Large-scale development centred on the Umeda 1-chome 1-banchi Project
First written in FY2016. 8 of 13 entries say "Restated". Latest entry: FY2022.
No other company in this theme has enough history to compare yet.
- FY2022AchievedAnnual report
「Overall completion was reached in February 2022, with the Hanshin Department Store's grand opening scheduled for April of the same year.」
The Umeda 1 Chome 1 Banchi Project (Osaka Umeda Twin Towers South) reached overall completion in February 2022. The Hanshin Department Store's grand opening took place in April 2022, after the filing date. - FY2021AdvancedAnnual report
「Regarding the large-scale Umeda 1 Chome 1 Banchi Project (building name: Osaka Umeda Twin Towers South), construction of the Phase II building is progressing as scheduled toward the Hanshin Department Store's grand opening in autumn 2021 and overall completion in spring 2022.」
Following completion of the Phase I building, construction of the Phase II building is progressing as scheduled, formalizing plans for the Hanshin Department Store's grand opening in autumn 2021 and overall completion in spring 2022. - FY2019AdvancedAnnual report
「Regarding the large-scale Umeda 1 Chome 1 Banchi Project (building name: Osaka Umeda Twin Towers South), the Phase I building was completed as scheduled in April 2018. The new Hanshin Department Store partially opened in June, and construction of the Phase II building was started toward overall completion in spring 2022.」
In addition to completion of the Phase I building and the partial opening of the new Hanshin Department Store, construction of the Phase II building was started. Overall completion is scheduled for spring 2022. - FY2019-Q3RestatedAnnual report
「Of the facilities projects planned at the end of the previous consolidated fiscal year, those completed during the first 3 quarters of the current consolidated cumulative period are as follows. Hankyu Railway Co., Ltd. and Hanshin Electric Railway Co., Ltd. 24,603 April 2018 ・Umeda 1 Chome 1 Banchi Project (Phase I building)」
The completion of the Phase I building of the Umeda 1 Chome 1 Banchi Project in April 2018 is reiterated as a completed facilities project. The entire project has not been completed. - FY2019-Q2RestatedAnnual report
「Of the facilities projects planned at the end of the previous consolidated fiscal year, those completed during the first half of the current consolidated fiscal year are as follows. Hankyu Railway Co., Ltd. and Hanshin Electric Railway Co., Ltd. 24,603 April 2018 ・Umeda 1 Chome 1 Banchi Project (Phase I building)」
The completion of the Phase I building of the Umeda 1 Chome 1 Banchi Project in April 2018 is reiterated as a completed facilities project. The entire project has not been completed. - FY2019-Q1AdvancedAnnual report
「Of the facilities projects planned at the end of the previous consolidated fiscal year, those completed during the first quarter of the current consolidated cumulative period are as follows.」
The Phase I building of the Umeda 1 Chome 1 Banchi Project was completed in April 2018. Investment amounted to ¥24,603 million, representing the achievement of a specific milestone for the Phase I building rather than completion of the entire project. - FY2018-Q3RestatedAnnual report
「Advancing large-scale development aimed at medium- to long-term business growth」
Large-scale development continues to be positioned as a major initiative aimed at medium- to long-term business growth. - FY2018-Q2RestatedAnnual report
「Advancing large-scale development aimed at medium- to long-term business growth」
Large-scale development has been reaffirmed as a major initiative aimed at medium- to long-term business growth. - FY2017RestatedAnnual report
「Regarding the large-scale Umeda 1 Chome 1 Banchi Project (the redevelopment plan for Osaka-Jin Building and the New Hankyu Building), new construction work for Phase I is being pursued diligently toward overall completion around spring 2022.」
The overall completion schedule and progress on new construction work for Phase I are stated as before. - FY2017-Q3RestatedAnnual report
「Regarding the large-scale Umeda 1 Chome 1 Banchi Project (the redevelopment plan for Osaka-Jin Building and the New Hankyu Building), new construction work for Phase I is being pursued diligently toward overall completion around spring 2022.」
The overall completion around spring 2022 and progress on new construction work for Phase I are stated as before. - FY2017-Q2RestatedAnnual report
「Regarding the large-scale Umeda 1 Chome 1 Banchi Project (the redevelopment plan for Osaka-Jin Building and the New Hankyu Building), new construction work for Phase I is being pursued diligently toward overall completion around spring 2022.」
The overall completion around spring 2022 and progress on Phase I construction are stated as before. - FY2017-Q1RestatedAnnual report
「Regarding the large-scale Umeda 1 Chome 1 Banchi Project (the redevelopment plan for Osaka-Jin Building and the New Hankyu Building), new construction work for Phase I is being pursued diligently toward overall completion around spring 2022.」
The overall completion schedule and progress on Phase I construction are stated as before, with no new milestone such as completion indicated. - FY2016First statedAnnual report
「The large-scale Umeda 1 Chome 1 Banchi Project (the redevelopment plan for Osaka-Jin Building and the New Hankyu Building) is also being pursued diligently, including the start of new construction work for Phase I in July 2015.」
The facilities plan calls for total planned investment of ¥89,747 million and completion around spring 2022. It also includes the redevelopment of the east wing and renovation of the west wing of the Kobe Hankyu Building, as well as development at Ebie 1 Chome.