Strengthening Storage Capacity and Supply Stability Through Expansion of the Kyushu Distribution Center
First written in FY2020. 2 of 4 entries say "Advanced", first in FY2021-Q1. Latest entry: FY2021-Q3.
10 other companies' latest entry also says "Advanced".
- FY2021-Q3AdvancedAnnual report
「In addition, to address expected future demand growth and ensure a stable supply of products, we will expand the Chubu Distribution Center (scheduled for completion in September 2021; total floor area: 27,575 m²), adjoining the existing logistics facility, in addition to the Kyushu Distribution Center (completed in September 2020; total floor area: 3,554 m²) and the Fukuyama Distribution Center (scheduled for completion in November 2020; total floor area: 23,722 m²).」
The expansions of the Kyushu and Fukuyama Distribution Centers were completed, while the Chubu Distribution Center plan continues, with completion scheduled for September 2021. - FY2021-Q2Kyushu Distribution Center completed; Chubu plan updatedAnnual report
「In addition, to address expected future demand growth and ensure a stable supply of products, we will expand the Fukuyama Distribution Center (scheduled for completion in November 2020; total floor area: 23,722 m²) and the Chubu Distribution Center (scheduled for completion in September 2021; total floor area: 27,575 m²), adjoining the existing logistics facilities, in addition to the Kyushu Distribution Center (completed in September 2020; total floor area: 3,554 m²).」
The expansion of the Kyushu Distribution Center was completed in September 2020. Completion of the Fukuyama Distribution Center is scheduled for November 2020 and that of the Chubu Distribution Center for September 2021. - FY2021-Q1AdvancedAnnual report
「In addition, to address expected future demand growth and ensure a stable supply of products, we will expand the Kyushu Distribution Center (scheduled for completion in September 2020; total floor area: 3,554 m²), the Fukuyama Distribution Center (scheduled for completion in November 2020; total floor area: 23,722 m²) and the Chubu Distribution Center (scheduled for completion in July 2021; total floor area: 27,551 m²), each adjoining the existing logistics facility. In addition, we plan to install a sorter system at the Chubu Distribution Center for automated sorting according to the product delivery area, further strengthening our logistics network.」
The expansion plans for the 3 distribution centers in Kyushu, Fukuyama and Chubu were reconfirmed, and the plan to install an automated sorting system at the Chubu Distribution Center was added. - FY2020First statedAnnual report
「In addition, to address expected future demand growth and ensure a stable supply of products, we will expand the Kyushu Distribution Center (scheduled for completion in September 2020; total floor area: 3,554 m²), the Fukuyama Distribution Center (scheduled for completion in November 2020; total floor area: 23,722 m²) and the Chubu Distribution Center (scheduled for completion in July 2021; total floor area: 27,551 m²), each adjoining the existing logistics facility.」
The expansion plan for the Kyushu Distribution Center, with completion scheduled for September 2020 and a total floor area of 3,554 m², was first listed as a separate theme.