Construction of a new head office building at the Riken Keiki Nara Manufacturing Plant
First written in FY2020-Q3. 2 of 5 entries say "Restated". Latest entry: FY2021.
No other company in this theme has enough history to compare yet.
- FY2021AchievedAnnual report
「Of the above, the new head office building has been completed.」
Construction of the new head office building at the head office plant of 理研計器奈良製作所 has been completed. - FY2021-Q3RestatedAnnual report
「Construction in progress increased by ¥655 million due to payments of commencement deposits and other costs for construction of a new head office building at the consolidated subsidiary 理研計器奈良製作所.」
For construction of the new head office building at the head office plant of 理研計器奈良製作所, payments of commencement deposits and other costs continue to be reflected as an increase in construction in progress. - FY2021-Q2AdvancedAnnual report
「Construction in progress increased by ¥655 million due to payments of commencement deposits and other costs for construction of a new head office building at the consolidated subsidiary 理研計器奈良製作所.」
For construction of the new head office building at the head office plant of 理研計器奈良製作所, payments of commencement deposits and other costs have progressed and are reflected as an increase in construction in progress. - FY2020RestatedAnnual report
「㈱理研計器奈良製作所 Head office plant (Sakurai, Nara Prefecture) New head office building Total planned investment: ¥1,310.000 million Internal funds Start: January 2020 Completion: June 2021」
The construction plan for a new head office building at the head office plant of 理研計器奈良製作所 remains ongoing. Total planned investment is ¥1,310.00 million, with completion scheduled for June 2021. - FY2020-Q3First statedAnnual report
「㈱理研計器奈良製作所 Head office plant (Sakurai, Nara Prefecture) New head office building Total planned investment: ¥1,310.000 million Internal funds Start: January 2020 Completion: June 2021」
The company newly disclosed a capital investment plan to construct a new head office building at the head office plant of 理研計器奈良製作所. Total planned investment is ¥1,310.00 million, funded internally, with construction scheduled to begin in January 2020 and be completed in June 2021.