Natural Disaster and Damage Risks for Renewable Energy Facilities
First written in FY2022. 5 of 9 entries say "Materialised", first in FY2022. Latest entry: 2026-10-15.
1 other company's latest entry also says "Materialised".
- FY2025MitigatedAnnual report
「Business interruption compensation for the period during which generation was suspended was received in January 2025 and recorded during the fourth-quarter consolidated accounting period.」
Following the cable-cutting damage at the Tochigi Prefecture power plant, restoration work was completed and business interruption compensation was received. Measures using insurance and compensation against natural disaster and theft risks progressed. - FY2025-H1MitigatedAnnual report
「Restoration work for the damage caused by the cutting of part of the electrical cables at Akuto Solar Park, a power generation plant in Tochigi Prefecture owned and managed by our group, was completed in early August 2024.」
Regarding the cable-cutting damage in February 2024, restoration work was completed in early August 2024. Business interruption compensation for the period during which generation was suspended has not yet been received and procedures are under way, while measures including the use of a security company, police patrols and additional security sensors have been implemented. - FY2024MaterialisedAnnual report
「In February 2024, part of the electrical cables at Akuto Solar Park, a power generation plant in Tochigi Prefecture owned and managed by our group, was cut, causing damage.」
Following the theft in March 2023, cable-cutting damage recurred in February 2024, reducing generation capacity by approximately half. We recorded restoration costs of ¥13 million as an extraordinary loss and are considering additional measures. - FY2024-Q2MitigatedAnnual report
「Part of the cables at a power generation plant owned by our group in Tochigi Prefecture was stolen in March 2023. Restoration work was completed during the second-quarter consolidated accounting period, and we have also received insurance proceeds covering the restoration costs and business interruption compensation.」
Following the cable theft at the Tochigi Prefecture power plant, restoration work was completed, and insurance proceeds covering restoration costs and business interruption compensation were received. - FY2024-Q1MaterialisedAnnual report
「In March 2023, part of the cables at a power generation plant owned by our group in Tochigi Prefecture was stolen.」
Part of the cables at an owned power generation plant was stolen, and we plan to file insurance claims for restoration work, the associated costs and business interruption compensation. - FY2022MaterialisedAnnual report
「This represents our share of the loss determined in March 2022 in connection with damage caused by a slope collapse at a solar power generation facility in Nahari, Kochi Prefecture, for which we provide maintenance and other services.」
A slope collapse occurred at a solar power generation facility, and we recorded our share of the burden, ¥11 million, as a loss from a natural disaster.