Construction of New Electrical Component Manufacturing Facilities at a Guangdong Subsidiary
First written in FY2019-Q3. 1 of 4 entries say "Raised", first in FY2021-Q3. Latest entry: FY2022.
No other company in this theme has enough history to compare yet.
- FY2022AdvancedAnnual report
「三井高科技(広東)有限公司 (Dongguan, People's Republic of China) Electrical component manufacturing facilities Total ¥4.851 billion Construction in progress ¥2.105 billion」
For the Guangdong subsidiary, the carrying amount of electrical component manufacturing facilities was ¥4.851 billion, including ¥2.105 billion in construction in progress, indicating that facility development was continuing. - FY2021SoftenedAnnual report
「三井高科技(広東)有限公司 People's Republic of China Dongguan Electrical components Electrical component manufacturing facilities 2,831 — Internal funds and borrowings February 2021 December 2022 25%」
The Guangdong subsidiary's plan changed from a 200% increase in capacity, a total investment of ¥3.228 billion and scheduled completion in April 2022 to a 25% increase in capacity, a total investment of ¥2.831 billion and scheduled completion in December 2022. - FY2021-Q3RaisedAnnual report
「三井高科技(広東)有限公司 People's Republic of China Dongguan Electrical components Electrical component manufacturing facilities 3,228 1,054 Internal funds and borrowings May 2020 April 2022 200%」
The capital investment plan at the Guangdong subsidiary increased to a total of ¥3.228 billion, with ¥1.054 billion already paid and post-completion capacity expected to increase by 200%. Completion was scheduled for April 2022. - FY2019-Q3First statedAnnual report
「三井高科技(広東)有限公司 Dongguan, People's Republic of China Electrical components Buildings and electrical component manufacturing facilities 1,200 - Internal funds and borrowings January 2019 December 2019 New construction」
A new plan was disclosed to construct buildings and manufacturing facilities for electrical components at the Guangdong subsidiary in Dongguan for a total of ¥1.2 billion. Construction was scheduled to begin in January 2019 and be completed in December 2019, funded by internal funds and borrowings.