How it moved
ProgressHeldSoftenedWorseFirst statedFY2022AdvancedFY2023 – FY20262022: 120222023: 120232024: 120242025: 020252026: 12026
Same theme, other companies
Hydrogen Energy Market Development and Dedicated Project PromotionA theme 9 companies write about · 0 as a headwind · 9 as a tailwind

The whole theme swung hardest in 2024: 1 of 8 companies on the "Worse" side.

4 other companies' latest entry also says "Advanced".

Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Full recordFilings, disclosures and news, newest first
  1. FY2026AdvancedAnnual report

    「The Company is advancing initiatives toward the social implementation of next-generation energy sources such as hydrogen, ammonia and e-methane, as well as CCUS, and is working to develop a new energy supply chain originating in the Tomakomai and Atsuma areas」

    The scope of the Company's initiatives expanded from research into the operation and maintenance of hydrogen production equipment to the social implementation of next-generation energy sources, including ammonia, e-methane and CCUS, and the development of regional supply chains.
  2. FY2024AdvancedAnnual report

    「In addition, to promote the use of hydrogen, the Company is working to establish operational and maintenance expertise for hydrogen production equipment that began operations in May 2023, and in February 2024 began considering a project to develop a domestically produced green hydrogen supply chain in the western Tomakomai area.」

    In addition to establishing operational and maintenance expertise for the hydrogen production equipment, the Company began considering a project to develop a domestically produced green hydrogen supply chain in the western Tomakomai area in February 2024.
  3. FY2023AdvancedAnnual report

    「To promote the use of hydrogen, the Company is evaluating the performance of hydrogen production equipment using water electrolysis that began operations in Tomakomai in May 2023 as a measure to address surplus renewable energy, while working to establish operation and maintenance technologies for cold regions and advancing various studies toward the realization of a hydrogen society in the future.」

    The hydrogen production equipment began operations in May 2023, and the Company moved to the stage of evaluating its performance as a measure to address surplus renewable energy and establishing operation and maintenance technologies for cold regions.
  4. FY2022First statedAnnual report

    「To promote the use of hydrogen, the Company established the “Hokkaido Hydrogen Business Platform” in July 2021 based on its proposal. In March 2022, a project involving hydrogen production equipment using water electrolysis was selected for a subsidy program by the Agency for Natural Resources and Energy of the Ministry of Economy, Trade and Industry. This equipment is attracting attention as a technology for absorbing fluctuations in the output of renewable energy sources. In cooperation with companies inside and outside Hokkaido, the Company aims to achieve the early development of a hydrogen supply chain and, in the future, to make Hokkaido a pioneer in the use of domestically produced clean hydrogen.」

    The Company identified the development of a hydrogen supply chain as a new priority initiative through the establishment of the Hokkaido Hydrogen Business Platform and the selection of its water-electrolysis hydrogen production equipment project for a subsidy.
Moved together

"Efficiency improvements in equipment maintenance, business operations, and materials and equipment costs" moved the same way as this thread, in the same document, in 3 of its 4 moves.

333322★123456
  1. ★This thread
  2. 1Efficiency improvements in equipment maintenance, business operations, and materials and equipment costs3×
  3. 2Financing through green bonds for renewable energy development3×
  4. 3Talent Development, Technology Transfer and the Advancement of Women3×
  5. 4Achieving CO2 Emissions Reduction Targets3×
  6. 5Early Restart and Safety Improvements at the Tomari Nuclear Power Station2×
  7. 6Improving Earnings and Strengthening the Financial Base2×

★ is this thread; numbers match the list above. The number on a line is how many documents both moved the same way in; lines between the other threads count the documents they moved together in too. Threads that move together often sit closer.

When this could move next
Hokkaido Electric Power Company's next results are scheduled for 2026-10-30. Read the earnings preview
News
No news is linked to this thread yet. When an article touches it, it will appear here by date.