Hokkaido Electric Power Company (9509) · InitiativeSoftened

Renewal of Internal-Combustion Power Generation Equipment at Remote-Island Power Plants

First written in FY2022. 1 of 4 entries say "Raised", first in FY2023. Latest entry: FY2024.

4entries
3years
0from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseFirst statedFY2022RaisedFY2023 – FY2024-Q32022: 120222023: 120232024: 22024
Same theme, other companies
Renewal of Internal-Combustion Power Generation Equipment at Remote-Island Power PlantsA theme 1 companies write about · 0 as a headwind · 1 as a tailwind

No other company in this theme has enough history to compare yet.

Full recordFilings, disclosures and news, newest first
  1. FY2024SoftenedAnnual report

    「Rebun Unit 11 (new installation: internal combustion) 750 July 2025 January 2026」

    The plan for Rebun Unit 11 remains in place, but the schedule was pushed back from the previously announced construction start in March 2025 and operations start in August 2025 to construction start in July 2025 and operations start in January 2026.
  2. FY2024-Q3AdvancedAnnual report

    「Thermal Rebun Unit 10 (new installation: internal combustion) 1,100 July 2023 December 2023」

    Rebun Unit 10 (1,100kW) began operations in December 2023, marking progress on the remote-island power plant equipment upgrade plan. The plan for Rebun Unit 11 remains in place.
  3. FY2023RaisedAnnual report

    「Thermal Rebun Unit 10 (new installation: internal combustion) 1,100 July 2023 December 2023 Thermal Rebun Unit 11 (new installation: internal combustion) 750 March 2025 August 2025」

    The remote-island equipment upgrade plan was expanded to include Rebun Unit 11, with an additional 750kW, while the schedule for Rebun Unit 10 was updated.
  4. FY2022First statedAnnual report

    「Thermal Yagishiri Unit 7 (new installation: internal combustion) 120 June 2022 March 2023 Thermal Okushiri Unit 10 (new installation: internal combustion) 750 May 2022 October 2022 Thermal Rebun Unit 10 (new installation: internal combustion) 1,100 March 2023 August 2023」

    The company first presented a consolidated plan to install a total of 1,970kW of new internal-combustion generating equipment at the remote-island power plants on Yagishiri, Okushiri and Rebun.
Moved together

"Early Restart and Safety Improvements at the Tomari Nuclear Power Station" moved the same way as this thread, in the same document, in 2 of its 4 moves.

2222★1234
  1. ★This thread
  2. 1Early Restart and Safety Improvements at the Tomari Nuclear Power Station2×
  3. 2Fluctuations in Fuel Prices and Foreign Exchange Rates2×
  4. 3Decline in Electricity Sales Volumes Due to Competition, Economic Conditions and Energy Conservation2×
  5. 4Interest-bearing debt and fluctuations in market interest rates2×

★ is this thread; numbers match the list above. The number on a line is how many documents both moved the same way in; lines between the other threads count the documents they moved together in too. Threads that move together often sit closer.

When this could move next
Hokkaido Electric Power Company's next results are scheduled for 2026-10-30. Read the earnings preview
News
No news is linked to this thread yet. When an article touches it, it will appear here by date.
Renewal of Internal-Combustion Power Generation Equipment at Remote-Island Power Plants | Hokkaido Electric Power Company,Incorporated (9509) | Komori