Increasing development speed through construction of a new production center building and relocation of the Hakodate plant
First written in FY2019-Q2. 4 of 12 entries say "Restated". Latest entry: FY2025.
No other company in this theme has enough history to compare yet.
- FY2025AdvancedAnnual report
「The principal additions during the period were as follows: Buildings—Production Center, fit-out work on the south side of the third floor: ¥148.763 million.」
Fit-out work on the south side of the third floor of the completed Production Center is progressing, adding equipment functions. - FY2021AdvancedAnnual report
「Following the plant's closure due to the relocation of its functions, the company assessed the plant's expected future use and determined that the recoverable amount of the asset would be significantly reduced, resulting in recognition of an impairment loss.」
The Hakodate plant was closed in connection with the relocation of its functions to the Production Center, and an impairment loss of ¥259.578 million was recognized. - FY2021-Q3Cited as achievedAnnual report
「This was mainly due to the completion of the new Kasukabe building, the Production Center, during the second quarter, which increased buildings and structures by ¥3.797 billion while reducing construction in progress by ¥2.799 billion.」
The new Kasukabe building, the Production Center, completed in the second quarter, continues to be reflected in the financial position through its transfer to buildings and structures and the decrease in construction in progress. - FY2021-Q2Cited as achievedAnnual report
「Completion of the new Kasukabe building, the Production Center, increased buildings and structures by ¥3.797 billion, while construction in progress decreased by ¥2.799 billion.」
The new Kasukabe building, the Production Center, completed in the previous quarter, has been reflected in the financial position through its transfer to buildings and structures and the decrease in construction in progress. - FY2021-Q1AchievedAnnual report
「This was mainly due to an increase of ¥3.695 billion in buildings and structures and a decrease of ¥2.515 billion in construction in progress, resulting primarily from completion of the new Kasukabe building, the Production Center.」
The new Kasukabe building, the Production Center, which had been under construction, was completed and reflected in the financial position through its transfer to buildings and structures. - FY2020RestatedAnnual report
「Total capital investment during the consolidated fiscal year was ¥4,182 million, primarily comprising construction costs for the company's Production Center currently under construction, including payments made at the start of construction and interim payments.」
Construction of the Production Center continued, with the majority of total capital investment of ¥4.182 billion allocated to payments made at the start of construction and interim payments. - FY2020-Q3AdvancedAnnual report
「This was mainly due to an increase of ¥2.875 billion in construction in progress, resulting from payments including the initial and interim payments for construction of the new Kasukabe building, the Production Center, and an increase of ¥673 million in investment securities.」
Construction of the new Kasukabe building, the Production Center, progressed with interim payments in addition to the initial payment, increasing construction in progress by ¥2.875 billion. - FY2020-Q2RestatedAnnual report
「This was mainly due to an increase of ¥1.398 billion in construction in progress, resulting from payments including the initial construction payment for the new Kasukabe building, the Production Center.」
Payment of the initial construction fee for the new Production Center was reflected in the company's financial position, increasing construction in progress by ¥1.398 billion. No new milestone, such as completion, is described. - FY2020-Q1AdvancedAnnual report
「This was mainly due to an increase of ¥1.42 billion in construction in progress, resulting from payments including the initial payment for construction of the new Production Center, and an increase of ¥484 million in investment securities.」
An initial construction payment was made for the new Production Center, increasing construction in progress by ¥1.42 billion. - FY2019RestatedAnnual report
「Primarily from a business continuity perspective in the event of a disaster, the company is constructing the Production Center, provisionally named, with a base-isolated structure adjacent to its existing development center in Kasukabe, Saitama Prefecture. Completion is scheduled for June 2020.」
The planned June 2020 completion of the base-isolated Production Center and the partial relocation of the Hakodate plant's functions have been reconfirmed. - FY2019-Q3RestatedAnnual report
「During the nine-month period of the current consolidated fiscal year, the newly confirmed major capital investment plans are as follows.」
The company has restated its plan for the new building of the Production Center, provisionally named, with total planned investment of ¥3.8 billion, funded with internal resources, construction commencing in May 2019 and completion scheduled for June 2020. - FY2019-Q2First statedAnnual report
「The company plans to increase development speed by constructing a new building on space reserved for expansion at the development center in Kasukabe, Saitama Prefecture, and relocating the Esan No. 1 and Esan No. 2 plants, which are part of the Hakodate plant's sensor production facilities, to the new building.」
The company will construct a new building provisionally named the Production Center, with planned investment of approximately ¥3.8 billion, a building area of approximately 2,193 m² and a total floor area of approximately 9,810 m². Construction is scheduled to begin in May 2019 and be completed in June 2020, funded with internal resources.