Kyodo Printing (7914) · InitiativeRecognition of head-office relocation expenses

Rebuilding the head office and constructing a new head office

First written in FY2018-Q2. 6 of 10 entries say "Advanced", first in FY2018-Q3. Latest entry: FY2023-Q2.

10entries
6years
0from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseAdvancedFY2018-Q3 – FY2019AdvancedFY2020 – FY20222017: 12018: 220182019: 220192020: 120202021: 220212022: 22022
Same theme, other companies
Reconstruction of the Former Head Office BuildingA theme 24 companies write about · 0 as a headwind · 24 as a tailwind

The whole theme swung hardest in 2026: 1 of 6 companies on the "Worse" side.

0 other companies' latest entry also says "Other".

Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Showing 14 of the 24 companies compared. The sentences above are computed from all 24.
Full recordFilings, disclosures and news, newest first
  1. FY2023-Q2Recognition of head-office relocation expensesAnnual report

    「As the Company recorded ¥175 million in gains on the sale of investment securities as extraordinary income, ¥185 million in losses on disposal of property, plant and equipment and ¥170 million in head office relocation costs as extraordinary losses, among other items,」

    In connection with the relocation to the new head office building completed in March 2022, the Company recorded ¥170 million in head office relocation costs and ¥185 million in losses on disposal of property, plant and equipment.
  2. FY2022AchievedAnnual report

    「March 2022 The new head office building was completed at the head office location (Bunkyo-ku, Tokyo).」

    The planned new head office building was completed in March 2022, bringing the rebuilding plan to the completion stage.
  3. FY2022-Q2AdvancedAnnual report

    「This was mainly because construction in progress increased by ¥2.994 billion due to construction of the new head office building, while investment securities increased by ¥1.836 billion, and cash and deposits decreased by ¥3.385 billion and notes and accounts receivable–trade and contract assets decreased by ¥2.477 billion.」

    The Company stated that construction in progress increased by ¥2.994 billion in connection with construction of the new head office building, reflecting construction progress in the asset balance.
  4. FY2021AdvancedAnnual report

    「Head office Head office (Bunkyo-ku, Tokyo) Company-wide New head office building 12,401 6,203 Internal funds, borrowings and other sources March 2020 March 2022」

    Progress on the new head office building plan was disclosed as follows: after construction began in March 2020, the amount already paid had increased to ¥6.203 billion, against a total planned investment of ¥12.401 billion, with completion scheduled for March 2022.
  5. FY2020AdvancedAnnual report

    「New head office building 12,401 1,861 Internal funds, borrowings and other sources March 2020 March 2022」

    Progress on the new head office building plan was reported as follows: construction began in March 2020, the total planned investment was ¥12.401 billion, ¥1.861 billion had already been paid, and completion was scheduled for March 2022. The completion date was also changed from the previous schedule of June 2022 to March 2022.
  6. FY2020-Q2Reversal of the provision related to the head office redevelopmentAnnual report

    「As the Company recorded ¥615 million in gains on the sale of investment securities as extraordinary income, ¥585 million in reversals of the provision for dismantling costs for property, plant and equipment associated with the head office redevelopment as extraordinary income, and ¥588 million in provision expenses for environmental measures as extraordinary losses, among other items, quarterly net income attributable to owners of the parent was ¥397 million, up 446.7% year on year.」

    The Company recorded a ¥585 million reversal of the provision for dismantling costs for property, plant and equipment associated with the head office redevelopment as extraordinary income.
  7. FY2019AdvancedAnnual report

    「Head office New head office building 14,260 Internal funds, borrowings and other sources February 2020 June 2022」

    The new head office building plan shows a planned investment of ¥14.26 billion, construction starting in February 2020, scheduled completion in June 2022, and funding through internal funds, borrowings and other sources as a capital expenditure plan.
  8. FY2018AdvancedAnnual report

    「Head office (Bunkyo-ku, Tokyo) Company-wide New head office building 14,260 Internal funds, borrowings and other sources February 2020 June 2022」

    The head office rebuilding plan has been specified as a capital expenditure plan, with a total planned investment of ¥14.26 billion, a start date, scheduled completion in June 2022 and a funding method.
  9. FY2018-Q3AdvancedAnnual report

    「The outline of the plan to construct a new head office building is as follows: building area, approximately 5,400 m²; total floor area, approximately 33,000 m²; 7 floors above ground; use, offices; completion, March 2022; total project cost, approximately ¥14.0 billion; funding, internal funds, borrowings and other sources.」

    The plan has become more specific, covering the building area, total floor area, number of floors, completion date, total project cost and funding method, following the resolution to rebuild and the presentation of the scheduled completion date in the second quarter.
  10. FY2018-Q2First statedAnnual report

    「During the six months ended, the company recorded an impairment loss of ¥1.441 billion on buildings and other assets at the head office and Koishikawa Plant following the resolution to rebuild the head office. As of the filing date, details of the new head office had not been determined, but completion was scheduled for March 2022.」

    The company resolved to rebuild the head office and recorded an impairment loss on the existing head office and other assets. Although details of the new head office had not been determined, completion was scheduled for March 2022.
Moved together

"Digital content distribution and short-run printing" moved the same way as this thread, in the same document, in 4 of its 10 moves.

444333★123456
  1. ★This thread
  2. 1Digital content distribution and short-run printing4×
  3. 2New product development and cultivation of new customers and markets4×
  4. 3Servitisation of printing-related operations4×
  5. 4Expansion of the tube and flexible packaging businesses3×
  6. 5Expanding orders for BPO, data printing and IC cards3×
  7. 6Decline in orders for My Number-related BPO services and a lack of new projects3×

★ is this thread; numbers match the list above. The number on a line is how many documents both moved the same way in; lines between the other threads count the documents they moved together in too. Threads that move together often sit closer.

When this could move next
Kyodo Printing's next results are scheduled for 2026-11-09. Read the earnings preview
News
No news is linked to this thread yet. When an article touches it, it will appear here by date.