Hokkaido Electric Power Company (9509) · InitiativeRestated
Plan to Retire Onbetsu Units 1 and 2
First written in FY2019-Q3. 2 of 4 entries say "Restated". Latest entry: 2026-10-02.
4entries
8years
0from disclosures
How it moved
Same theme, other companies
Decommissioning of Thermal Power Generation Facilities and Restructuring of the Power Generation SystemA theme 4 companies write about · 11 as a headwind · 0 as a tailwind
1 other company's latest entry also says "Advanced".
Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Full recordFilings, disclosures and news, newest first
- 2026-10-02Advancedwww.nikkei.com
「音別発電所1、2号機(釧路市)を同月末で廃止することも発表した。」
音別1・2号機の廃止計画について、廃止時期未定の状態から、2030年3月末に廃止する具体的な決定へ進んだ。 - FY2026RestatedAnnual report
「Ombetsu Units 1 and 2 (retired) 148,000 (74,000 × 2 units) Undecided」
The plan to retire Ombetsu Units 1 and 2, with total capacity of 148,000 kW, continues, with the retirement date remaining undecided. - FY2019RestatedAnnual report
「Ombetsu Units 1 and 2 (retired) 148,000 (74,000 × 2 units) Undecided」
The plan to retire Ombetsu Units 1 and 2, with total capacity of 148,000 kW, and the status of having no scheduled retirement date continue. - FY2019-Q3First statedAnnual report
「Ombetsu Units 1 and 2 (retired) 148,000 (74,000 × 2 units) Undecided」
A plan to retire Ombetsu Units 1 and 2, with total capacity of 148,000 kW, is disclosed. The scheduled retirement date changed from February 2019 to undecided.