Announced details
Power grid stabilization and expansion of renewable energy adoption
No capital, personnel or business relationships requiring disclosure
Not disclosed due to a confidentiality agreement. There are no capital, personnel or business relationships with the company requiring disclosure.
374-35 and 374-36 Aza Aikawa, Makubetsu, Nakagawa District, Hokkaido
The impact on financial results for the fiscal year ending December 2026 is expected to be minor. The company expects the business to contribute to financial results from the fiscal year ending December 2027 onward following the start of operations.
The company does not address Contract Value / Offering price.
Earnings simulation based on market performance
| Item | Details |
|---|---|
| Names of Products / Services Covered | Makubetsu, Hokkaido AC 1,990 kW Battery Storage Facility / Grid-Scale Battery Storage Business |
| Counterparty overview | Not disclosed due to a confidentiality agreement. There are no capital, personnel or business relationships with the company requiring disclosure. |
| Relationship with the Company | No capital, personnel or business relationships requiring disclosure |
| Contract Date | July 2026 (scheduled) |
| Launch date | January 2027 (scheduled start of operations) |
| Applicable area | Power grid stabilization and expansion of renewable energy adoption |
| Location | 374-35 and 374-36 Aza Aikawa, Makubetsu, Nakagawa District, Hokkaido |
| Location scale | PCS output: 1,990 kW; battery capacity: 8,224 kWh |
| Impact on Business Performance | The impact on financial results for the fiscal year ending December 2026 is expected to be minor. The company expects the business to contribute to financial results from the fiscal year ending December 2027 onward following the start of operations. |
| Source | Earnings simulation based on market performance |
Items this document does not state (8)
These are items the company does not state in this document. We do not leave them blank, nor fill them in from other sources or by inference.
The reasons the company gives
The company's own explanation, not something inferred from the numbers.This is a field in which market growth is expected as a result of efforts to stabilize the power grid and expand the adoption of renewable energy. Development risks are limited because the full grid interconnection application, payment of the construction cost contribution, site acquisition and administrative due diligence have been completed, and the earnings simulation confirmed a certain level of profitability. The company stated that it intends to expand its renewable energy-related business and contribute to enhancing corporate value over the medium to long term.