.」

    The company reiterates the same information as previously stated regarding its response to the conformity review and the target start and completion dates for the additional safety enhancement construction.
  12. FY2017-Q2SoftenedAnnual report

    「As an operator, we cannot prejudge the progress of the conformity review. However, we aim to commence additional safety enhancement construction in the latter half of 2018 and complete it in the latter half of 2023.」

    The target timing for the additional safety enhancement construction has been pushed back from the previously stated start in November 2016 and completion in December 2021 to a start in the latter half of 2018 and completion in the latter half of 2023.
  13. FY2016First statedAnnual report

    「Going forward, our group will respond sincerely and appropriately to the Nuclear Regulation Authority's conformity review and steadily implement the necessary safety measures, making every effort to develop a safe power station and achieve an early start of operations.」

    The company states that it will proceed with the conformity review under the new regulatory standards, earthquake and tsunami countermeasures, severe accident measures, and facilities for responding to specific severe accidents and other events.
Moved together

"Risks of schedule delays and higher construction costs at the Oma Nuclear Power Plant" moved the same way as this thread, in the same document, in 6 of its 15 moves.

632★123
  1. ★This thread
  2. 1Risks of schedule delays and higher construction costs at the Oma Nuclear Power Plant6×
  3. 2Fuel cost risk from coal price fluctuations, transportation disruptions and supplier issues3×
  4. 3Guarantee liabilities and contract guarantee exposure relating to overseas IPPs and related businesses2×

★ is this thread; numbers match the list above. The number on a line is how many documents both moved the same way in; lines between the other threads count the documents they moved together in too. Threads that move together often sit closer.

When this could move next
Electric Power Development's next results are scheduled for 2026-10-30. Read the earnings preview It last moved in the General Meetings of Shareholders of 2026-05-27: "Advanced".
News
No news is linked to this thread yet. When an article touches it, it will appear here by date.
Advancing the Oma Nuclear Power Project with Safety as the Fundamental Principle | Electric Power Development Co.,Ltd. (9513) | Komori