Construction of the Kyushu Financial Group headquarters building
First written in FY2019. 1 of 3 entries say "Softened", first in FY2020. Latest entry: FY2022-Q3.
No other company in this theme has enough history to compare yet.
- FY2022-Q3AchievedAnnual report
「The "Kyushu Financial Group Head Office Building," which was under planning at the end of the previous consolidated fiscal year, opened on 6 December 2021.」
Following changes to construction costs and the scheduled completion date after construction began, the Kyushu Financial Group Head Office Building opened on 6 December 2021. - FY2020SoftenedAnnual report
「To further leverage the group's collective capabilities, we began construction of the "Kyushu Financial Group Head Office Building (provisional name)" in April 2019. Construction costs were ¥9,741 million, financed with internal funds and borrowings from Higo Bank and Kagoshima Bank, and completion was scheduled for June 2021.」
Construction of the head office building had begun, while construction costs changed from ¥8,011 million to ¥9,741 million and the scheduled completion date changed from January 2021 to June 2021. - FY2019First statedAnnual report
「To further leverage the group's collective capabilities, we began construction of the "Kyushu Financial Group Head Office Building (provisional name)" in April 2019. Construction costs were ¥8,011 million, financed with internal funds and borrowings from Higo Bank and Kagoshima Bank, and completion was scheduled for January 2021.」
Construction of the head office building began to consolidate head office functions, improve productivity and help ensure regional safety in the event of a disaster. Construction costs were specified as ¥8,011 million, with completion scheduled for January 2021.