Komori
Other Disclosures7422TOHO LAMAC CO.,LTD.Trading & Wholesale

Notice Regarding the Acquisition of Fixed Assets (Grid-Scale Battery Storage Business)

東邦レマック decided at a meeting of its Board of Directors to acquire fixed assets related to a grid-scale battery storage business in Makubetsu, Hokkaido. The contract is scheduled to be signed in July 2026, and operations are scheduled to commence in January 2027.

Worth reading
59In focus
0–100. This measures how worthwhile something is to read, not how good or bad the company is.
Direction
Improvement
Direction inferred from the company’s description.
Scale
1990
kW (PCS output)
Wording
Conditional
How definitive the wording is.

Announced details

Makubetsu, Hokkaido AC 1,990 kW Battery Storage Facility / Grid-Scale Battery Storage Business
Applicable field (uses covered by this announcement)

Power grid stabilization and expansion of renewable energy adoption

Launch dateJanuary 2027 (scheduled start of operations)
Contract DateJuly 2026 (scheduled)
Relationship between the counterparty and the company
TOHO LAMAC CO.,LTD.7422
Relationship with the Company

No capital, personnel or business relationships requiring disclosure

Counterparty (name not disclosed)

Not disclosed due to a confidentiality agreement. There are no capital, personnel or business relationships with the company requiring disclosure.

Location (as indicated in this announcement)

374-35 and 374-36 Aza Aikawa, Makubetsu, Nakagawa District, Hokkaido

PCS output: 1,990 kW; battery capacity: 8,224 kWh
Impact on Business Performance

The impact on financial results for the fiscal year ending December 2026 is expected to be minor. The company expects the business to contribute to financial results from the fiscal year ending December 2027 onward following the start of operations.

The company does not address Contract Value / Offering price.

Source (materials cited by the company)

Earnings simulation based on market performance

Announced details
ItemDetails
Names of Products / Services CoveredMakubetsu, Hokkaido AC 1,990 kW Battery Storage Facility / Grid-Scale Battery Storage Business
Counterparty overviewNot disclosed due to a confidentiality agreement. There are no capital, personnel or business relationships with the company requiring disclosure.
Relationship with the CompanyNo capital, personnel or business relationships requiring disclosure
Contract DateJuly 2026 (scheduled)
Launch dateJanuary 2027 (scheduled start of operations)
Applicable areaPower grid stabilization and expansion of renewable energy adoption
Location374-35 and 374-36 Aza Aikawa, Makubetsu, Nakagawa District, Hokkaido
Location scalePCS output: 1,990 kW; battery capacity: 8,224 kWh
Impact on Business PerformanceThe impact on financial results for the fiscal year ending December 2026 is expected to be minor. The company expects the business to contribute to financial results from the fiscal year ending December 2027 onward following the start of operations.
SourceEarnings simulation based on market performance
Items this document does not state (8)
CounterpartyContract ValueOffering priceAward/certification nameAwarding / certifying bodyRegistration number and expiry dateQuantitative EffectsUsage history

These are items the company does not state in this document. We do not leave them blank, nor fill them in from other sources or by inference.

The reasons the company gives

The company's own explanation, not something inferred from the numbers.

This is a field in which market growth is expected as a result of efforts to stabilize the power grid and expand the adoption of renewable energy. Development risks are limited because the full grid interconnection application, payment of the construction cost contribution, site acquisition and administrative due diligence have been completed, and the earnings simulation confirmed a certain level of profitability. The company stated that it intends to expand its renewable energy-related business and contribute to enhancing corporate value over the medium to long term.

How to read this page

This is not the documentKomori reads the disclosure the company filed and writes this summary. Figures are as stated by the company and are not audited.
Weight is not a verdictIt measures how much this changes what the company had already told the market. It is not a view on the shares.
Corrections happenIf the company reissues this disclosure, the page is rebuilt from the corrected version and the revision number moves up.
Notice Regarding the Acquisition of Fixed Assets (Grid-Scale Battery Storage Business) | TOHO LAMAC CO.,LTD. (7422) timely disclosure | Komori