Development of the New Tokyo Head Office and Kobe Research Facility
First written in FY2025. 1 of 2 entries say "Advanced", first in FY2026. Latest entry: FY2026.
2entries
2years
0from disclosures
How it moved
Same theme, other companies
Rebuilding of the New Tokyo Headquarters and development of the Kobe research facilityA theme 1 companies write about · 0 as a headwind · 1 as a tailwind
No other company in this theme has enough history to compare yet.
Full recordFilings, disclosures and news, newest first
- FY2026AdvancedAnnual report
「New Tokyo headquarters: total cost ¥21,279 million, amount paid to date ¥12,036 million, construction started January 2024, completion October 2026 / Kobe Port Island research facility: amount paid to date ¥1,260 million, construction started March 2026, completion in FY2028」
The rebuilding of the new Tokyo headquarters is progressing toward its scheduled completion in October 2026, with a total cost of ¥21,279 million, while plans for the Kobe research facility have taken concrete shape, with completion scheduled for FY2028. - FY2025First statedAnnual report
「New Tokyo headquarters (Chuo-ku, Tokyo): total ¥21,227 million, construction start January 2024, completion autumn 2026 / Kobe Port Island research facility (Kobe, Hyogo): amount paid to date ¥1,188 million, construction start FY2026, completion FY2028」
The Company described plans to rebuild the new Tokyo headquarters and develop the Kobe Port Island research facility. The new Tokyo headquarters is scheduled for completion in autumn 2026, and the research facility in FY2028.