Development of a Contract Testing and Development Facility by Furukawa Technical Center
First written in FY2020. 2 of 4 entries say "Restated". Latest entry: FY2024.
No other company in this theme has enough history to compare yet.
- FY2024RestatedAnnual report
「Contract testing has also begun at the Furukawa Technical Center, which was built as a future contract testing and development center, and we will use it to gain a detailed understanding of customer needs and link these insights to the development of new products.」
Following its completion, the Furukawa Technical Center began contract testing and is operating as a center for understanding customer needs and developing new products. - FY2021-Q3RestatedAnnual report
「The following major investments in facilities and other items that were under planning at the end of the previous consolidated fiscal year were completed during the nine-month period of the current consolidated fiscal year. Contract testing and development of electric servo motor-type vibration testing machines 640,878 July 2020」
The completion of the Furukawa Technical Center in July 2020 was also confirmed in the facility disclosure for the quarter. - FY2021-Q2AchievedAnnual report
「The following major investments in facilities and other items that were under planning at the end of the previous consolidated fiscal year were completed during the six-month period of the current consolidated fiscal year. Contract testing and development of electric servo motor-type vibration testing machines 640,878 July 2020」
The Furukawa Technical Center was completed in July 2020. Total investment was ¥640.878 million, completing the construction plan for a contract testing and development center for electric servo motor-type vibration testing machines. - FY2020First statedAnnual report
「Contract testing and development of electric servo motor-type vibration testing machines, ¥632.535 million, ¥367.448 million, internal funds, October 2019, September 2020, production capacity, approximately 10%, increase」
A plan was presented to construct the Furukawa Technical Center as a contract testing and development center, with a planned total investment of ¥632.535 million, completion scheduled for September 2020 and an approximately 10% increase in production capacity.