Senshukai (8165) · InitiativeAdvanced
Strengthening the EC Platform Through the Development of a New Core System
First written in FY2020. 3 of 6 entries say "Advanced", first in FY2022-Q1. Latest entry: FY2023.
6entries
4years
0from disclosures
How it moved
Same theme, other companies
Development and Enhancement of the Direct-to-Consumer E-commerce Platform SystemA theme 20 companies write about · 1 as a headwind · 19 as a tailwind
The whole theme swung hardest in 2025: 2 of 10 companies on the "Worse" side.
13 other companies' latest entry also says "Advanced".
Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Showing 14 of the 20 companies compared. The sentences above are computed from all 20.Full recordFilings, disclosures and news, newest first
- FY2023AdvancedAnnual report
「デジタル基盤・顧客データの整備が完了し活用フェーズに進行、サイトパフォーマンスを改善、ITコストの見える化を実現、IT戦略の人材補強を実行等、DX戦略実行の為の準備を進めたこと」
基幹システム刷新後のデジタル基盤・顧客データ整備が完了し、活用フェーズへ移行したと説明された。サイト性能改善、ITコストの可視化、人材補強も実施された。 - FY2022MitigatedAnnual report
「現在、システムは安定稼働しており、柔軟性のある新たなシステムを起点にBPRを実行し、お客様の信頼回復に努めるとともに黒字転換を目指しております。」
2022年1月のシステムリプレイスは障害発生後、年度末時点で安定稼働に至り、新システムを起点とするBPRへ移行している。 - FY2022-Q2AdvancedAnnual report
「現在、新しいシステムは概ね平常通り稼働しており、受注状況も回復傾向にあるものの」
基幹システムのリプレイス後に障害が発生したが、現在は概ね平常通り稼働し、受注状況も回復傾向にあるという復旧状況が示された。 - FY2022-Q1AdvancedAnnual report
「当初の予定どおり、本年1月に基幹システムのリプレイスを実行いたしました。」
2022年1月の基幹システムリプレイスが予定どおり実行され、システム刷新は計画段階から実行段階へ進んだ。一方、稼働後に受注・配送トラブルが発生した。 - FY2021-Q3RestatedAnnual report
「本年7月に発表いたしました中期経営計画の推進体制強化と、デジタルを活用した事業変革の前提となる基幹システムの2022年刷新に向けた手数料や人件費等の増加により減収減益となりました。」
デジタルを活用した事業変革の前提となる基幹システムを2022年に刷新する計画が継続しており、その準備に伴う手数料・人件費等の増加が業績要因として現れている。 - FY2020First statedAnnual report
「Construction of a New Core System」
通信販売事業の新基幹システム構築について、投資予定総額47億87百万円、既支払額12億97百万円、2019年2月着手・2022年1月完了予定として開示された。JR東日本への自己株式処分による調達資金も含め、EC基盤の整備を進める計画である。