Construction of a New Head Office Building
First written in FY2016. 3 of 10 entries say "Restated". Latest entry: FY2019.
No other company in this theme has enough history to compare yet.
- FY2019Cited as achievedAnnual report
「Buildings and structures increased by ¥203 million following completion of the external works for the new head office building.」
Completion of the external works for the new head office building was reflected in the financial position, reiterating the completion of the remaining construction. - FY2019-Q2AchievedAnnual report
「This was mainly due to an increase of ¥136 million in buildings and structures following completion of the external works for the new head office building, while」
The external works for the new head office building were completed, indicating that the remaining construction under the new head office building plan was finished. - FY2018RestatedAnnual report
「Phase 1 of construction of the new head office building, which began in April 2016, was completed in September 2017. Phase 2, comprising external works including demolition of the old building and parking area improvements, will be carried out, with all work scheduled for completion in September 2018.」
Completion of Phase 1 was confirmed, with Phase 2 covering demolition of the old building and parking area improvements scheduled to continue, and all work scheduled for completion in September 2018. - FY2018-Q3Cited as achievedAnnual report
「This was mainly due to an increase of ¥2,224 million in buildings and structures and a decrease of ¥1,935 million in construction in progress following completion of the new head office building, as well as an increase of ¥1,266 million in investment securities.」
The new head office building, completed in the previous quarter, continued to be reflected in the financial position through an increase in buildings and structures and a decrease in construction in progress. - FY2018-Q2AchievedAnnual report
「This was mainly due to an increase of ¥2,615 million in buildings and structures and a decrease of ¥1,997 million in construction in progress following completion of the new head office building, as well as an increase of ¥862 million in investment securities.」
The new head office building was completed, and the increase in buildings and structures and decrease in construction in progress were recorded accordingly. - FY2017RestatedAnnual report
「New head office building: ¥3,000,000 thousand; amount already paid: ¥1,995,840 thousand; internal funds; commencement: April 2016; completion: September 2018」
Construction of the new head office building is ongoing. The plan calls for total investment of ¥3 billion, approximately ¥1,995.84 million already paid, and completion in September 2018. No new completion milestone was disclosed. - FY2017-Q3AdvancedAnnual report
「This was mainly due to an increase of ¥1,987 million in construction in progress, primarily as a result of payments of the construction commencement deposit and interim payment for the new head office building.」
In addition to the construction commencement deposit, the Company proceeded with payment of the interim amount for the new head office building, increasing construction in progress by ¥1,987 million. No completion was disclosed. - FY2017-Q2RestatedAnnual report
「This was mainly due to an increase of ¥919 million in construction in progress, primarily as a result of payments including the construction commencement deposit for the new head office building.」
Payments including the construction commencement deposit for the new head office building continued. No new milestone, such as completion, was disclosed. - FY2017-Q1AdvancedAnnual report
「This was mainly due to an increase of ¥1,011 million in construction in progress, primarily as a result of the payment of a construction commencement deposit for the new head office building.」
The Company paid a construction commencement deposit for the new head office building, increasing construction in progress by ¥1,011 million. - FY2016First statedAnnual report
「A new head office building is currently under construction due to the ageing of the existing building, and completion is scheduled for September 2017.」
The capital investment plan states a planned investment of ¥3 billion, funded with internal funds, with work commencing in April 2016 and completion scheduled for September 2018.