Itochu Enex (8133) · InitiativeLower operating rates due to scheduled power plant inspectionsLatest General Meetings of Shareholders (2026-05-22): "Advanced"

Expanding Power Generation through the Commissioning of Newly Built Thermal Power Plants

First written in FY2018-Q3. 3 of 7 entries say "Restated". Latest entry: 2026-05-22.

7entries
9years
1from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseRestatedFY2018-Q3 – FY2019-Q3AdvancedFY2021-Q1OtherFY2022-Q22018: 320182019: 120192020: 120202021: 120212022: 020222023: 020232024: 020242025: 020252026: 12026
Same theme, other companies
Development and Capacity Expansion of High-Efficiency, Low-Environmental-Impact Thermal Power GenerationA theme 6 companies write about · 0 as a headwind · 12 as a tailwind

4 other companies' latest entry also says "Advanced".

Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Full recordFilings, disclosures and news, newest first
  1. 2026-05-22AdvancedGeneral Meetings of Shareholders

    「Two LNG gas engine power generation units, with a combined capacity of 15,600 kW, were added and began operating in December 2025.」

    The addition and start of operation of power generation equipment are presented as results, together with its use to increase the power generation ratio and maintain supply-demand balance.
  2. FY2022-Q2Lower operating rates due to scheduled power plant inspectionsAnnual report

    「Profit from operating activities was ¥3.101 billion, down 9.4% year on year. This was mainly due to lower heat demand this summer and lower operating rates resulting from scheduled power plant inspections.」

    Lower operating rates due to scheduled power plant inspections were cited as a factor behind the decline in profit from operating activities in the electricity and utilities business.
  3. FY2021-Q1AdvancedAnnual report

    「Profit from operating activities was ¥1.472 billion, up 9.0% year on year, and quarterly net profit attributable to owners of the company was ¥1.111 billion, up 24.1%. This was mainly because major scheduled repairs in the power generation business, which had been carried out in the previous fiscal year, were completed, resulting in higher operating rates in the current fiscal year.」

    After the major scheduled repairs were completed, power generation facility operating rates increased, and profit from operating activities and net profit in the electricity and utilities business exceeded the year-earlier period.
  4. FY2019-Q3RestatedAnnual report

    「In the power generation business, total power generation exceeded the level in the same period of the previous year due to the operation of the thermal power plant newly built in October 2017, but earnings fell below the previous year's level due to soaring fuel costs and other factors.」

    Reconfirming that total power generation exceeded the year-earlier period due to the operation of the newly built thermal power plant.
  5. FY2019-Q2RestatedAnnual report

    「In the power generation business, total power generation and profit and loss both exceeded the year-earlier period due to the operation of the newly built thermal power plant, which began operations last October.」

    Reconfirming that total power generation and profit and loss exceeded the year-earlier period due to the operation of the newly built thermal power plant.
  6. FY2019-Q1RestatedAnnual report

    「The newly built thermal power plant, which began operations last October, was in operation and total power generation exceeded the year-earlier period. Profit and loss also exceeded the year-earlier period.」

    Reconfirming that the newly built thermal power plant began operations and that total power generation and profit and loss exceeded the year-earlier period.
  7. FY2018-Q3First statedAnnual report

    「Meanwhile, in the power generation business, total power generation exceeded the level in the same period of the previous year after the thermal power plant newly built in October last year began operating, but earnings fell below the previous year's level as raw material costs continued to rise.」

    The company has for the first time described operating results showing that the newly built thermal power plant began operations and total power generation exceeded the year-earlier period.
Moved together

None of this company's other threads moved the same way in the same document twice or more.

When this could move next
Itochu Enex's next results are scheduled for 2026-10-30. Read the earnings preview It last moved in the General Meetings of Shareholders of 2026-05-22: "Advanced".